First Quantum Minerals Ltd
TSX:FM

Watchlist Manager
First Quantum Minerals Ltd Logo
First Quantum Minerals Ltd
TSX:FM
Watchlist
Price: 19.28 CAD 1.1% Market Closed
Market Cap: 16B CAD
Have any thoughts about
First Quantum Minerals Ltd?
Write Note

Earnings Call Analysis

Q3-2024 Analysis
First Quantum Minerals Ltd

Solid Q3 Performance and Positive Outlook Amid Challenges

In Q3, the company reported a 4% revenue increase with EBITDA soaring 55%, despite copper prices being 2% lower than the previous quarter. Copper production rose by 13% to 116,000 tonnes, prompting a revision in annual guidance to 400,000–420,000 tonnes. C1 cash costs improved by 9% to $1.57 per pound, with full-year guidance narrowed to $1.80–1.95. Notably, gold production also increased, leading to higher forecasts. Liquidity remains strong at $1.5 billion, with strategic partnerships under exploration as management focuses on stabilizing operations amid power challenges in Zambia and pending approvals in Panama.

Solid Operational Performance Amid Challenges

In the third quarter, First Quantum Minerals showcased resilience despite ongoing power challenges in Zambia. Total copper production reached 116,000 tonnes, marking a notable 13% increase from the previous quarter. The strong operational performance contributed to significant improvements, with a 9% reduction in C1 cash costs, bringing it down to $1.57 per pound.

Revenue Growth and Financial Health

Even with copper prices slightly decreased by 2% compared to the previous quarter, First Quantum managed to grow its revenue by 4% and buoyed its EBITDA by an impressive 55%. This resulted in net earnings attributable to shareholders improving to $108 million, a positive turnaround since entering preservation at the Cobre Panama mine.

Increased Production Guidance

The company raised its production outlook, expecting copper production to range between 400,000 and 420,000 tonnes for the year. Specific to the Kansanshi mine, guidance was adjusted to 155,000 to 165,000 tonnes, while gold production for Kansanshi is now expected to reach between 90,000 and 100,000 ounces.

Cost Management and Hedging Strategy

First Quantum has effectively managed costs, narrowing the top end of its cash cost guidance for the year to between $1.80 and $1.95 per pound. The company also maintained a strategic hedging approach, with roughly 43% of its copper production hedged through zero-cost collars until late 2025, securing an average floor and cap price of $4.07 and $4.78 per pound.

Construction Progress at Kansanshi

Progress on the $1.25 billion Kansanshi S3 expansion continues to be on track. The team has completed significant installations, and the first production is anticipated in the second half of 2025. The project's budget remains intact, with $550 million still to be spent, of which $200 million is already committed.

Liquidity and Debt Management

The company’s liquidity remains strong at $1.5 billion, which includes $693 million in cash and $830 million of undrawn revolver. Notably, net debt increased by $154 million to $5.6 billion, primarily due to capital expenditures on the S3 project. The successful amendment of the Trident facility, extending repayments to 2026-2028, has freed up $425 million in liquidity for the upcoming year.

Ongoing Challenges and Future Outlook

Despite strong performance metrics, First Quantum continues to navigate challenges, particularly regarding the Cobre Panama operations, which remain in preservation status. The company is actively engaged with the new Panamanian government to expedite the approval of its Preservation and Safe Management plan, a crucial step for resuming operations.

Safety and Community Engagement

Amidst operational success, First Quantum expressed deep regret over the tragic death of an employee, reiterating its commitment to workplace safety and support for affected families. Furthermore, community engagement efforts highlight the company’s aim to reinforce its commitment to responsible mining practices in the regions it operates.

Earnings Call Transcript

Earnings Call Transcript
2024-Q3

from 0
Operator

Thank you for standing by. This is the conference operator. Welcome to the First Quantum Minerals Inc. Limited Third Quarter 2024 Results Conference Call. As a reminder, all participants are in listen-only mode, and the conference is being recorded. [Operator Instructions]

I would now like to turn the conference over to Bonita To, Director, Investor Relations. Please go ahead.

B
Bonita To
executive

Thank you, Julien, and thank you, everyone, for joining us today to discuss our third quarter results. During the call, we will be making forward-looking statements. As such, I encourage you to read the cautionary notes that accompany this presentation, our MD&A and the related news release. As a reminder, the presentation is available on our website and that all dollar references are in U.S. dollars unless otherwise noted.

On today's call are Tristan Pascall, our Chief Executive Officer; Ryan MacWilliam, our Chief Financial Officer; and Rudi Badenhorst, our Chief Operating Officer.

And with that, I will turn the call over to Tristan for opening remarks.

