Fortuna Silver Mines Inc
TSX:FVI

Watchlist Manager
Fortuna Silver Mines Inc Logo
Fortuna Silver Mines Inc
TSX:FVI
Watchlist
Price: 6.4 CAD 2.07% Market Closed
Market Cap: 2B CAD
Have any thoughts about
Fortuna Silver Mines Inc?
Write Note

Earnings Call Transcript

Earnings Call Transcript
2018-Q4

from 0
Operator

Good day, ladies and gentlemen, and thank you for joining us for the Fortuna Silver Mines' Fourth Quarter and Full Year 2018 Financial and Operational Results Conference Call. As a reminder, today's meeting is being recorded. [Operator Instructions]And now to get it started with opening remarks and introductions, I am pleased to turn the floor to Investor Relations Manager, Mr. Carlos Baca. Mr. Baca, please go ahead sir.

C
Carlos Baca
Investor Relations Manager

Thank you, Jim. Good morning, ladies and gentlemen. I would like to welcome you all to Fortuna Silver Mines and to our fourth quarter and full year 2018 financial and operations results call. Today, we'll be using a webcast presentation, which will be controlled by us. You can download the presentation at our website, www.fortunasilver.com. Please click on the Investors tab, then click on the Financials tab and under Q4 2018, click on Earnings Call Webcast.Jorge Alberto Ganoza, President, CEO and Director; and Luis Dario Ganoza, CFO, will be hosting the call from Salta, Argentina.Before I turn over the call to Jorge, I would like to indicate that this earnings call contains forward-looking information that is based on the company's current expectations, estimates and beliefs. This forward-looking information is subject to a number of risks, uncertainties and other factors. Actual results could differ materially from a conclusion, forecast or projection in the forward-looking information. Certain material factors or assumptions were applied in drawing a conclusion or making a forecast or projection as reflected in the forward-looking information.Additional information about the material factors that could cause actual results to differ materially from the conclusion, forecast or projection in the forward-looking information and the material factors or assumptions that were applied in drawing a conclusion or making a forecast or projection as reflected in the forward-looking information is contained in the company's Annual Information Form and MD&A, which are publicly available on SEDAR.The company assumes no obligation to update such forward-looking information in the future, except as required by law.I would now like to turn the call over to Jorge Alberto Ganoza, President, CEO and Co-Founder of Fortuna.

