B2Gold Corp
TSX:BTO

Watchlist Manager
B2Gold Corp Logo
B2Gold Corp
TSX:BTO
Watchlist
Price: 3.68 CAD -1.87% Market Closed
Market Cap: 4.8B CAD
Have any thoughts about
B2Gold Corp?
Write Note

Earnings Call Transcript

Earnings Call Transcript
2021-Q1

from 0
Operator

Good afternoon. My name is Jason, and I will be your conference operator today. At this time, I would like to welcome everyone to the B2Gold First Quarter 2021 Financial Results Conference Call. [Operator Instructions] I would now like to turn the call over to Clive Johnson, President and CEO. Mr. Johnson, you may begin your conference.

C
Clive Thomas Johnson
President, CEO & Director

Thanks, Jason. Welcome to the conference call to discuss the financial results for the first quarter 2021. Thanks for attending. We had another very strong quarter, as you're going to hear from Mike surely has evidenced and has laid out in the news release, very good financial performance, again, driven by strong operating performance at the mines, which allowed us a significant beat on operating all sustaining costs. And all of this, as everyone is still aware, is during COVID. So once again, it speaks to the tremendous leadership and then the tremendous management and the employees we have at all of our sites, everyone on the same page, which is committed to continuing to mine during COVID if we could do it safely and responsibly.We've got great relationship with the governments in the countries that we mine. And I think we've earned a lot of trust there, I think, over time with our -- the cultural approach that we bring to the business, it's treating people with fairness, respect, and transparency. And I think that pays off at a time of crisis or in a situation like COVID because we establish some mutual trusts. So the government, our employees, and the company all wanted to do the same thing that is to keep mining but do it safely and recognizing the impact of COVID. So we took many steps that we've talked about before, to assist the areas we're in, [ opposite ] COVID as we do with all sorts of aspects in the mines, but I think it's been a great success in a very difficult scenario all around these companies don't have a safety yet. So the fact that we continue to mine and pay taxes and keep these good paying jobs going and keep opportunities as safe as possible. I think it's been a good thing for the industry. I think there's a positive going forward, potentially in the mining space because I think post-COVID, many governments will look at who were the good performers, what were the good businesses to have in your country during COVID.And I think the response from miners, not just as others as well, have shown governments that gold mining can be very positive thing in the time of crisis. So just in generally, we were going to review the results of the quarter. And then we're going to talk a little bit about Gramalote. And as everyone sees in the news release, we delayed the completion of a final feasibility study and then Gramalote (00:02:57) but we think that will be about a year. And the economics are positive from what the piece of work that we've done so far.But we feel there's a much better project there or sorry, potentially better project there with an optimization for the drilling and other things that we can do. So while the economics are positive, we want to make it a better project, and we're going to take the time to do that. I think it's important to note that also we were going to be looking at -- we'd originally hoped to potentially have boots on the ground in September this year, if there was a positive development decision. That -- there was going to be some delay in that anyway because the government had -- was interested in our idea of doing resettlement in stages instead of all together, waiting 2.5 years to do all of resettlement and then start construction. So we've had conversations with the government where they've been interested to hear more about the idea. But they did ask us to go and then do some public consultation, understandingly, and also to have the government reviews, proposals, which will take some time. So we probably would have been looking at a 6-month delay for boots on the ground regardless of the economics and whether we've had a positive development season.So now we're talking about a feasibility study in the year. And Bill will give you detail as to what we think and why we think more drilling and some of the other things are important. People talk about optimization sometimes to perhaps trying to gauge some negative. But in this case, there's a number of things you'll hear from Bill that we identified in the project some time ago that we thought were things we may have liked to have optimized.But over time, we were trying not to change the footprint because AGA and the prefeasibility study had realized a construction permit. So we are trying to stay within the balance of that. Now we can open that up and look at the authorization and hear more about that from Bill. We remain very positive on the project. We've got good conversations with AGR partner, and we're looking to briefly to shortly finalize a budget over the next year, an increase in budget, and we should be able to hopefully announce that soon. But conversations we've had were on the same page. We're disappointed that we didn't have the robust economics we saw in the PEA that we'll talk to some of the things that change. But they, I think, along with ourselves, remain positive that this can become a good asset and a good project for us. So we'll go and do all of that work.I think it's really important to note as well the government relations remain very good in the U.K. and with federal government, we had a meeting with yesterday. I had a call with their representative of the Minister of Mines in Colombia, and they've been very supportive, but they're disappointed to hear that it's not going to happen right away, but very supportive of our desire to build the best project for everyone, including the Colombian people and the government as well. So very supportive there. And there's a lot of activity going to be happening, as you'll hear on the site in terms of working towards the resettlement program, all of our social programs we're doing there working with the government with small miners. There's a lot of good things that are going to happen in addition to the optimization to paying us keep this project moving forward.Generally, corporately, I think I'll just touch on the strategy briefly, we remained pretty much on the same page on strategy we've been on for some time, which continued to optimize production that's around our sites or at the sites as we've seen. We're going to continue to pursue our development opportunities to see where we're going with those in Gramalote, Kiaka and then also looking at the potential for additional -- the production at Fekola from the Anaconda area.As we announced in the news, we applied for an extension of the Menankoto license, which is part of Anaconda with the government, we felt we fulfilled all the requirements and obligations to legally do that. And we're in discussions with the government as we speak about remedying the situation, and we hope to have a positive resolution of that. But we will take whatever legal means we have to us if required because we think legally, we were -- we should have been awarded there, extension of the license. So we're working to deal with any confusion on that and also working to the government on that. It's an important project for us. And in fact, as you'll hear from Bill, we have been planning to -- we are planning to be trucking ore from Menankoto Anaconda down to the separate ore down to the Fekola mill as early as early next year.Obviously, that's subject to the getting the license issue sorted out. And once again, we think there's tremendous potential in Anaconda not only for the saprolite, which we've seen in the resource, but it is also in so far, but much greater potential than the saprolite and underneath and so far it's a very good drilling attempt. So it's an important project to us. I think it's a very important project to the people and the government of Mali as well. And we're uniquely suited to produce from there to everyone's benefit, given the proximity to the Fekola well.Other than that, we're going to continue to focus on everything we've done extremely well, which is exploration. We've had great results around. I've asked Tom to say a few words today because we traditionally had great results around the mines in turning resources into reserves, increasing my like network continues, and this continues to go very well. But we also -- we have broad exploration twice and being on B2Gold. We're very good at grassroots exploration as well as brownfields. And we've got a very good exploration budget this year, a large budget, which I think is a good thing. If you look at the return on investment over let's say, the last 3 years or so, I think somebody worked up and it's about $19 an ounce for our exploration spend to several ounces of gold, our costs on the market we grow. So as I always say, the cheapest ounces will be the ones that you find. So Tom will talk about some of the exciting grassroots projects that we're doing and will touch on that brownfields as well.In addition, we're always looking at opportunities to grow. M&A has been topic these days. We've said repeatedly that for us to go into that area would have to be something that we could find value for our shareholders on an accretive basis, not anticipating higher gold prices or exploration success. That's the discipline we've had for decades, and that will continue. So we're looking in here. If anything, we transact on anything, it's going to be something that we think there's an opportunity for us to drive shareholder value.We're not likely, frankly, in a way in any bidding wars on a few pieces of us that are out there because we won't overpay. And we did some of the heavy lifting before in the sense of building with Otjikoto and acquiring a building with Otjikoto and Fekola when it was very unpopular to be drilling, but to hedge the opportunity at the time being contrary. But we continue to look at things that make sense to throw the value through from an acquisition point of view.So with that as an overview, I'll pass it over to Mike, and he's going to give us some of the financial highlights to the quarter, discuss our financial position, and then we'll be hearing from Bill and then Tom. Over to you, Mike.