T
Tristan Pascall
executive

Thank you, Bonita, and thank you, everybody, for joining us today for our third quarter update. It is pleasing to report strong operational performance from the Zambian operations during the quarter to which Rudi will cover in his remarks. Over the last several quarters, the work by the teams at site have placed us in today's position to deliver on the upper end of the copper production guidance range and the lower end of the cost guidance that we provided earlier this year. While the Zambian operations had a successful quarter with production, it is with deep regret that we announced the death of a colleague at Kansanshi towards the end of the quarter. The health and safety of our colleagues across the business is our top priority. This includes providing all necessary support for both our employees and their families during this difficult time. I would like to extend my deepest sympathies to the family and friends impacted by this tragedy.

In Zambia, the country continued to experience power restrictions during the quarter. However, our teams at Kansanshi and Trident were quick to respond with operational adjustments to mitigate the impact of these restrictions, resulting in minimal disruptions to copper production.

In the near term, with existing contracts covering approximately 50% of our power needs through to April 30, 2025, we expect to have sufficient power to avoid operational interruptions in the remaining quarter of the year. These agreements include options for extension, providing flexibility in our power sourcing strategy. We continue to be proactive in our power management efforts, recognizing the importance of power stability, not just for the mining sector, but also for Zambia's broader civil society. And as such, we are working constructively with the government to develop long-term solutions that support both industry and the country's energy security. Our efforts reflect our broader commitment to Zambia's economic and energy stability ensuring that essential services and industries remain operational, whilst mitigating the impact of power shortages.

For the medium term, the company is in an advanced discussions to receive offtake from 3 independent power producers for solar and natural gas projects that will add nearly 800 megawatts to the in-country power generating capacity. These projects are scheduled to come online in 2025 and will ensure that we can secure sufficient power for the commissioning and ramp-up of the S3 expansion at Kansanshi. In addition, the company is looking at direct offtake arrangements with independent renewable power producers that are expected to be commissioned in 2027, '28 that will add an additional 480 megawatts of power generation capacity.

With regards to longer-term solutions, we remain supportive of the commitments made by the country to ensure future energy resilience. On this front, we are actively collaborating with ZESCO on critical projects aimed at expanding and stabilizing the national grid, including installation of Static Var Compensators in the northwestern province.

Staying in Zambia, the 2025 national budget was presented on September 27 by the Minister of Finance and National Planning. The minister reaffirmed its commitment to maintaining stable and predictable tax policies to encourage investments and as such, there were no significant changes to the mining tax regime.

Over to Panama, we continue interactions with various levels of government stakeholder and community groups in the country. We have not yet met with the new President who has made public statements that the issue of the Cobre Panama Mine will only be addressed in early 2025. In the meantime, we continue to work on the approval of the Preservation and Safe Management program. The plan was submitted on August 27, along with a formal presentation to the Ministry of Commerce and Industries on September 25. But the plan is still pending the government approval, and therefore, aspects of the plan have not yet been implemented by the company.

At Cobre Panama, however, maintaining the integrity of the site remains of utmost importance for the company and Rudi will review the maintenance works that we continue with there. In parallel with the work at site, the company has also embarked on a comprehensive program of public outreach to provide transparent information regarding the mine to the Panamanian people. As part of the program, we have presented at universities, schools and several public events. The publication of our virtual tour online has attracted a significant number of visitors curious to further understand the role of responsible mining in Panama. And we continue to engage closely with our key stakeholders, including our workforce, local communities and suppliers.

With regards to arbitration, our ICC arbitration continues to be the most advanced with a final hearing scheduled for September 2025. Under the FDA arbitration, the company has 3 years from the date of Panama's breaches of the FDA to file its arbitration claim. We continue to maintain the position that arbitration is not our preferred outcome, and we remain committed to dialogue with the new government and to be being part of the solution for the country and the people of Panama.

Along with our third quarter results, the company announced the appointment of Ms. Montalvo and Mr. Xia to the Board of Directors. I'm pleased to welcome both to the Board, both of whom bring several decades of industry experience with him and with Juanita's experience in social affairs in Latin America and Africa and Kevin's deep knowledge of the copper markets.

With that, I will conclude the opening remarks and pass the call to Rudi to review our operational results.

R
Rudi Badenhorst
executive

Thank you, Tristan, and thank you, everybody, for joining our call. It is pleasing to share with you today the strong operational performance during the third quarter despite the power challenges in Zambia. I would like to thank the teams in Zambia for their proactive and decisive actions in power management that allowed copper production to continue virtually uninterrupted for the last several quarters.

Total copper production for the third quarter was 116,000 tonnes, a 13% increase over the second quarter. The improved volumes also resulted in a 9% quarter-over-quarter decline in C1 cash costs to average $1.57 per pound. With a strong production year-to-date, we have increased our copper production guidance for the year to between 400,000 and 420,000 tonnes. Kansanshi had a solid quarter recording its highest quarterly production in copper since 2021 and in gold since 2022. Copper production totaled nearly 50,000 tonnes in the third quarter, an improvement of well over 8,000 tonnes from the second quarter as mining from Main 15 and Main 17 cutbacks allowed access to higher grades.