J
Jorge A. Ganoza Durant
President, CEO & Director

Thank you, Carlos, and good morning to all. I'll give you a brief introduction to our year-end results and progress at our Lindero Gold Project in Argentina and then turn the call over to Luis, who will take you through the financial statements. After that, we will open the call for questions and answers.In Slide 4 of the presentation, during 2018, we carried our business with mining operations in Peru and Mexico, where our San Jose mine runs among the 14th largest primary silver producers in the world. We're in construction of our 3rd mine in the province of Salta, Argentina. Apart from Brownfields exploration at our mines and projects, we're currently in exploration for new silver and gold deposits in Mexico, Argentina and Serbia. Some of these initiatives are carried via strategic investments and joint ventures with junior explorers like Prospero Silver and Medgold. Important to mention is our consistent focus on sustainable low-cost growth and maintaining a high-margin business.Under the 2018 highlights on Slide 5, we pride ourselves of the strong margins of our business. Our adjusted EBITDA for the year is $114 million, representing a robust 43% margin over sales. Our margin on mine operating income is 37%. Our free cash flow from ongoing operations before Lindero investment is a strong $55 million. Liquidity available stands at $243 million, including our available credit facilities, with a modest debt-to-EBITDA ratio of 0.7 as of year-end.Our Lindero project has 40% advanced towards completion, where 91% of direct capital cost has been committed. Remaining construction capital to completion is $172 million. On February 14, we issued a press release informing we received a resolution from the Federal Environmental Protection Agency of Mexico indicating there is no contamination of soil as a result of the overflow of a rain containment pond at the San Jose mines tailings facility -- a dry stack facility back in October.Moving on to Slide 6. Our mine team delivered another consistent year of excellent performance with silver and gold production 7% and 12% above guidance. Measured against the previous year, silver was up 5% and gold down 4%.Slide 7. Precious metals accounted for 72% of the $263 million in sales for the year. Silver is a precious metal with the largest contribution to sales at 48%. Average realized silver price for the year was $15.70 per ounce and $1,273 per ounce for gold. This is 8% lower for silver and 1% higher for gold when compared to 2017 realized prices.Comparing against 2017, our sales were down 2%, EBITDA was down 7% and adjusted net income down 21%. The drop in net income is explained by marginally lower sales, 4% higher cost of sales and 5% higher selling and G&A. The increase in G&A is mainly related to expanded capabilities in key areas to meet demands of our growing business. These areas include Mexican business administration, technical services, health, safety, environment and legal.Slide 9. All-in sustaining cost reported as core product came in at $10.60 or 11% below budget and guidance. The San Jose mine reported a low $9 per ounce of silver and Caylloma $11.70. San Jose all-in sustaining cost was 11% lower against the previous year, explained by lower investments in plant infrastructure and higher metal produced.Slide 10. We recorded capital expenditures of $113.8 million for the year. The breakdown of this, $8.6 million in Brownfields exploration, $24 million in sustaining capital at our mines, 3.6% in Greenfields exploration and $77.5 million at Lindero.Slide 11. The pyramid in Slide 11 presents our asset portfolio. Here, the biggest value catalyst for the company over the next 12 months is the development of Lindero into a third producing mine. Lindero is strategic to the company at various levels: One, it is a mine with gold reserves for 13 years of operations; two, the production profile offers the opportunity for a quick payback in the initial years at the highest grade portion of the deposit occurs on surface; three, projected EBITDA margin above 40% is consistent with the portfolio strategy; four, immediate exploration opportunities to add gold ounces within the Lindero porphyry system and the nearby gold mineralized Arizaro porphyry are relevant and important to us. Once Lindero is in operation, we will be in a position to divulge annual EBITDA.Slide 12. For construction scheduled for Lindero captures a difficulties faced with the start of activities after the break of Christmas holidays. Start of construction in January and particularly in early February were severely hampered by abnormal rainfall over segments of the access road, some 100 kilometers and 150 kilometers from the project, which limited heavy truck transit and supply of personnel for multiple days.Since the beginning of March, we are back to project pace with approximately 900 people on site and construction advancing on all key fronts. We plan to initiate commissioning in Q4 and ramp up the project of -- ramp up the project over year-end and into Q1 2019.On Slide 13, we have committed approximately 91% of the project's direct capital cost and had $172 million in construction CapEx remaining to completion, with 40% of the project advanced. Our estimate for total construction CapEx is $295 million or 20% increase over our feasibility budget. The $295 million figure carries provisions for the extension in our schedule, contractor standby claims, added provisions for road maintenance for next year and $17 million in contingencies. Although no one likes to see any deviations from budgets and guidance, we are -- we view our costs under control considering we're leaving behind the period of greater uncertainty in the construction. Over 1.2 million cubic meters in excavations for leach platforms and foundations are 90% to 95% concluded. Massive excavations are always an area of risk for estimations and predictions and is basically done. Initial delays on camp availability are over since last year. We have no limitations for contractor mobilization, and all major contractors are on site performing in line with our construction plan to date. Procurement and expediting of equipment and materials is also in line with project schedule.Next, we have a few slides with photo gallery. On Slide 14, in this slide, we show the advance on leach pad and solution pond construction. As you can appreciate here, site preparations are basically concluded and the main tasks now are liner installation and placement of forward liner.On Slide 15, at the crushing site, all foundation excavations are 95% concluded and our civil contractor is placing concrete for foundations and building retention walls working in parallel in the areas of primary, secondary and tertiary crushing and agglomeration.Slide 16. This slide shows progress on the ADR and SART areas. On Slide 17, Slide 17 presents a view of the camp facility. The mine will be run with an owner-operated mine fleet. The fleet is made up of 6 100 ton trucks, 2 wheel loaders, 1 crawler, 2 449 dozers, 2 blast hole drill rigs and other ancillary equipment. The entire fleet is on site, operational. And as part of our readiness plan, we have an ongoing training program in conferring members of nearby communities. Here, we show a photo of the trainees in front of one of our trucks. We also present a photo of our 8-megawatt power plant, which is scheduled to be operational by mid-year.With that now, I'll turn the call over to Luis, who will take you through the financial statements.