M
Michael Andrew Cinnamond
Senior VP of Finance & CFO

Thanks, Clive. I think I can run through the results of the quarter fairly quickly. It was a good clean quarter and some nice results. So just starting firstly with revenues.We had revenue of $362 million on the sale of 257,000 ounces and realized an average price of $1,791 an ounce. And overall, we sold 14,000 ounces more than we'd originally budgeted, and that's really a function of having higher production than budgeted in the quarter. So total production in the quarter, including our share of caliber, was 221,000 ounces, basically, 19,000 ounces ahead of budget. Total production from our 3 sites, operating mines was 206,000 ounces, which was 18,000 ounces ahead of budget.So looking at those individually, Fekola, we produced 125,000 ounces, which is about 8,000 ounces higher than budgeted. And that's primarily a function of Fekola processing facilities, just continuing to outperform. We had originally expanded for Fekola Mine to a notional annual throughput rate of 7.5 million tonnes. We did budget 7.75 million tonnes for 2021. But in the first quarter of 2021, we had a quarterly record of almost 2.1 million tonnes, or an annualized rate of well above 8 million. So Fekola mill is outperforming, and we're seeing more production as a result.Masbate was 58,000 ounces, 7,000 ounces ahead of budget, and that's a function mainly of higher than budgeted mill recoveries. We got -- if you look at the ore or feet that was processed in the period, we had better recoveries from the high-grade sulfide ore that we mined from Main Vein in the period and also better recoveries from the low-grade stockpile that with some -- which material we ran through the mill, and that was originally mined from Colorado, but both of them had better recoveries. Then Otjikoto production was 23,000 ounces, 2,000 ounces higher than budget. And that was really slightly better on all fronts, processed tonnes, grade mine recovery.Looking at that in the context of cash costs per ounce produced. Consolidated cash costs per ounce just for the quarter is $609 per ounce. That was $54 lower than budget. And from our 3 operating mines, $581 per ounce, and that was $60 less than budgeted. And if you look at the individual components, Fekola, $503 per ounce, $55 less than budget. And the deal on budget in terms of cash cost for once is a function of a few things. It's higher than budgeted production, as I mentioned, and lower than budgeted mining and processing costs. We had lower maintenance costs at the mill in terms of -- sorry, lower budget maintenance cost for the mining fleet. And then we had lower budgeted processing cost at the mill. Higher mill throughput and lower cyanide use. Also to note, the new Fekola par facility actually came online in the quarter slightly earlier than we thought, and we think that probably benefited cash cost by approximately $4 per ounce in the period against budget.Masbate, $608 per ounce, cash cost $80 less than budget, and that's almost exclusively higher production in the period. We did have some savings in mining costs, but it's mainly driven by higher production. Otjikoto was $940, and that was $56 per ounce lower than budget, and that, again, is primarily a function of the higher production.Then turning to all-in sustaining costs per ounce sold, consolidated, including Calibre, $932 an ounce, which was $146 lower than budget. And if you look at our 3 operating mines, it was $919 per ounce or $159 per ounce lower than budget. And that's a function of a few things. Obviously, the lower cash costs, as described socking to go. And also the higher than budgeted ounces sold, we produce more and sold more, and that has a positive impact on the sort of fixed capital element when you look at it in terms of all-in sustaining cost per ounce. And also, we had lower CapEx in the period. That's mainly lower sustaining capital for -- it's really the timing of fleet maintenance and rebuilds. So it's really -- those are really the primary drivers. The capital costs, we think are just timing, and we think they'll reverse later in the year. Just to give you the individual components of the all-in cost. Fekola was $770 per ounce. That was $128 lower than budget. Masbate was $818, $194 lower than budget. And Otjikoto $1,475, which is a larger number, but it's still $240 less than budget.Just a reminder for everyone on the line. The production from Otjikoto was very significantly weighted to the second half of the year. In the first half of the year, we're processing almost exclusively from stockpiles at site while we continue to strip the Otjikoto and Wolfshag pits. And when we get into the -- those pits later in the year, especially the higher-grade components of Wolfshag in the second half of the year, we'll see that production level significantly increase.Overall, production-wise, cash cost-wise, we still think we're on target for our guidance for the year. Guidance is maintained. Again, reminder, it's significantly weighted to the second half of the year. Our production for the first half is between 390,000 and 415,000 ounces. And the second half is 580,000 to 615,000 ounces, and that reflects us getting into that, the better grade material in the second half of the year, both Fekola and at Otjikoto. Masbate is fairly consistent as it goes all the way through the year.A couple of other comments on the operation. I know Bill is going to give you some comments later, but just a couple of other thoughts. At Fekola, what's not included in the budget of that guidance for Fekola is any new material from the Cardinal area. We're currently looking at that now and what we can pull into the 2021 mine plan. But that wasn't included in our budget or guidance. Fekola Solar, I mentioned, that that came online. We did -- I think we've now managed to source the remaining solar panels and get them on the way to site. They were on a ship at 1 point where they can go through the Suez Canal. But fortunately, that's resolved. And so we're still on track to finish the solar plant by the end of the second quarter. But in the meantime, we did bring it online, the first part of it online earlier than we expected. Just a couple of comments, I think, on really income statement, good results, nothing major to highlight. The earnings for the period, $99 million. Earnings attributable to shareholders of the company, $91 million or $0.09 per share, and adjusted EPS was also $0.09 per share.And a few things to highlight on the cash flow statement. So cash provided by operating activities was $146 million. So that's pretty close to our budget in the end. So we did have a beat, as I mentioned, on the cash cost side. So the cost of our operations were lower. But offsetting that, we had some working capital movements really related to the timing of that and certain tax payments that offset that. So we ended up pretty much right on budget for the quarter for operating cash flow. And assuming a gold price of $1,800 for the full year, we're still on track, we think, for last guided operating cash flow number of somewhere around $630 million. Approximately $500 million of that will come in the second half of the year as we get into the higher-grade material and higher production, higher sales.And just to remind everyone that the second quarter's operating cash flow will be impacted by the payment of those outstanding 2020 tax liabilities. There's about $140 million worth of 2020 tax obligations that will be settled in the second quarter. The largest part of which is for Fekola, about $125 million of that total relates to either Fekola taxes or priority dividend payments, which are triggered as a tax. And we'll also have, in addition, that $140 million, we'll also have some other withholding tax payments we'll make for monies that we're going to pay -- remit up from sites as dividends to pull us the amount of cash up from sites.A couple of other things to highlight in the cash flow statement. Dividends to shareholders during the quarter $42 million, USD 0.04 per share. We're pretty comfortable with our dividend level right now, annualized, it would be USD 170 million. We are paying one of the highest dividend yields right now in the gold sector. And it's a significant component of our 2021 free cash flows. So we will look at it again in the second half of the year. But as I mentioned, I think we're pretty comfortable with that level just now.The only other couple of items I'd highlight on the cash flow statement, investing activities, just under $60 million for the period, that's about $18 million less than budget. And as I mentioned in the all-in sustaining cost discussion. Some of that's timing on CapEx for mobile fleet and rebuilds at sites. We think that will reverse later in the year. And on the non sustaining side, we were under fairly significantly. Gramalote was under $6 million. It's under budget, but we'll continue to work on the feasibility study, so we expect that will reverse. And in fact, as we noted in the news release, we are currently in discussions with AGA about increasing the feasibility study budget by approximately $34 million. So our share would be $17 million higher than we've currently budgeted. And that would take us through to the end of the first quarter of 2022 when we expect the financial feasibility study.Also, under on the CapEx side, we were about $5 million under in the quarter in exploration. That's just a function of timing. Again, and we expect that to reverse later in the year. And so overall, we finished Q1 with $512 million in the bank and $600 million undrawn. We've got the full amount of our revolving credit facility available and available to draw. And so we're in good shape, cash wise, liquidity wise, and it was a good solid production quarter and results quarter. So I think those are the main things I was going to highlight there. So thanks.