In addition, we maximized mixed tonnes at higher grade through the mills by swapping the mixed and sulfide milling circuits during the third quarter, and this will continue for the larger part of the fourth quarter. As such, we have increased our copper production guidance above our previous guidance range to between 155,000 and 165,000 tonnes. As I noted earlier, gold production at Kansanshi was also strong in the third quarter at 32,000 ounces. This has allowed us to also increase our gold production guidance above the previous guidance range to between 90,000 and 100,000 ounces for Kansanshi and 120,000 to 135,000 ounces at the group level.

Sentinel reported copper production of 58,000 tonnes in the third quarter, approximately 4,800 tonnes higher than the previous quarter as throughput continued to improve. The higher throughput was driven by improved fragmentation of ore and better performance of the input crushers. Mining performance and throughput is expected to further improve over the remainder of the year with the ongoing development of the Stage 3 Western cutback, which will increase the availability of soft ore. As such, we continue to expect copper production to be within our guidance range albeit at the bottom end of the range at 220,000 to 230,000 tonnes.

Enterprise had its first full quarter of commercial production, producing 4,800 tonnes of nickel. At the end of September, the nickel plant was turned off for 9 days in order to prioritize power for the copper circuit. However, the nickel plant assumed normal operations in October and production guidance remains unchanged at 17,000 to 20,000 tonnes of contained nickel.

At Cobre Panama, the operations remained under the phase of preservation and safe management throughout the quarter. The inspection frequency of the process plant has increased from 28 to 56 days. However, start-up frequency of equipment remains unchanged at 14 days. All the major ultra-class mobile equipment is in a maintenance cycle that adheres to the original equipment manufacturers long-term storage recommendations and includes periodic inspections as well as scheduled start-ups. The costs for the P&SM program in quarter 3 were approximately $13 million per month and are expected to be in the range of $11 million to $13 million per month for the remainder of the year.

I wish to thank all our employees at Cobre Panama and their continued commitment to the operation and maintaining the mine area to the highest environmental standards.

As Tristan noted earlier, we had a tragic accident during the quarter. The death of our colleague was profoundly felt by the team at Kansanshi and across our company. We continue to support the family, and we are committed to applying the lessons learned from the investigations as we seek to ensure the safety of all our colleagues.

Thank you. I will now hand the call over to Ryan to review the financials.

R
Ryan MacWilliam
executive

Thank you, Rudi. On the market side, the copper price was strong early in the quarter, supported by the weaker U.S. dollar and lower interest rates. Prices then pulled back on concerns around Chinese growth, reaching a low of $3.91 in early August. While prices increased steadily late in the quarter following the announcement of Chinese stimulus measures. Overall, Q3 realized copper prices were 2% lower than Q2. Despite the slightly lower copper price, revenue and EBITDA increased by 4% and 55%, respectively. On the back of the strong operational performance that Rudi described and the resulting higher copper sales and increased gold volumes.

Q3 net earnings attributable to shareholders also improved to $108 million. Returning to a positive position for the first time since Cobre Panama entered preservation and safe management. On to costs. C1 costs improved by 9% to $1.57 per pound. This improvement was due to higher production across all sites, coupled with lower fuel costs from decreased fuel prices and improved burn rates. As Rudi and Tristan mentioned, our Zambian electricity costs have increased because of the power shortages and the resulting higher third-party imports. The cost impact of this has been mitigated by strong gold byproduct credits during the quarter. The result of both strong gold production and strong gold prices with the gold price averaging $2,400 per ounce during the quarter.

Additionally, the reduction in inflation that has played out globally in recent months has resulted in some of our input costs tracking favorably compared to the assumptions used in our initial C1 cash cost guidance. We are therefore narrowing the top end of our cost guidance by $0.10 with our revised, full year guidance range of $1.80 to $1.95 per pound.

In order to prudently manage the balance sheet through the construction of S3, we've maintained the hedging approach that we described on our Q2 call. We now have roughly 43% of our copper hedged in the form of zero cost collars through to the end of 2025. Some of our hedges that we previously put in place rolled off during the quarter, resulting in a realized hedge gain of $21 million. We've continued to add new collars during the quarter with average floor and cap of $4.07 and $4.78 per pound, respectively. This takes our current total hedge position to 245,000 tonnes of collars with an average floor in cap of $4.18 to $5.01 per pound.

Net debt increased this quarter by $154 million to $5.6 billion. This was driven by capital expenditure on S3 and increased working capital levels. This increase in working capital was predominantly a result of sales made towards the end of the quarter and cash only being received for these sales after the quarter end. Liquidity remains strong at $1.5 billion comprising of $693 million in cash and $830 million of undrawn revolver.

It was also pleasing to successfully complete the amendment and extension of the Trident facility on October 15, with repayments now commencing in 2026 out to 2028. This frees up $425 million in liquidity in the coming year, while we focus on delivering S3. We also continue to review the merits of a sale of CLC and a minority investment into our Zambian business. This is consistent with our broader strategy. We were open to partnerships in Zambia and across the group if it creates strategic value for our business and host countries. As these discussions are currently underway, we'll not be making further comments in this regard.