L
Luis Dario Ganoza Durant
Chief Financial Officer

Thank you, Jorge. So on Slide 20 (sic) [ Slide 19 ], sales for the fourth quarter were $59.4 million (sic) [ $59.6 million ], down 21% from 2018 due to lower metals sold and significantly lower metal prices for silver, lead and zinc. The lower metals sold was mostly quarterly effect as full year metal sold was above 2017 for silver and slightly below for gold. We reported net income of $2.2 million in the quarter. We have noted the comparability year-over-year of net income is affected by a $21.9 million after-tax impairment reversal at Caylloma in 2017. Adjusted net income for the quarter was $4.4 million compared to $12.3 million in 2017. The reduction was driven mostly by lower sales. Adjusted EBITDA for the quarter was $22.7 million compared to $34.9 million recorded in 2017, and free cash flow from ongoing operations was $11.8 million compared to $19 million in 2017.On the same slide, for the full year 2018, we recorded net sales of $268 million, slightly below 2017. We reported net income of $34 million or $0.01 per share. Adjusted net income was $38.3 million, down 21% from 2017 due to a combination, as Jorge mentioned, of lower sales, higher production cost, higher depletion charges at the Caylloma mine as a result of reversal of impairment in 2017. Annual EBITDA of $113.9 million was 7% below the prior year. Net cash from operating activities and free cash flow from ongoing operations show an increase over the prior year of 19% and 49%. The increase in spite of lower operating results has to do with negative changes in working capital in the comparative year of 2017. Independent of the change over the prior year, however, we want to stress that free cash flow generation capacity of our business which in the current metal price environment stands at levels of around 20% of sales. We're currently converting close to 50% of EBITDA into free cash flow. We believe these levels are sustainable and consistent with the expected long-sustaining capital expenditure requirements at our mines. Free cash flow from ongoing operations for the full year 2018 was $55.2 million.When breaking down our sales performance for the quarter, we can see the highest impact gain from lower silver and gold sold and lower silver and base metal prices. This was partially offset by improved treatment and refining charges year-over-year.The next slide, we show the sales breakdown for the full year with the main single negative impact coming from lower silver prices. This was partially offset by improved treatment and refining charges and slightly higher volume effect from silver sold.On the next slide, our comparative segmented results show a similar pattern at both operations, mainly slightly lower margin for the full year and the stronger drop in margins in the fourth quarter. This is consistent with the stronger price environment in the first half of the year and higher quarterly production throughout the first 9 months of 2018.Cash cost for the full year of both mines, San Jose and Caylloma, was above 2017 in the range of 6% to 7%, although only 3% to 4% above our guidance. In the fourth quarter of 2018, we experienced higher production cost compared to the average of 2018. In the case of Caylloma, we do not regard this as a trend. We expect cash cost to come down in the first quarter of 2019 towards the midpoint of the range provided in our guidance for 2019.In the case of San Jose, costs in the fourth quarter of 2018 are consistent with the midpoint of the range provided in our guidance for 2019.The next slide, we have a breakdown of our G&A. We show higher G&A expenses at the operating mines for the full year. The main reasons were described by Jorge. The increase in the quarter is due to a large extent to non -- expenses of a nonrecurrent nature. Moving forward, for this line item, we expect an average of $2.2 million to $2.4 million per quarter. And for corporate G&A, shown in the second line item, we expect average quarterly expenditures of between $2.8 million and $3 million. Our effective tax rate for the full year was 50%. This is higher than the average 45% we typically expect to see. The main reason for this had to do with the evaluation of the Argentine peso and the weighted impact of deferred tax calculations as well as onetime withholding charges. The fourth quarter shows a high effective tax rate of 69%. This was mainly the result of a lower base of income before taxes and withholding taxes I just mentioned.And finally, on this slide, we want to highlight, again, our strong cash and liquidity position. We have expanded our credit facility from $120 million to $150 million, of which $80 million remain undrawn. We believe this, along with our positive free cash flow, puts us in a comfortable position to meet the funding requirements of the Lindero construction.Thank you, and back to you, Carlos.

C
Carlos Baca
Investor Relations Manager

Thank you, Luis. We would now like to turn the call over to any questions that you may have.

Operator

[Operator Instructions] We'll take our first question from Sherry Deng with Scotiabank.

S
Sherry Deng
Associate

I just want to ask, does the $295 million new guided capital include VAT, and -- that you expect to get back, and if so how much?

L
Luis Dario Ganoza Durant
Chief Financial Officer

So thank you. The answer is no. It does not include VAT. We estimate we have remaining $30 million to $32 million of VAT associated with the outstanding portion of the CapEx until completion.

S
Sherry Deng
Associate

Okay. And how do you expect the timing of receiving these VAT refund back in full?

L
Luis Dario Ganoza Durant
Chief Financial Officer

There is an opportunity for an early claim of VAT during the construction phase. That is an opportunity that still haven't materialized due to regulatory issues in Argentina. There is no formal -- even though there has been an amendment in the tax code allowing for this as an incentive to new projects, there is yet no formal procedure to actually go through with it. So we are waiting for that. Outside of that, VAT should be collected once we start the commercial operations. In the worst-case scenario, for that, we estimate a period of 2 years, in the case there is no early collection of VAT.