C
Clive Thomas Johnson
President, CEO & Director

Thanks, Mike. Bill, over to you, give us an overview of operations and review and a bit of an outlook for highlights from operations and what we're looking at going forward.

W
William Lytle
Senior Vice President of Operations

Yes, sure. Thanks, Clive. Can you hear me all right?

C
Clive Thomas Johnson
President, CEO & Director

I do.

W
William Lytle
Senior Vice President of Operations

Yes. Okay. Well, thanks. A lot of the stuff certainly was either handed at by Clive or by Mike, maybe I can just provide a little more color commentary to the actual operations.If you look overall, obviously, we're quite happy with how everybody did at all 3 operations for the quarter, every site exceeded a budget. And we really didn't see any downside as far as working forward into Q2 and into the second half of the year.Kind of going mine by mine, if you look at Fekola, great quarter. As far as development, I think everyone is aware, we previously said that our budget was run at 7.75 million tonnes per annum. We put out in the press release that, obviously, the mill is running much better than that. We're still holding at kind of what we're saying is 8 million plus, but our life of mines are due here in the middle of the year. So we're going to take a good hard look at what we think that number is going forward. We certainly believe that we've got some potential to add quite a bit of saprolite from both the Cardinal and from the Menankoto or the Anaconda area. Discussing Cardinal specifically, we did receive our bulk sample approval, so we are right now out there starting to strip it and -- or will be heading to the mill or already has started heading to the mill, I think, or if not, it's imminent. So we certainly see going through the rest of Q2 and into Q3, we will be developing that. And of course, as Mike insinuate or discussed. We see in 2022 and 2023, the potential for additional ounces to come from Cardinal, which are not in our current life of mine.And the same story kind of holds true for Menankoto. We -- from the operations perspective, we're assuming that the current situation is resolved. And we believe when it gets resolved, that we're going to see truck saprolite into the Fekola mill in 2022. And given the fact that we have a large additional capacity for the mill, those numbers could be quite significant as far as changing the life of mines. So once that's resolved, I think in Q3, we're talking about coming out with what we want to do there and putting it into production in 2022.And it's also -- I think it's important to note, while we're talking about trucking to Fekola, we see that as like Phase 1 of the project. Tom's group continues to drill out there. And we continue to have some success as far as looking at the hard rock. And so once we get the Phase 1 studies complete and get it all set up for trucking, we really want to take a hard look and is there a potential to put another mill up in that area. And so that's kind of -- that will be the emphasis once we finish the trucking study and get that all put to bed. We'll move on to what does the trade-off look like trucking versus putting a mill up there.Real quickly on the solar side, Mike hinted at it, but solar plant is up and operating really well. I think we've been publicly stating that we're kind of in 75% completion, but the reality is we're probably higher now. We've seen great returns on that solar as far as reducing our power cost. And we believe that in Q2, we're going to finalize that, and we'll have the full benefit starting in Q3.Going to Otjikoto. Otjikoto once again had a really nice quarter. No issues as far as mining or milling, right on schedule. The development, as Mike pointed out, the key is the second half of the year, the development for getting into Wolfshag 3 remains on schedule. We don't see any issues there for meeting our targets. The underground remains -- while it's a little bit behind, we still see gold coming out as projected in Q1 of 2022. So overall, no issues at all Otjikoto.Maybe one of the things to talk about is we are in the process of connecting up our overhead power line, that facility, the power facility at Otjikoto operates in stand-alone configuration, it's an Island. We believe by connecting to the overhead power line that we'll be able to continue to reduce power costs that are significantly throughout the rest of the life of mine by taking the off-peak power prices, which I saw something, I think it reduces almost $0.04 a kilowatt hour for those hours that were on the off-peak hours.Looking at Masbate. Masbate, once again, a great quarter. That's -- I continue to say that's a project that is probably just day in and day out, just performs as designed. We continue to see better recoveries and better grade at Masbate as we say every quarter. And that certainly can -- that contributes towards the over production for the quarter. The rest of the year there is kind of business as usual. We're in the process of developing another lift for our tailings. That remains on schedule. So overall, on the operational side, everything completely as advertised and as predicted.Maybe talking a little bit, as Clive asked a little bit about Gramalote. I think it's important to talk -- to start out talking about what the feasibility was trying to do and really get our head around why we've now talked about on handcuffing, maybe the project design from what the pre-feasibility was. When we took over the project, we agreed with AngloGold that we were going to basically hold the design. And the reason was is they had already pulled a construction permit. So the footprint had to remain the same. And we basically had to just try and optimize within the existing footprint. What we found very early on is that there was a lot of things that we wanted to do. And some of these things were quite significant, things like diverting rivers in a different direction, moving infrastructure facilities, taking a look at the tailings, tailings pond. And in order to do that, we would have been required to open up the permit. So we've decided to go ahead in maintain the same footprint but keep a log of where we were going and what we could change.And so when the feasibility was done, remember, there was -- one of the key things was upgrading the resource from inferred to indicated, and that was very successful. And then updating the cost, when that was all said and done, we looked at it, we said, while this project is positive, we certainly think that there's a better project here. And so we presented it to AngloGold. Anglo agreed with our concept. And basically, what we decided is that we were going to do some additional drilling because we thought there was some further potential for -- to increase the resource up to indicated. We were going to take a look at the engineering design as far as taking the handcuffs off and moving things around. And we thought it was still critical because we do think this is a project, and we do think this is something that we can move forward quite rapidly once we get what we're now considering kind of the updated feasibility.We wanted to make sure that the social aspects continue to move forward. So things like resettlement. We've been talking with Anglo, and we've been talking to the government about how we can make sure that, that stays on track. There we are -- Colombian government is in the process of formalizing some artisanal mining within the region. That's a very positive development. So we wanted to continue to support that. And we wanted to make sure some of the critical path items, things like bringing the power line into the region continue to move forward. So all of these things, we put together as a packet for AngloGold. Conceptually, they agree with the concept, and we provided a budget to them. They're in the process of having to look at that. And we think very shortly, we will continue to move this project forward. We see the updated feasibility study coming out at the end of Q1. And obviously, if it's positive, we would mobilize shortly thereafter. And I think it was Clive that talked a little bit about. It's really important to remember the difference between our proposed new schedule and what the actual schedule was, was not that different because when we talked about kind of doing the B2A when we were going to do concurrent resettlement, the government came back to us and ask for us to do some additional stakeholder engagement and to have them review the results of that stakeholder engagement.So we saw the potential for a 6-month delay in any case. So we're not really that far off of that schedule. Talking -- moving maybe now to Kiaka, I'm not going to spend too much time on that. As we've said, and we've continued to message, we do believe by the end of Q2, the results will be out, we will be discussing that. Clive, is there anything else that you want me to talk about?

C
Clive Thomas Johnson
President, CEO & Director

Hello? I think I was on mute, of course.

W
William Lytle
Senior Vice President of Operations

That's okay.