That concludes the finance section. I'll now hand the call back to Tristan.

T
Tristan Pascall
executive

Thank you, Ryan. Before handing the call over for Q&A, I am excited to share with you the progress that has been made at the Kansanshi S3 expansion since our last update. During the quarter, the team at site completed the assembly of the SAG and ball mills, and installation of the gearless mill drives have commenced. System configuration of the plant control system has been completed for the primary circuit, and work is now focused on ancillary systems and services. In our presentation deck, you will see other areas of progress, including installation of the flotation cells, direction of the pebble conveyors and the primary crusher, all of which remains on schedule.

The focus on site has now shifted to bulk piping and electrical installation works. Commissioning activities have started in the 33kV distribution substation, which is scheduled to be energized in the fourth quarter. The plant simulator is now on site and operator training is expected to start imminently.

We expect that all required equipment will be on site by the end of November. We have been focused on supplementing manning levels, bringing in the additional manpower that will be needed for the installation of equipment over the coming months as we commission S3. Our operational readiness team is in place at Kansanshi and already working with our project team to facilitate a smooth ramp-up on completion of the construction phase. There is a lot of activity on site, and we are on track for first production in the second half of 2025.

Thank you for your attention. This brings our prepared remarks to an end. Operator, we can open the call for Q&A.

Operator

Certainly. We'll now begin the analyst question-and-answer session. [Operator Instructions] Our first question is from Orest Wowkodaw with Scotiabank. Please go ahead.

O
Orest Wowkodaw
analyst

It sounds promising that it could be pathway to a discussion, I guess, in the new year with the new Panamanian Government on restarting Cobre Panama. I am just curious, does the - do you think the environmental audit has to be completed to begin that process? And can you give us an update on when you think that's going to happen? And then also wondering about what the status is of the existing concentrate sitting at Cobre Panama?

T
Tristan Pascall
executive

Hi Orest, thanks for the questions. So, in terms of the environmental audit, yes, the government's comments, the President's comments in particular, have noted that they would like to see that audit happen. We expect in the timetable that they've been providing was by the end of this year, although at this stage, we haven't seen that environmental auditor appointed as yet. Currently, our understanding is that the terms of reference for that audit are being prepared and that they would then appoint the auditor.

Our hope is that, it can still be completed on time, and that the audit would then be in place for the timing that we talked about and the present hasn't been made clear in terms of a restart early next year or at least dealing with the issue early next year.

In terms of your question on the concentrate that materials is sitting at the port, the 121,000 tonnes it's in reasonable condition in terms of copper content, but we remain concerned about degradation of the sulfur in that material, and that does continue to pose some hazard environmentally. It is in the best interest of the environment and everyone there to get that material shipped off. Our understanding that it is the government's intent to do that through approval of the preservation safe management plan would allow that material to move. And we think that's important to happen as soon as practically can be achieved.

Operator

The next question is from Ralph Profiti with Eight Capital.

R
Ralph Profiti
analyst

Thanks operator. Just wondering and maybe Rudi can chime in here, as the wet weather comes in at Sentinel in Q4, just wondering what the conditions of the benches are in sort of utilizing some of the terrace mining initiatives sort of what state are we in there? I am just wondering if that's kind of driving the bottom end of the range as we think about conservatism into Q4?

T
Tristan Pascall
executive

Thanks, Ralph. Rudi, do you want to take that question?

R
Rudi Badenhorst
executive

Yes, no problem. Hi Ralph. Thanks for the question. Certainly - well, let's start off with - the wet season hasn't started in Zambia yet. At the end of this week, we're going through the 60th birthday anniversary of Zambia with independence. And normally, that's when the rain starts.

So we -- but I can assure you, we are well prepared for the wet season, considerable amount of capital has been spent on dewatering activity and setting up the pit into such a way that allows for the handling of water in the event that we have exceptional wet season. But we're quite confident that the measures that we've taken are adequate enough. And then mining is set up to deal with it.

As far as the back end of production is concerned at Sentinel, sure, yes, surely, we are always taking the wet season into consideration when - in our plans and in our budget. But also we are taking necessary maintenance measures as well during the quarter that impacts that.

R
Ralph Profiti
analyst

Got you. Helpful. Yes. Ryan, can you help us out with capital spending versus budget at S3 sort of the remainder of 2024 and maybe into 2025. Tristan's comments about ramp-up in labor activities and manpower. Just wondering whether or not we're seeing inflationary pressures there?

R
Ryan MacWilliam
executive

Sure, Ralph. So we've spent $700 million on S3 to date. So that means we've got $550 million to go. As Tristan noted, we're on budget. Of the $550 million to go, $200 million of that is already committed. That relieves a balance, which is still to be priced but in most of those contracts, we have visibility and what we expect the pricing to be. So I think that - all of that gives us the confidence in Tristan's remarks about the fact that the project remains on track and on budget within that $1.25 billion.