S
Sherry Deng
Associate

Okay. So once commercial production starts, you expect within that 2-year period to receive the VAT in full? In installments?

L
Luis Dario Ganoza Durant
Chief Financial Officer

Yes. We believe that's a reasonable expectation.

Operator

[Operator Instructions] We'll go next to Chris Thompson with PI Financial.

C
Chris Thompson

Quick question, just really related to Lindero here. Just referring to Page 4, there's a couple of, I guess, milestones indicated on the slide there. I mean, in April, you're -- that's when you start, I guess, mine development and equipment installation, October starting commissioning, and in December first goal point. I wonder if you could just sort of help us just join the dots by way of expectations for tonnes of -- on stockpile ahead of commissioning and first irrigation?

J
Jorge A. Ganoza Durant
President, CEO & Director

Yes. With respect to mine preparation at the orebody outcrops has a large surface expression, outcropping over a significant area. There is -- the sequencing of the mine or the startup of the mine is not several months in advance. We will start with a modest stockpile because the mine has a lot of flexibility to access ore very readily. The stockpile, I believe, is -- there is a buildup. Don't quote me on the numbers, but I believe we start with about 100,000 tonnes in the first month, but again, we're basically excavating ore and blasting ore right on surface. So the mine has a lot of flexibility. With respect to irrigation, we plan to initiate ore stacking under the current schedule in early October. That's when we plan to initiate stacking. We believe that pending -- we have a ramp-up curve for stacking that calls for first irrigation towards November, December. So pending on that, we should have enough fragment solution for the ADR towards December, year-end. But we will have the crushing and stacking starting in October. So there, we have 3 months of commissioning with load and ramping up starting in October for these.

C
Chris Thompson

Just in relation, I guess, to the CapEx that may need to spent, $172 million. How should we be apportioning that on a quarterly basis this year?

J
Jorge A. Ganoza Durant
President, CEO & Director

We should expect the bulk of that in the first semester of 2019, which is when we are -- we have one other major contractor's civil works concluding all of their work. We also have a conclusion of the leach pad, the conclusion of the power station. A lot of things are delivered in the first half of the year, almost all. The work that continues is with electromechanical and piping. So the reasonable expectation is to see the bulk of the figure registered and accounted in the first half of the year.

C
Chris Thompson

Okay, great. Just can you just -- Jorge, can you just comment on, obviously, this is a very -- you're ramping up, obviously, construction here. Any issues that really stand out as far as critical items at the moment that you're a little bit more mindful about?

J
Jorge A. Ganoza Durant
President, CEO & Director

As I mentioned in the start of this conference call, we battled with 3 issues most of 2018. Those were, one, slow buildup of our camp. That was a difficulty that persisted throughout the year. We were consistently behind the curve with the camp. And to make up time, we compressed the schedule, compressed activities, which in turn demanded more people offsite, which in turn created more pressure on the buildup of camp. So that is over, it's done. We have -- we are ahead of the curve today. Since the end of 2018 -- actually, since the start of the year, we are in front of the curve with respect to holding capacity for workers onsite and that's something important. Second is the initial -- the largest task of the project at the start was large earth movements -- massive earth movements and excavations. We encountered larger volumes of rock mass than earlier we estimated. That was a source of delay with respect to our schedule and excavations of the leach pad, but particularly on the excavations of the foundations for the crushing site, primary and secondary and tertiary crushing. In all those areas, we encountered larger volumes than originally estimated by the geotechnical work carried in nearing phase. So that is something we have struggled with through 2018 and early in mid-year. And those excavations, as I said, are concluded. So -- and last but not least is getting the contractors on site, performing according to our estimations and the project demand. And today, we have all the major contractors on site. Our scheduled feeds on the performance of -- we're seeing on the ground from these contractors, and we see a room for opportunity. We're scheduled second half today looking forward a lot of float. We have, as we extended this schedule, provided additional flow in the schedule, but these are not large amounts of flow productivity. But we are comfortable with the pace we are advancing with and that we have room to accommodate unforeseens, albeit it's not a large room. We believe the project is at a stage where we have more certainty with respect to performance and the different activities of the quarries. So it creates -- the project is an accumulation of problems, and we moved through the problems, we solved them and move on to the next one. The issue is when you get stuck with the same problem over and over and over. I don't see that today and that's something that we struggled with last year, as I said, with camp and excavations and getting the contractors at the reasonable report. Those 3 key issues are resolved, are behind us. Moving forward, I am seeing the team performing, working with the contractors or EPCM, and going through the issues, solving the problems and moving forward. So I am very optimistic as to -- in the way I see the project today.