C
Clive Thomas Johnson
President, CEO & Director

Yes, thanks, Bill. I think that's a good survey. And maybe for the interest of the people on the line, maybe just talk a little bit about some of the issues between the PEA and the feasibility work. Now the study when it comes on next year will not be an updated feasibility study. It will be the feasibility study. So now we've done the feasibility work that's given us some economic indicators, but we have not completed the study. I think it's an important point. But can you maybe talk a little bit about some of the differences between the PEA and what we're seeing now and the feasibility work that we've done, some of the factors behind that?

W
William Lytle
Senior Vice President of Operations

Yes, sure. I mean, some of the key ones relate to the resource, as I said. Obviously, for a 43-101 feasibility study, we can only use indicated. And we did the modeling only on Gramalote Ridge. And it didn't include the oxides in that. The pit design itself has changed a little bit based on some Geotech issues related to the pit design. But the mining itself, the mining rate and the mining design remained exactly the same. On the milling side, we believe that we have a more elegant and more efficient milling process. We have looked at -- it certainly was cheaper. We've included some additional equipment that weren't -- that wasn't in the pre fees, and that's just due to level of detail. The tailings facility remained exactly the same. Power, overhead power lines come in. Some of the key cost drivers, which had changed things like the power cost was slightly different. We had updated some of the cost due to inflation. And then one of the key ones, as you talked about already is resettlement. We wanted to move people out sooner instead the way that the pre-feasibility had the resettlement was that it had a really long period where you had to complete -- fully complete resettlement before you could start construction. And as I said, we were looking for concurrent resettlement. There the issue there currently is a river that flows right through where the existing pit or where the future pit would be. There's a big tunnel where they diverted that. We think that there's a potential to make that a better project. So some of these issues -- yes, those are the key differences.

C
Clive Thomas Johnson
President, CEO & Director

Okay, thanks. Yes, I guess just maybe on -- from a strategic and a corporate point of view, we're quite well-known for being aggressive and there's a big different between being aggressive and being reckless as I point out to people. But in terms of the way we approach projects the way we do it very safely and responsibly, and but do it really quite often quick -- more quickly than some others in the industry may move. I think this is a -- this is perhaps an example and some people recognize that of our discipline. And we have a project that has some positive economic indications, albeit not as robust as it was before. But we took a look at it and say, well, what's the best thing to do? The best thing to do here because we're famous for building quality projects based on quality work and attractive economics. So that continues. So this is an indication perhaps if anybody needed to know it, and I don't think they should have needed to know given our presstitute, but in the example of our financial and corporate discipline, where we think we can make it a better project, and our partners and ourselves are prepared to believe in that concept as well. We are prepared to spend some money to do it. So at the end of the day, the delay is appropriate to do a lot of very good work and then have a look at what comes out. We're hoping we're going to have a significant improvement from the economic indicators, they're while positive, we're not to do about lead our threshold given the track we see so much upside or significant upside potential in the work that we're going to be doing.So thanks, Bill, for that. And I'd like to pass on to Tom Garagan now to talk a little about some of the things he's excited about, about our large exploration budget this year and some exciting new countries and targets for us.

T
Thomas Alan Garagan
Senior Vice President of Exploration

Thank you, Clive. Hello, everybody. As you know, we have an exploration budget this year of some $66 million to be spent, not only on our main projects, but also in grassroots exploration. In fact, in the grassroots exploration, we're looking at just over $27 million.Just a brief comment on the exploration around the mines. At Masbate, we're continuing to drill on the pit edges and the deeper portions of the pits where the pits get bigger with the better gold prices that we're seeing now. In Mali, we're continuing to do exploration down plunge on Cardinal remains open, and we'll continue to do exploration in the Anaconda area as that area remains open.In Namibia, our exploration is almost exclusively focused right now on what we call the OTG-23 Zone, which is about 100 meters away from Wolfshag. We'll have more on that later as that work continues, but we view that as a positive sign for Otjikoto.And just in the grassroots exploration, we're talking about significant budget, within that budget, we're talking about over 30,000 meters of diamond and RC drilling on some of our newer targets. I'll mention specifically, we'll start with Uzbekistan. It's an area we've been looking at. I hate to say this is a kind of basin a little bit. But for probably close to 15 years digging back to the DENR days, it was an area we had visited back then, when we continue to work on relationships with government and geologists in that country. And that led to us a few years ago being awarded some licenses in the country. The license we have are right near 3 world-class ore bodies, Muruntau, which is a everybody -- there's a large variety of numbers related to that, but basically the world's largest gold mine at over 2 million ounces of production per year. And then there's 2 other 10-million ounce deposits in the immediate area. Our work in the area to date has been trenching, order drilling and some lab programs. And we're just about to start a 10,000-meter RC program this week. And this will be fall away during the year with diamond drilling. This is an area of world-class deposits. It has not seen a lot of exploration outside the exploration being done by the local government components. We're very excited about this area.In addition to that, in Finland, we have almost 8,000 meters of diamond drill planning on our property. We're currently earning -- we've already earned 51% from the line, and we're up -- we're getting close to having earned our 70% on this project. We're excited about the area it's on a stretch with new discovery called [ Vaccari ] and the geology of [ Vaccari ] continues onto our ground, and we had some decent gold anomalies in our overburden drilling and our till drilling and then also some of our soil sampling and certainly rock sampling. So we're excited about the potential for that, which is that hold something.Something new this has come up just recently, we've been awarded licenses in Egypt in the historic mining area. Those licenses are just being papered right now. So I don't have too much detail on that at this time. We'll have more later, but it's an area we've been, again, been focused on for several years of doing grassroots exploration and evaluating the potential of that area. So we are excited about it. And then we'll continue doing grassroots exploration on other targets that in other areas of the world that hopefully will be available for more discussion later on this year. Thank you, Clive.

C
Clive Thomas Johnson
President, CEO & Director

Thanks, Tom. Appreciate it. I think -- operator, I think we're ready to open up for questions now.

Operator

[Operator Instructions] Your first question comes from the line of Tyler Langton from JPMorgan.

T
Tyler J. Langton
Research Analyst

Just to start with, I guess, Gramalote. I mean, can you talk a little bit about to kind of make the economics more attractive, just the importance of either sort of increasing production at the project or kind of lowering operating costs or capital costs? Just trying to get a sense of maybe kind of what's sort of the most important or bigger focus.

C
Clive Thomas Johnson
President, CEO & Director

Sure. Bill?

W
William Lytle
Senior Vice President of Operations

Yes, sure. So certainly, we see some potential for capital reductions. That's one of the big ones. Another one of the big ones relates to increasing the ounces that we can generate over the life of the project. And this includes kind of a drilling program within the existing design pit. There was some -- there were a few ounces left within the existing pit, which in the inferred category. And then just outside of the proposed pit, which would be in the measured indicated in inferred category. So we see those 2 things really as some of the key economic drivers. And in particular, if you look at the CapEx, as I said, there were some -- mostly related infrastructure projects where we think we can bring the cost down, things where maybe the project has been going -- been designed for like 10 years now where people kind of lose focus on if you had a blank sheet of paper, could you optimize things. And that also relates to certainly the constructability of the project. And so those are some of the things that we're looking at. As far as the OpEx, we don't see a lot of changes that -- between what we have now and versus what we would have a year from now.

T
Tyler J. Langton
Research Analyst

Got you. Okay. That's helpful. And then maybe switching to Fekola. With Cardinal, I think maybe last quarter, you talked about that mine potentially contributing, I think, 20,000 to 25,000 ounces kind of in Q2, and that would be kind of the main contribution for the year. Is that kind of still what you're thinking? Or I think maybe I heard some comments talking about maybe contributing in Q2 and Q3. Could you just provide some more color there, that would be great?