Operator

Next question is from Ian Rossouw with Barclays.

I
Ian Rossouw
analyst

Just a question on the S3 expansion, Tristan, you mentioned in your remarks, first production is expected in the second half of 2025. If I compare that to some of the previous releases, the wording was mid-2025. Just wanted to get some clarification if there has been any delay to the target for first production? And then secondly, sticking to Kansanshi, just on the gold production, in the start of the year as part of your three-year production outlook, you cut gold production guidance at Kansanshi by 30% for this year and 25% next year.

And then the increase today is essentially sort of taking that production at Kansanshi back to where the guidance was last year. Can you provide a bit of details what's resulted in these changes and whether its mine plan, I guess, you mentioned in the release, its grade related. But just how should we think about that for next year's figure?

T
Tristan Pascall
executive

Thanks, Ian. I'll let Rudi take the second part of that question on gold production and how that's come about through the swapping of the mills from sulfide to mix. But in terms of your first question on S3 timing, I think Ian, in our response to that is we have the opportunity now with greater clarity to the end of the project to be more specific. So I wouldn't call it a change in outlook.

It's more that we've been more specific on how we see the project land, and that is, we expect completion by mid-year. And then we're really focused now on operationalizing and ramping up through the second half of the year. So our notes really speak to that how we see first ore start and first production come through and ramp up through the second half of the year. But broadly speaking, we're comfortable with the project delivering on the timetable we've been outlining.

Rudi, would you like to just speak there on the gold and the situation for the year.

R
Rudi Badenhorst
executive

Hi Ian, good to hear from you again. As you would be aware, Ian, at Kansanshi that the gold grade reasonably tracks our copper grade. And where we currently mining in the upper benches of the Main 15 cutback. We are seeing slightly higher mixed ore grades, which also then necessitated or gave us the opportunity to swap the milling circuit. So it's meant that we have seen a higher tonnage going through the plant of mixed grade and obviously, the goal of the company is that.

And at the same time, during the third quarter, we installed some additional Knelson Concentrators at Kansanshi and brought others online, which also resulted in the additional goal. As far as 2025 is concerned, we'll look at that when we provide our guidance earlier in the New Year.

Operator

Next question is from Myles Allsop with UBS.

M
Myles Allsop
analyst

Yes. Great. Thanks. Just going back to Cobre Panama, could you just give us a quick update in terms of speed to remobilize if you were to get approval tomorrow, what would be the likely sort of timing to be able to start ramping up? And would it be helpful to get a sense as to why you said the government has not approved the Preservation and Safe Management plan.

But the kind of sense last quarter was that it was eminent and three months later, and it still sounds like its imminent. Do you have a better understanding as to why it's dragging and will we be having the same conversation in three months' time? And that's the first question.

T
Tristan Pascall
executive

Thanks, Myles. Yes. So look, in terms of ramping Cobre Panama back up, if and when that decision comes through, yes, I think what we would - how we would respond to that is, certainly, at this time, it's really about bringing people on and bringing supplies back online. There's a lot of Panamanian suppliers that are sitting idle and waiting. There's a lot of employment in Panama that's sitting idle and waiting. We -- there was some 4,500 redundancies made at the site. We currently speak to around 3,000 of those people every month, and most of those are ready to come back to work immediately. But I think as time drags on, that gets harder to get people back. It's just a natural attrition there.

And so I think if it does delay too much later into second half of next year, that gets more challenging. In terms of how we think the overall ramp-up will run, we would be able to start up one train or a second train fairly -- in a fairly straightforward manner, but then it's going to take time to build out capacity. And so probably would take in the order of six months to build out to the sort of full level.

In terms of the second part of your question on the Preservation and Safe Management plan, yes, certainly, we had felt in country and the conversation seems to be that it's imminent. Comments from various ministers who are involved in that decision-making process have been public in saying that's imminent, and we continue to receive that guidance on the ground there, that it is imminent. Certainly, what we think is dragging on that is that the government has made clear, the President made clear, they're focused on the Social Security Reform at the current time and that is taking a lot of attention.

Nonetheless, as I said, the public comments have been around imminent approval because that was important in terms of managing the environmental topic at Cobre Panama, and that's in everybody's interest that sits well outside a commercial interest or the mine's interest or the government's interest that's in the interest of everyone that those environmental -- the environmental security, the asset integrity of the sites is maintained. And so it's - therefore, our view that it should be approved without any further delay.

Operator

The next question is from Lawson Winder with Bank of America Securities.

L
Lawson Winder
analyst

Thanks very much, operator. Good morning, Tristan, Rudi and Ryan. Excellent Q3 results in Zambia, and thank you for the update. If I could ask about the Zambian asset sales process, just in light of the recent news and of another potential offer for a minority interest, would you be able to characterize the nature of that sale process, for example, are there still new bids coming in?