C
Chris Thompson

Just a final maybe housekeeping item here. Can you give us a date for the revised reserves resources company-wide?

J
Jorge A. Ganoza Durant
President, CEO & Director

Yes. We are aiming to release those this month of March. Our technical services group has been lending support to Lindero and that has crowded their schedule a bit. Originally, we publish earlier than March, but right now, our date is before the end of the month.

Operator

And we'll take our next question from Mohammed Alassaf with ABPM.

M
Mohammed Alassaf

I'd like to ask a question with regards to customers because there is a major shift since 2017. Since most of the revenue was from Mexico and now it's from Switzerland, I wanted to know what was the reason for this? Also I have a few smaller questions as a follow-up.

J
Jorge A. Ganoza Durant
President, CEO & Director

The reason is basically that we are conducting direct exports from Mexico and the jurisdiction of the buyer is Switzerland. So based on the requirements on that particular note, where you saw that information, that is information that needs to be consigned the jurisdiction of the buyer.

M
Mohammed Alassaf

Okay. I also have a question with regard to the impairment test. You are forecasting higher prices for gold in the -- to 2025. What are the reasons for this?

J
Jorge A. Ganoza Durant
President, CEO & Director

We've used a range of long-term prices with which we feel comfortable. The range is -- goes up to $1,313, $1,315. That is one of the factors that has been contemplated. Of course, one of the key factors as part of that exercise. And the reason is there is support in the consensus focus of long-term prices for those ranges.

M
Mohammed Alassaf

Okay. My final question is about your return on tangible equity. I see this year is a little bit lower than the 5-year average. How do you see this moving forward?

J
Jorge A. Ganoza Durant
President, CEO & Director

Well, we are in a construction period. So you got to take that into account. If you adjust for Lindero, thinking more in terms of return on assets, you'll probably find us in the range of 13% -- 12% to 14%. With Lindero, we believe that should improve slightly, if not remain within the same range.

Operator

[Operator Instructions] We'll take our next question from Trevor Turnbull with Scotiabank.

T
Trevor Turnbull
Analyst

Jorge, I just had a question also with respect to the ramp up, but it's a little different. I was curious with the grinding and -- the crushing and grinding circuit and the HPGRs, do those start to get used -- the HPGRs specifically, are they used from the very beginning? And when you first start mining, is the rock a bit softer closer to surface, so is the HPGR kind of not going to get tested too much in the beginning and it kind of ramps up as the rock gets harder? Can you just talk a little bit about how those are going to get integrated into the ramp up?

J
Jorge A. Ganoza Durant
President, CEO & Director

Yes. We start with the full line, we start with the HPGR of the VAT, that is the plan. We start primary, secondary, tertiary agglomeration from where you are stacking. With respect to the question associated to the performance of the HPGR and the conditions of the rock material on surface, we do not identify today a risk on the side of material that can compromise the operation of HPGR, if that was your question. We do not have a clay material -- yes, on surface material tends to be a bit softer, but we do not have clays. Although there is some level of [ materization , ] it's not deep here. So no, we have not identified -- although we have looked at it and it has been part of our discussion, we do not identify that as an issue in the commissioning phase. No, remember we're in the one of the dryest parts of the world and the rock gets, yes, will have some level of [ materization ] but it's -- we do not identify as an issue there today.

Operator

Next, we'll hear from Adrian Day with Adrian Day Asset Management.

A
Adrian Vincent Day

I was just wondering once Lindero is up and running, what is the sensitivity on your cost to the Argentine peso, up and down?

L
Luis Dario Ganoza Durant
Chief Financial Officer

So based on our estimates, our operational expenditure structure will carry a sensitivity of around 30% to 35%.

A
Adrian Vincent Day

Okay. And do you have forecast of the peso -- internal forecasts?

L
Luis Dario Ganoza Durant
Chief Financial Officer

Yes. We are working with a base case scenario for our different projections that contemplate the peso close to the ARS 48 level -- the exchange rate at a level of ARS 48 per dollar towards the end of this year. And into 2020, we -- again, based on inflation and our base case scenario, more in the range of ARS 54 per dollar towards the end of 2020, with an average exchange rate above ARS 50 for 2020, which is our first year of operation, right?

Operator

[Operator Instructions]

C
Carlos Baca
Investor Relations Manager

Thank you, Jim. If there are no other questions, I would like to thank everyone for listening to today's earnings call, and we look forward to you joining us next quarter. Have a good day.

Operator

Ladies and gentlemen, this does conclude today's meeting, and we thank you all for your participation. You may now disconnect your lines, and we hope that you enjoy the rest of your day.