W
William Lytle
Senior Vice President of Operations

Yes. I think what I said was, hopefully, what I said was 20,000 to 25,000 ounces over 2021 starting in Q2 from the bulk sample, right? So we're talking about 20,000, 25,000 ounces out of that bulk sample. But I will say that it looks to me like we're -- while we do not have it yet, and I must stress that. And I should also stress that that is an inferred resource that we see starting really right now through the end of the year, we're going to start mining at Cardinal. And so there is potential that it could be a little bit more than that.

Operator

Our next question comes from the line of Ovais Habib from Scotiabank.

O
Ovais Habib
Research Analyst of Mining

Congrats on a good quarter. First couple of questions, Clive are on Gramalote. And this is, I guess, I can direct to, Bill. Not -- you've already answered a lot of the questions I had, so good overview on that front. But in regards to the additional, I guess, extended resettlement, just to make sure that I understand correctly, was this due to additional footprint need to be added? Or is this resettlement always in the plans or on the works?

W
William Lytle
Senior Vice President of Operations

No, it was always -- even back in the AGA days, there was quite a big resettlement, which went along with it. We certainly have provided now more detail around that, and we're in the process of really working through our Resettlement Action Plan. So a RAP has been developed. And the difference really was, as I said, there was a condition precedent for the construction permit, which basically said you had to do all of the resettlement. So everywhere, in every region, you had to move everybody out. And what we realized is that there was a big chunk of it which we could do. And then we could start construction, and there were some people on the periphery that we could then deal with as we got to that area. And so that's really the difference. But the overall resettlement is basically the same. There are some people that are saying that they're in there, some people saying they're out. But in general, the quantum is pretty close to the same.

O
Ovais Habib
Research Analyst of Mining

Got it. Okay. And just kind of talking about the optimizations that I expected. Is the plan basically to get close to the economics shown in the PEA before going to green light to the property? What I'm trying to ask is, is there a point where you would kind of walk away from Gramalote? Or is this kind of -- where is the point where you would make a decision essentially is what I'm trying to ask.

W
William Lytle
Senior Vice President of Operations

Clive will probably answer that. From an engineering standpoint, I mean, all we want to do is we want to make sure that it's got the best economics possible and that it's most easy for us to build.

C
Clive Thomas Johnson
President, CEO & Director

Yes. I think we are going to spend a significant amount of money in addition with our partner, and we're expecting to agree in a new budget, as we've talked about in the news release. So we definitely are doing that for a reason, and the reason is because we think we're seeing enough indicators. As Bill says, when you start taking the handcuffs off the engineering side and the design side of things, that we see significant potential to make it a project that we would want to go forward with. So the economics today are positive. I mean I guess some companies might use mechanisms like hedging, et cetera, to maybe look at making those things better potentially. But that's not where we are in the sense of we're looking at it from a technical point of view, saying we think we can have our ounces. We think we can lower the capital. If you look at the all-in sustaining cost based on the current economics from the feasibility work, I think it was somewhere around close to the mid-7s. So attractive project from that perspective, can you add more ounces, can you lower the amount of capital and add to that 15% IRR. So we wouldn't be -- I mean ourselves and AGA are companies, I believe, I can't speak for them, but I believe that we are not companies that would continue to pursue something if we thought we were sort of flogging a dead horse or just giving false hope. We really see an opportunity here to make this a project that we would want to develop.

O
Ovais Habib
Research Analyst of Mining

Perfect. I have a couple of more questions, but I'll let others ask questions and then jump back in the queue.

Operator

Your next question comes from the line of Geordie Mark from Haywood Securities.

G
Geordie Mark
Co

Good quarter. Maybe if I can expand on some of Ovais' questions. Not to belabor the point. Just in terms of the change in budget, is that largely drilling expense related in addition to the 18,000 meters that was already planned this year?

W
William Lytle
Senior Vice President of Operations

Do you want me to answer that, Clive?

C
Clive Thomas Johnson
President, CEO & Director

Yes.

W
William Lytle
Senior Vice President of Operations

Yes. So Geordie, there's kind of 3 components there, for sure. You're right, there is a big chunk of drilling, which goes along with that. And I can let Tom or Brian kind of maybe give more clarity there. But there's also the engineering component, which is more just the actual consulting and engineering aspect of it, and then if -- there's a social component. And like I said, we do want to push forward some of the key social issues. And so we have put some money in there for things like basically preventing some sort of inflation happening with resettlement, purchasing land packages now, making sure that we've got the right areas available for resettlement. Those types of things also will take up a chunk of the budget.

G
Geordie Mark
Co

Okay. Brilliant. And then there's also a mention of the power line. Is there -- is that in terms of trying to bring that online to basically move the project forward or the project timing forward and progress with optimization?

W
William Lytle
Senior Vice President of Operations

Well, what we know is the power line is absolutely on the critical path regardless of what happens, right? So we've been in negotiations with a couple of power companies down there and have picked a group that we'd like to do the studies for. So they have to go out now and do a full ESIA. They have to do all the engineering, and basically, they have to design the route on the site. And so they're talking about something like a 28- to 30-month schedule to do that. So we decided, at this point, we're going to put a little bit of money at risk to get those studies going. And so that's what that is.

G
Geordie Mark
Co

Okay. That's excellent. And in terms of -- if we stay on power, move over to Fekola, I see obviously Fekola at 2/3 solar panels is heading beyond capacity. Is that right at the moment or nominal baseline at least? And with additional -- the additional -- with the final 25% panels in place, do you expect any linear sort of capacity increase there? Or you kind of met with battery storage sort of limitations there for delivering more power into the local group?

W
William Lytle
Senior Vice President of Operations

Yes. So I'm super bullish on this. So I'm going to pass that one on to probably John Rajala, who's really more qualified to answer that.

J
John Rajala
Vice President of Metallurgy

Yes. We'll plan on trying to maximize our solar power usage. Only 75% of the capacity is online right now. So because of -- we lost some panels, about 25% in the fire, and they're going to be on-site very soon and then installed, we plan on having that in operation by around the end of June or so. So we'll be up to 100% of capacity and hopefully increase -- we should be able to increase the amount of power -- solar power contribution from that. Does that cover that?

G
Geordie Mark
Co

Okay. I was just wondering if it's going to be beyond the original expectations given the performance.

J
John Rajala
Vice President of Metallurgy

Well, we think we have a good shot at it. We've been exceeding expectations just with 75% capacity in operations. So hopefully, we'll be able to continue that with the additional solar panels installations.

G
Geordie Mark
Co

Okay. That's great. And if I can just indulge one more. Moving over to Kiaka, obviously, experience on solar power and looking at a dual LNG/solar source there. And what sort of capacity you're thinking for that power plant?

C
Clive Thomas Johnson
President, CEO & Director

Dennis, you want to talk to that?

D
Dennis Robert Stansbury

Yes. The power plant we're looking at for Kiaka is a combined LNG/solar plant. We're currently looking at about 30-megawatt plant, very similar to Fekola for that right now. In optimization, you might want to kick that up a little bit, but it's in that magnitude.

Operator

Your next question comes from the line of Josh Wolfson from RBC Capital Markets.

J
Joshua Mark Wolfson
Analyst

Bill, earlier on the call, you mentioned that the Anaconda trucking study was going to be continuing on this year. Could you clarify what the permitting challenges there relate to? And I guess it sounds like you're still able to proceed with Anaconda. Or if not, what the sort of implications are in advancing that opportunity?

C
Clive Thomas Johnson
President, CEO & Director

Bill?