Or is the process closed? Are you in a final phase perhaps with a short list of bidders? And even can you give us an idea of maybe how many bidders might be involved? And ultimately, what will the criteria be if FM makes - sorry, First Quantum makes a decision to accept an offer.

R
Rudi Badenhorst
executive

Sure, Lawson. Was pretty public -- sorry. Sure. Lawson, we've been pretty consistent that across the business, we're more I've been to partnerships, and that includes in Zambia, but it's only if it's in the interest of our Zambian business, the Zambian government and all the stakeholders involved. So we remain open-minded in respect of potential partnerships. We are engaged in discussions in that respect, but we wouldn't provide any comment beyond that given they are live discussions.

L
Lawson Winder
analyst

Okay. No, fair enough. And then where my followed-up would be would actually be on Sentinel. So it was great to see that the improved fragmentation in the pit was leading to some improved crushing and milling rate. What are kind of the next steps to ultimately get to that 62 million tonnes per year run rate? And when filings thinking of when that will ultimately be achieved?

R
Rudi Badenhorst
executive

Hi, Lawson, really effectively achieve that run rate during the months of August and September with 5 million tonnes per annum being throughput at Sentinel. Sentinel, certainly now in a position and you'll remember during the last few calls, we said that we're setting up the pit to be productive, which means that we will continue to line what's in front of the shovels.

We won't be chasing grade. And it's all about setting up the terraces and getting those shovels in a position where they can mine effectively and the trucks can all effectively. That's where Sentinel is at now. And we're quite confident that over the preceding year, we'll see those rates of 5 million plus on a monthly basis is happening a lot frequently.

Operator

Next question is from Bryce Adams with CIBC.

B
Bryce Adams
analyst

Thanks for the update, and thanks Tristan for the comments around Panama. My question is a follow-up on the earlier Panama questions. If the environmental order is not yet started and the order isn't appointed, does this mean the discussions with the government are more likely to be second half of next year rather than earlier in the year? Understanding an audit might take up to six months to complete. The timeline here seems like those government conversations could take a little longer. Just wondering if I have it wrong, but it appears like that audit might conclude by mid next year. That's all I had.

T
Tristan Pascall
executive

Yes. Bryce, thanks for the question. I think we need to see what the terms of reference are for the audit and how that would work. I mean certainly, Cobre Panama has been the subject of intense audit all through last year and this year. The audit result that we had is an operating asset from August to October was 100% compliance on all the environmental and biodiversity requirements of the 371 commitments under the ESIA, and it was only elements of the health and safety where some improvements warranted, and we're underway. Subsequent to the Supreme Court decision and while we were closed, we brought an independent orders to review. And the government itself brought in auditors when the mine was in suspension. And again, the independent audit was demonstrated a high level of compliance and the government ordered itself continue to demonstrate 100% compliance on the environmental and biodiversity requirements under the ESIA. So we feel good.

We feel confident about the position of the mine and that any independent audit looking at it would feel the same way. That probably point out areas and we're quite happy that those areas have pointed out and that we get everything to the highest possible standards. But we'll just need to see what those terms of reference are in order to understand the timetable that you referred to. Beyond that, I can only point to the President's comments and his most recent comments in New York to say that would be looking to deal with the issue early in 2025.

Operator

The next question is from, pardon me. I have to manual update somebody. The next question is from Gabriel Simoes with Goldman Sachs.

G
Gabriel Mosquera Simões
analyst

I've given an update on the Zambia power situation like you mentioned you expect minimal reserves in the fourth quarter. But it'd be interesting to understand your view on this looking a bit further out, right? So what could we see in terms of disruption as Kansanshi ramps up new concentrator? And how big an impact that could have? And if there are any measures being taken by the country in terms of power generation, or in terms of infrastructure to improve the situation, please of the extended drought or in terms of future gas in the coming years?

T
Tristan Pascall
executive

Thanks, Gabriel. Yes. So certainly, the situation with El Nino had an impact on the country, not just on power, but on food security and First Quantum has been supporting Zambia. We have trucked some 4,000 tons of maize into the country to support the government's efforts on food security. And the power situation, we've been putting in place the alternative sourcing of power, and that is from imported sources. And we have three providers of that imported power mostly from Mozambique and from Namibia to augment the in-country supplies. And so at this stage, we feel good about this season. And as Rudi says, the rains are expected imminently for the wet season.

It does look like in terms of your question, looking ahead that the forecasts are that the El Nino has already flipped into La Nina, although a mild La Nina than probably was earlier expected midyear, and the current outlook is the La Nina is a mild La Nina, and that means rainfall a more normal rainfall.

However, we do continue to prepare for both scenarios. That is a heavy La Nina, lots of rain. And as Rudi said, we've done the work on preparing for dewatering in the mines, to be able to cope with that heavy situation. But also the other scenario, which is lighter rain, and that would mean that the mining conditions are good, but that we might see prolonged disruption to power.

So the contracts that we've placed to external parties provide for that optionality they provide the ability to continue those imports, and we feel comfortable that the level of import would allow us to start S3 without substantial impact on our production expectations. Beyond that, we continue to work with the government utility ZESCO in supporting infrastructure in the country. We have projects online with them to support the stability of the grid in Static Var compensation over the next two years, and we have projects with them to support increased renewable energy in the country to some 480 megawatts of power to come in from wind and solar sources.

And beyond that to support them in purchasing power directly as ZESCO from surrounding countries, including some 250 megawatts from South Africa that's coming through in the next month or so. I hope that covers the question, Gabriel. But in terms of outlook, we believe that we've built in the flexibility and optionality that we can cover any potential shortfall in power.

G
Gabriel Mosquera Simões
analyst

Super clear. Thank you. If I could just add another question on your hedging strategy. But you mentioned that around 43% of all I'm thinking of, expected production. As you expected to release to spot prices in 2025. So I just wanted to understand how you're thinking about the strategy going forward? Just around 50% of production hedged, anyone you're comfortable moving forward? Or should we see any changes to that policy?

T
Tristan Pascall
executive

Ryan, would you take a follow-up question, please?

R
Ryan MacWilliam
executive

So some hedging strategy, broadly, at the moment, we're targeting having around 40% to 50% of our production hedged through zero cost collars up to the end of 2025. And as hedges roll off, so you've seen us replace them with new hedges as we did in Q3. As we come into the back end of this year and into early next year, we'll decide whether or not to extend that into 2026. And that decision will be driven by where the copper price comes to, how we're going on Zambia and a variety of other factors. But for now, the plan is to stay between 40% and 50% hedged through to the end of 2025.

Operator

The next question is from Dalton Baretto with Canaccord Genuity.

D
Dalton Baretto
analyst

I'm thinking past S3 in your growth pipeline to Taca Taca. Under this new Argentine, RIGI regime I understand there's some pretty specific timelines in terms of getting the project approved by RIGI and then some specific timelines around capital spending. And I'm wondering if you can just update us in terms of how you're thinking about Taca Taca as it relates to the RIGI regime?

T
Tristan Pascall
executive

Hi, Dalton. Yes, thanks for the question. And yes, it's pertinent to speak about Taca Taca. We saw a large delegation from Argentina at LME Week. And I think certainly, that reflected a lot of confidence that the country is developing in terms of the investment promotion legislation that was passed as part of the omnibus legislation, and we've seen RIGI. And certainly, for us, it provides an important step forward for Taca Taca. That project, we continue to like the project, potentially deliver perhaps 250,000 tons of copper a year for the first decade of an overall life that's 30 years plus. We're not at a sanction decision stage yet. We - the timelines of the RIGI that an application is required within the next two years. And there is a possibility that it can be extended by one year, but at the moment, the application window is around two years.

In that time, we would also need to see the environmental permit for Taca Taca come through and water permits. And in that timetable, we would also need to be working on the financing pathway for the project. So we see those three as parallel work streams and that need to develop alongside each other in the timetable that's provided for under the RIGI.

D
Dalton Baretto
analyst

And as my follow-up. I mean, you touched on financing. And I was wondering, as you think about financing Taca Taca or whether a JV there is on the table or even if whether this plays into potentially JV on the Zambian.

T
Tristan Pascall
executive

Sure, Dalton. I think that what we see in Argentina is a level of confidence developing, and I think that needs -- that will continue to develop as we see stability come through over the coming months and during that period, for the application of RIGI. During that time, we think the country will continue to open up for the right partners. We've been open. Ryan made comment about our approach to partnership. That is that we see the benefit for that. We're doing that on our La Granja project, where we partner with Rio Tinto in Peru. We're doing that, and we're going through a process in Zambia, where we look at partnership.

And in fact, Cobre Panama was a partnership with KOMIR, the Korean government. So Argentina itself, we think can lend itself and that the right partners will gain confidence and gain interest in the country in order to develop a financing pathway forward. And we think that the timetable that's outlined in the RIGI that two years is appropriate to consider and work through that process.

Operator

The next question is from Craig Hutchison with TD Cowen.

C
Craig Hutchison
analyst

Just a question around Q3, you guys obviously had a very strong, sorry, Q4, you had a very strong Q3 results. But the guidance kind of implies that you'll be somewhere in the range of 80,000 to 100,000 tonnes for Q4. And yet the setup seems pretty good at Sentinel softer ore and a shift to more mixed oxide at Kansanshi. Can you just give some context as to where you're going to see that change in terms of production, the lower guidance for, I guess, Q4. Is that being driven by lower grade to Kansanshi? Or is there some planned maintenance shutdowns in the quarter?

T
Tristan Pascall
executive

Rudi, would you like to take that question? Thanks, Craig. Rudi?