W
William Lytle
Senior Vice President of Operations

Yes. So I'll talk -- as I said, so I think Clive was pretty clear that we're kind of working through what our permitting issues are right now. But what we've always said is it is a separate license, right? So it would have to go through the full permitting. And we're working on those studies right now. So obviously, for permitting, you would need a full ESIA, which we're in the process of completing right now. You would need some sort of feasibility study. And what we're calling that is kind of a Phase 1 aspect of the Anaconda project. All of those, it is our intent to kind of complete those in Q3. And then you would have to go and look at what the license conditions would be for actually bringing the product up, how it would be for tolling it through Fekola. All of those things would need to be discussed. So that's why we're talking about really you're probably -- with the exception of maybe a bulk sample, you're probably not going to see any ounces, best case, probably in the second half of 2022 being trucked.

J
Joshua Mark Wolfson
Analyst

And that -- just so I understand that, those ounces that would be produced, the Menankoto permit, the issues there do not affect the ability to truck the ore to Fekola?

W
William Lytle
Senior Vice President of Operations

All that stuff has to be resolved before we could do it, for sure.

C
Clive Thomas Johnson
President, CEO & Director

There's a few different licenses there though. There's been other licenses that are not impacted by this current discussions going on with the government about the Menankoto license. But yes, clearly, we should be very clear about that, we need to resolve this issue with the government about our right to the extension of the license. And I'm hoping to resolve that shortly.

J
Joshua Mark Wolfson
Analyst

Okay. And then looking at Kiaka, any update that's going to be coming out? I guess we won't have the updated Gramalote numbers until early 2022. What's the potential for the team to look to advance that project in the second half of this year, either in lieu of Gramalote or even alongside it, assuming Gramalote proceeds next year?

C
Clive Thomas Johnson
President, CEO & Director

Yes. That's -- I mean we haven't got too far into that yet because we're waiting to see the results of the feasibility study in Kiaka and to see whether it meets the threshold for us to go forward. We're going to know that by the, as I said, middle of the year. But yes, conceptually, if it was a positive development decision there, we can look at -- we talked before about the potential for if they were both positive, Gramalote and Kiaka, we wanted to develop both of them. We talked about various possibilities. One would be to sequence the construction team. We'll never build 2 new mines at the same time. That's one of our rules. It's been key to our success. We've got one great team, but you can also look at potentially using the team for earthworks. Initially, let's say in Gramalote [ with Jack ] and then moving that team to the next one, whichever one you do it. And then similarly, the mill construction team, when they complete one project could move to another. So all of that, of course, is based on the final feasibility at Gramalote and also with the feasibility study -- the updated feasibility study we're working on right now that will be -- we expect to be prepared to release in the middle of the year at Kiaka.

J
Joshua Mark Wolfson
Analyst

Understood. And one sort of final one. Just in the language in the release, the comments about Gramalote and, I guess, the expanded footprint that could require the permit modifications, that not affecting the license but that potentially affecting the implementation schedule. Is that just for, I guess, the project as it was if it was advanced this year? Or does the potential footprint change and the permitting changes affect the implementation schedule if it was advanced next year as well?

C
Clive Thomas Johnson
President, CEO & Director

Bill, you want to answer that?

W
William Lytle
Senior Vice President of Operations

Yes. Yes. It's -- the language maybe is not quite as clear as it could be. So what we're really talking about, the way it works in Gramalote or in Colombia is that they kind of have 3 levels of permit modifications, right? So they're just kind of insignificant. And these are things like when the resolution of your topography gets better and your road has shifted just a little bit, right, there's no real kind of major social or environmental impact change. And those are kind of you do on the fly. And then there's these minor modifications where it might be where you're moving something around just a little bit. And once again, there's no significant environmental or social impacts or potentially positive social or environmental impacts. And those have a small review process, and you can kind of do those on the fly. And so those are the things that we've always been talking about inside of the existing permit we can do. Now what we're talking about is kind of, as I said, taking the handcuffs off and looking at what we're calling potentially major permit modifications, where you're actually taking structures and maybe moving them into a different valley or moving an access road somewhere else, which have real impacts, which have to be investigated. So as we go along for the engineering process now, we've got to start looking at, okay, this is really optimal. This is how much money it could save us. Is it worth trying to get a permit modification to do that? If it is, then you start talking with the government what would it take as far as updating your impact assessment. So all of those things are now going to be in play as opposed to us just saying, okay, we're going to keep it to kind of these nonconsequential or minors. Now we're talking about -- let's talk about majors. I don't like that -- the phrase that we're increasing the footprint because that's not necessarily the case. What we're actually doing is we're kind of modifying the footprint. And in that modification, we may be changing the potential social or environmental impacts and those need to be evaluated.

C
Clive Thomas Johnson
President, CEO & Director

I think it's important to note there. We talked a bit about it earlier on, but the relationship with Colombian government is very strong. There's a very strong Canada/Colombia relationship. We've got the Minister of Mines from the government -- the government are very supportive of responsible mining. It's an important part of their economy. So we've always said Gramalote is in a great location in their mining district of Antioquia. If you flew over Colombia, where is the best place to build the first large open gold mine in the country? You'd probably pick -- you would pick Gramalote. So tremendous local support in the community, and there's some disappointment now because they thought this is going to crank up pretty quickly. But once again, if we are successful, what we're looking at doing -- this is a really important source of jobs, and there's lots of people working there now, and that continues. All that work continuous as we talked about resettlement, working at the government, small miners and other things. So between ourselves and AGA, there's been a lot of good work done here over the years. It's very important to note that. I mean I'm building these, working with the local community and the federal government and all governments. And there's a lot of support for this project. So we think it makes a lot of sense. The government gets that. And I think they're highly motivated to work with us to see Gramalote become the best project it can be and to get it built for them, for all sorts of positive reasons for the economy, local economy, but also the overall benefits to the government and the people of Colombia. So there's a lot of support for this project. And it's really important to keep that in mind.

J
Joshua Mark Wolfson
Analyst

Okay. And then, sorry, final question. I know I'm taking a lot of time here. When you think about these potential changes and modifications in the footprint, are there permitting elements that you're able to accelerate before that first quarter 2022 target date? Or does that sort of date then start the permitting process for these modifications?

W
William Lytle
Senior Vice President of Operations

Yes. That's a really good question. And the answer is we have to look at that. That's really literally what we're doing right now. As I said, it's a huge trade-off study in our mind on the potential delays as far as permitting versus the potential economic benefits. As Clive has indicated and I said already, we have a positive project now, but can we make it that much -- can we make it even better? Those are the things that we're looking at. What I will tell you is you have to remember that resettlement still kind of is on that critical path. And so we're now working through that Resettlement Action Plan. And that's really going to push us out into Q1 2022 in any case. And so how do you play around with that? That's what we're looking at right now.

Operator

Your next question comes from the line of Don DeMarco from National Bank Financial.

D
Don DeMarco
Analyst

Just building on one of the last questions. There was a mention of comparing Kiaka to Gramalote. Maybe I'd take this a bit further. And is there a chance for some of the projects that Tom talked about to take priority over Gramalote, say, over the next 12 months? I mean you've been in Egypt and Finland and Uzbekistan for a few years now. Which of these projects is most advanced, maybe even closest to a PEA?

C
Clive Thomas Johnson
President, CEO & Director

Yes. No, I think -- no, we haven't been working in Egypt or Uzbekistan for a couple of years. Now we've done some work in Uzbekistan. This is relative. And this is pretty early-stage stuff where we've done some [ larger ] drilling and things like that and some -- we're doing some reverse circulation drilling and heading towards diamond drilling as well. And both -- so they're all pretty early stage. They're really big attractive targets, but we don't want to oversell it. They're at an early stage. So we're a long way away from talking about a PEA and any of these things. But we're in an elephant country in the circumstance we're looking at. And that's the reason there. Tom, do you want to comment on that further or...

T
Thomas Alan Garagan
Senior Vice President of Exploration

I think that's pretty accurate, Clive. We're still early on in the game. But as Clive says, these are all elephant country targets. That's why we've chosen it. But I don't know that within a year -- well, for sure, not within the year, we're going to be replacing the other development projects with these.

D
Don DeMarco
Analyst

Okay. Great. Then given the Gramalote NPVs in the $500 million range at this point, and obviously, as you mentioned, there's visibility for it to grow. But is this project perhaps of a magnitude now that's better suited to one owner? And maybe if you believe in the project, is now a time to increase ownership? What are your thoughts on that? We know from your previous comments that Anglo likes the project as much as you do.

C
Clive Thomas Johnson
President, CEO & Director

Yes. I think that -- I can't speak for AGA. But we've had lots of calls recently, of course, talking about the situation, being very transparent in a good joint venture. And from what -- they took a look at our news release, what we're saying. We, of course, wanted their input into that. So they'll be coming out shortly with their quarter and their thoughts on development projects. But we're both disappointed that it wasn't as robust as the economics we saw in the PEA. But seeing the opportunity, as we said, over time and we can make that better. In terms of ownership, I think that what I've heard is that AGA is prepared to spend a significant amount of money along with us to see if we can -- with those operating to see if we can make it a better project. So I'd be a little surprised if -- we wouldn't be considering changing our ownership in it now. We've invested a lot of money and time, et cetera, and believe in the path that we're on, the potential. Also again, you can ask AGA that question in their quarter, which I think comes out in the middle of May. But the indications from sources, they are -- they want to be a player in Colombia. They've got other projects, Quebradona, et cetera, that they're pretty excited about. So they think Gramalote, what they've said to me, is an important part of what they're looking to in Colombia. And they were hoping to, with us as operator, to showcase what we could do together to the Colombian government. We still hope to be able to do that, just had a bit of a delay, as we've said here. So sure, we have always said that if an opportunity came to us, we'd consider that. From what I've seen so far, I don't see that there's going to be a willing seller. I think we'd go forward 50-50. That's -- once again, I can't speak for AGA, but that's what I've -- we've been told from them very recently.

D
Don DeMarco
Analyst

Okay. And just finally, you guys have a strong development team. You built Fekola, finished the Fekola expansion. With Gramalote delayed, is there any motivation to deploy your development team onto some type of an interim project?

C
Clive Thomas Johnson
President, CEO & Director

Well, I think that -- I think we have -- there are some areas within the company of things that we're working on, whether it be looking at expansion opportunities or other things like that, where you might use some of the team or some of the senior team in input. But we're going to go and acquire something and build something because we have a tremendous construction team that we need to keep busy. That's just not -- that's the way to run this business in our opinion. We have a great team. And the team is -- I think this team has been together for so long -- or come back together is the better way to put it. So back on the Bema days, Julietta and then Kupol and then, of course, Kinross takeover. They -- some of them worked for Kinross for a period of time. But as soon as they got the call to come back to the culture of B2, the vast majority came back. So it's like an old sort of rock band in a way where they took some time off and then they decided to do another tour. And so the whole band gets back together or most of the band, and they're able to attract other high-quality people because of that. And I think there really is a mutual respect here and trust. Our construction guys really feel valued in the company as they are, and they love doing stuff for us. So if we find the right opportunity in a situation of acquiring a deposit or whatever, of course, we'd be looking at that. Not to keep the team busy. I believe the team will be available when we're ready to go and get the band back together. But if we find something, of course, they're ready to roll.Bill, you have anything to add to that?

W
William Lytle
Senior Vice President of Operations

Yes, I would like to add to that just a little bit. One thing that people don't realize, clearly, a lot of these guys in the construction realm are very good at all of the civil-type stuff. And so some of these guys are deployed right now within -- at Fekola. Or maybe they're doing -- maybe they're doing a quick project at Masbate. But they were actually working on the operational side. One of the key secrets is that this whole core team, like the logistics team, the procurement team, the warehousing team, those people sit down on a site. And so right now, they're at Fekola, bringing up the next group. But we haven't lost them, right? They're still there. Obviously, the exciting part of mine running is the construction aspect. So everybody wants to go on construction projects, but they understand if there's not a project, that they'll sit down and wait for the next one.

Operator

Our next question comes from the line of Lawson Winder from Bank of America.

L
Lawson Winder
VP & Research Analyst

Just a question on -- obviously, acknowledging the political risk management being a core competency for B2Gold. Could location of Gramalote and Kiaka feature into which you might ultimately prefer developing?

C
Clive Thomas Johnson
President, CEO & Director

Sorry, can you just say that again?

L
Lawson Winder
VP & Research Analyst

Could the location of Kiaka and Gramalote factor into which of the 2 projects you might have a preference to develop first?

C
Clive Thomas Johnson
President, CEO & Director

Yes. That's an interesting question. I think that -- I'll go first here. But I think that we think they're both in good locations in the country that they're in. Kiaka is in an area with significant mine operations and the relatively "safer" part of the country. In the sense of Gramalote, I think I touched on earlier, we're in Antioquia, a historic mining district. Local people understand that. We've worked hard to show them what it would look like and what we're trying to do. A lot of support there, and it's a great location within Colombia, for sure. So I would say -- I don't know if somebody else can chime in here, Bill, whoever. But I don't know, I think they're both in -- they're both in attractive areas in the country. So I don't know that one would be decided over the other on that basis. So Bill, what do you think about that?

W
William Lytle
Senior Vice President of Operations

Yes. No, you're absolutely right, Clive, for sure. I mean we just like the good projects. I will tell you, most of the guys, if I'm being honest, from a construction standpoint, we've spent the last 3 or 4 years in West Africa building that project. So they'd like a new venue. And of course, the fishing is much better in Colombia. So they do have a preference.

C
Clive Thomas Johnson
President, CEO & Director

I think a few things are better.

L
Lawson Winder
VP & Research Analyst

Okay. That's a good one. Also on Kiaka, Clive, you mentioned in the past that it could be developed with a partner. Have there been any discussions in that direction?

C
Clive Thomas Johnson
President, CEO & Director

No. I think the key thing, of course, now is get the feasibility and see what it looks like. The alternatives have always been to bring a partner in, sell the asset if we don't think it's for us or we just don't want to take too much on, and there's always an alternative. So I think the key now is going to be getting the results of the feasibility study, see if it meets our criteria. If not, then if somebody else is interested in it, potentially. All those options are still on the table, but it's hard to have those discussions until you really know the economics of the project.

L
Lawson Winder
VP & Research Analyst

Fair. And if I might, can I just ask a question on the Menankoto permit? In terms of what's going on in the ground there, has this third party that now has a license already started exploring? And a follow-up to that, are you able to share with us who the third party is just in terms of -- like are they a junior? Are they a local company? Are they a major mining company? Maybe you can't share that, but if you could, it would be helpful.