R
Rudi Badenhorst
executive

Yes. You hit the nail on the head. It's primarily lower grades at Kansanshi, and that's driven by normalization of the mixed and sulfide circuits where we swapped back with mixed material going back towards its original circuit and then doubling up again on the tonnage throughput on sulfide, which generally runs at a lower grade. So that's pretty much driven through there. The Stage 3 cut-back at Sentinel, yes, it's nice and softer ore, it runs through the month a lot easier.

But as we are still in the upper reaches of that cut-back, it is relatively tarnished and weathered material. So it doesn't float as well as your primary sulfides. But yes, primarily driven by Kansanshi and swapping others in circuit.

Operator

The next question is from Ian Rossouw with Barclays.

I
Ian Rossouw
analyst

And just a quick one on working capital, Ryan, you mentioned you've sold quite a bit of material towards the end of the quarter and received the cash post quarter end. Obviously, prices are up a bit versus the quarter average. But just wanted to get a sense of how much of that $200 million working capital you would expect to come back for that to normalize?

R
Ryan MacWilliam
executive

Sure, Ian. So of the $200 million working capital build, $100 million of that was an increase in receivables. About $40 million of that was a VAT receivable, which came in just after the quarter end. And then of the balance, the $60 million of receivables due to sales, we probably got about $20 million to $30 million that came in just after quarter end. So net about $60 million of $100 million came in just post quarter end rather than getting in before the end of the quarter.

I
Ian Rossouw
analyst

And just on the inventory side because you're still tracking sales quite a bit behind the production so far this year. Is there some expected on working on the inventory working capital?

R
Ryan MacWilliam
executive

Not significantly. We actually had low inventories at the end of Q2. So that's why you saw it slightly moved the other way through the end of this quarter. So maybe we'll get inventories a bit lower through the back end of the year, but I shouldn't assume a big release from a working capital perspective coming into the year-end. I mean a lot of that inventory is still sitting in that Cobre Panama concentrate.

Operator

The next question is from Myles Allsop with UBS.

M
Myles Allsop
analyst

Yes, thanks for the follow-up. So just a couple of things. First of all, again, going back to the Preservation and Safe Management. How much should we put in our forecast for the cost in 2025? Should we keep running at around $12 million a quarter? Or at what stage will you take it a step lower than that? So that would be helpful. And then going back to the Zambian power question as well. Can you just remind us how much power you consume currently and how much that will lift by with S3? And then if you're 50% covered, where will you be when S3 is running?

T
Tristan Pascall
executive

Thanks, Myles. I might ask Rudi to take that second question on the specifics of the power draw in Zambia at the moment and then with S3. But in terms of your first question on the cost of the Preservation Safe Management Plan or the plan that we're running at the moment. As Rudi outlined, we were at around $13 million a month through the course of Q3, and we're saying about $11 million to $13 million.

Myles, the tension there is to make sure that we ensure the environmental security. That covers about 1,400 people on site. That's the highest proportion is that labor cost. And it is appropriate that we continue to maintain that dedication and that level of compliance. But certainly, there is a law of gravity and we can't withstand that forever. We really do need to see the sources of funding for that to come through. And obviously, the concentrate in the share is a source that can be applied and support all the environmental works that need to happen.

To date, the company has been doing that just on the basis of ensuring good compliance but ultimately, we do need to see that come through. I think we will get to a point where we need to go to a next step in terms of reducing that cost and obviously, that's around people. And we're talking to the government around the timing and how that can work. The level of engagement is increasing, and it is important that we get those answers so that we can address those questions as to what is the right level of people and performance going forward so that we can manage that cost, manage the level of employment there at the site, but also ensure that there isn't a legacy that Panama has to bear there.

And all of that is part of the conversation that we're seeking engagement, having engagement on. And that's why the Preservation and Safe Management Plan is important and why we continue to push and request that that's approved as soon as possible.

R
Rudi Badenhorst
executive

Myles, I jump in here on the question on power. Currently our power draw on the assets in Zambia is around about 310 to 315 megawatts. Obviously, all of that is underwritten by power supply agreement by ZESCO and with currently with the drought, as Tristan mentioned earlier, we've obviously made various efforts to secure imported power directly through third-party providers. At the moment, we're importing about 190 megawatts of the total requirement. And the rest is provided by the state utility, ZESCO. As per our agreements when S3 comes online next year through commissioning and full ramp-up, it's another 85 to 90 megawatts but we've already, as I highlighted in our Q2 call secured power to ensure the suitable start-up and maintaining our production when S3 is running.

Operator

This concludes the question-and-answer session. I'd like to turn the conference back over to Tristan Pascall for any closing remarks.

T
Tristan Pascall
executive

Thank you, operator. I'd like to thank everybody for joining us today and for your interest, and we look forward to speaking to you again at our next update. Thank you.

Operator

This brings to a close today's conference call. You may disconnect your lines. Thank you for participating, and have a pleasant day.