C
Clive Thomas Johnson
President, CEO & Director

Yes. I think, obviously, we're in that process and have them for some weeks of having extensive conversations with the government. And we feel we've had some positive indicators from those discussions. It's a small Malian company, frankly, without a history of mining construction expertise or financial strength. So at the end of the day, we just feel that -- I do want to point out, and I think I mentioned it earlier, but the history of Malian gold mining, it's been a really good place to do business. And I've said this many, many times. If you go back to our mine opening up many years ago, and this is in a speech of the President at the time, it is tremendous, and the government support is really great and a mutual trust relationship. We delivered on the promises we made, which is what we try to do always. And we're transparent with the government and very respectful. Really good relationships. And I think if you look at -- talk to Mark Bristow and look at the Randgold experience and the Barrick experience, he's argued for decades, and he got it right. He got there early and was contrarian and it paid off really well for the Randgold shareholders. He says the same thing, that it's one of the better -- it's a really good company to work for with the government. They understand the importance of gold mining for their economy, hugely important, never more than today when you look at COVID, et cetera. And they've always honored their laws. It's not -- there aren't many countries in the world where you actually have a mining convention as we do in Mali, [ the marks ] in your taxes for the duration of your project, the tax regime. And back in the only days, Randgold had some pretty attractive tax deals. They were typical in the industry at the time, putting in things like 5-year tax holidays, relatively low royalties, but the government never ever attempted to change the tax structure in those mining conventions. And those mining conventions are backed up, and if you have issues, you end up in Paris to deal with them. So that means that we've gone there. And this new government, we've had success in working with this new government within the Ministry of Mines, the civil service there, who many of them are the same, and getting things like permits for bulk sample, permits for other things. So this is one that we feel -- as we said in the news release, we feel we have right to the extension of the Menankoto licensing. That's what should have happened. And we're working with the government to really show our side of that story and that argument. We spent $27 million there. And the really logical thing for Menankoto and for everyone, including the government that will own 20% of Menankoto and owns 20% of Fekola, the clear, better thing for the vesting for the people of, we believe, of Mali and our shareholders is -- and the government with their ownership is to see that Menankoto ore trucked down to Fekola, and we think we have a legal right to that license. So we will take legal -- working cooperatively with the government, respectfully, just to solve this situation. But we will take the steps to defend our rights as required as we go through the process. So our hope is to resolve it through discussion and get back to work. We had scheduled at least $8 million of work in the Anaconda area. Some of it's ongoing to the north of the Menankoto license. So we're still going. But this is an important part of the potential to even further improve Fekola but also is there another Fekola there. We see a lot of potential there. So yes, the history of Mali has been very good. And I've been very strong in my view of saying to shareholders and people that don't -- as my father used to say, all people that generalize are wrong. Don't generalize about Africa or even West Africa. Look at the situations and where they are. Mali has had centuries of gold mining. They get it. The governments have always gotten it. We're looking for this government to continue the tradition that the Malian governments have, which is honoring the laws and seeing the importance of gold mining and future gold mining investment in the country. So that's our position today, and we're having some constructive conversations around that and hope to see the situation resolved.

L
Lawson Winder
VP & Research Analyst

Okay. And I just realized it's a quarter past the hour or so. I had one more, but I'll try and ask it really quick. I think this is for Mike. Basically, in January, you guys guided to much higher H1 unit cost and Q1 came in well below the low end of what your guidance was. Is it fair then to expect a very material increase in like all-in sustaining costs in Q2?

M
Michael Andrew Cinnamond
Senior VP of Finance & CFO

Well, on the operating side, we just -- we did better, right? If you look at the factors impacting the better cash costs this quarter, they're better recoveries that we just didn't model, right? So we expect it we'll keep those -- the benefit of those as we run through. And then like lower input costs at Fekola for things like cyanide. So again, we expect to keep the benefit of that. So I think some stuff will roll forward and just benefit overall. You shouldn't just push it all in the second half of the year. The guidance we gave for the second half of the year, we think, is still good. And then on the all-in side, it was the benefit of those lower cost, higher production, which we think will lead to that higher production as we roll through the year. And then some of it was that CapEx versus timing. So you will see that what we don't spend in H1, we still expect to spend in H2. So on the CapEx side, yes, those costs will just roll over into the second half. On the OpEx side, most of those benefits, we should keep.

Operator

Your next question comes from the line of Carey MacRury from Canaccord.

C
Carey MacRury
Analyst of Metals and Mining

Maybe just one more question on Gramalote. I think the all-in sustaining costs were about 15% higher than the PEA. How much of that is underlying cost inflation versus maybe just fewer ounces in the plan? Or is there some other factors driving that change?

C
Clive Thomas Johnson
President, CEO & Director

Who wants to answer? Bill or Mike?

W
William Lytle
Senior Vice President of Operations

Yes. So the all-in sustaining cost will be up a little bit because of some inflation, for sure, particularly related to, as I think I've mentioned, labor, power and fuel prices versus what the PFS/PEA had.

C
Carey MacRury
Analyst of Metals and Mining

Is there any context maybe on like what the dollar per tonne difference is? Or...

W
William Lytle
Senior Vice President of Operations

Maybe I can dig that up. I don't have it right here at my fingertips.

Operator

Our next question comes from the line of Anita Soni from CIBC.

A
Anita Soni
Research Analyst

I only have one question left, and that's with regards to like Gramalote. I know it's a broad question, but can you give me an idea of the timing, how long it takes for permits in Colombia? I'm not as familiar with Colombia.

W
William Lytle
Senior Vice President of Operations

Yes. Yes. So as I said, there's kind of 3 levels. And we've had some pretty in-depth discussions with the government on these particular issues. And so you're kind of looking, as I said, for the insignificant ones, those are on the fly. The minor ones might be kind of in that 3- to 4-month range for review and approval. And I think it's 6 to 9 months on the majors from the time you submit.

A
Anita Soni
Research Analyst

Okay. And the last question. I know also very early stage, but as you think about a construction decision, what are you looking at for a construction time line on this one?

W
William Lytle
Senior Vice President of Operations

Well, I'll just say we were always talking in that 30- to 36-month range. I don't -- I can't think of any reason why that would change.

Operator

Our next question comes from the line of Jared Hoover from Morgan Stanley.

J
Jared Hoover
Equity Analyst

I know there's been a number of questions asked on Gramalote, but I just wanted to get 2 more in, please. And it seems from a lot of the commentary that the 2 main points that are going to result in potentially better economics on this project is around infrastructure and how you can move that about and optimize that. And the other is potentially increasing the life of mine production. But if I look at the 2 pits Monjas West and the Trinidad pits, it looks to me like those are lower-grade pits. So if you have to bring it into the life of mine, it seems like it would automatically increase our costs. So is it more a case of, yes, you potentially bring that into life of mine, but it's more a case of your -- you having to look at the recoveries around that project and that potentially enhancing the economics? So if you could just chat to that, please. And then my second question is just around your partner, AngloGold. If for some reason it doesn't meet their particular hurdle rate and they want to maybe sell the project, are there any mechanisms that would allow them to -- or in your agreement with them that could allow you to potentially pick the project up like the full 50%? Or would it be in stages, sort of 10, 20, 30, et cetera? So just if you could chat to that, that would be very helpful.

C
Clive Thomas Johnson
President, CEO & Director

So in the second part of your second question, you were saying -- I didn't quite get that. Are you asking whether we think AGA would be amenable to us purchasing some of their interest in stages? Is that the question?

W
William Lytle
Senior Vice President of Operations

And is there a mechanism to that.

J
Jared Hoover
Equity Analyst

Yes. Just in the case of ending -- or a one-off, the total 50%.

C
Clive Thomas Johnson
President, CEO & Director

Right. There's a mechanism, yes. Okay. Bill will answer the first one, but I'll answer that one maybe first, the second part. Yes, there's a mechanism in the agreement where if you make a -- if we put forward a development plan as operator and AGA has a limited period of time, I think it's 30 days, to respond -- both parties to respond to deciding to fund that development plan. Whether there's a mechanism whereby you can purchase the other 50%, either party can based on fair market value, based on the feasibility study that the development decision would be based on. In addition though, there is a provision where either party can go down to 30%. There's a mechanism where it can go to 30% if you want to stay above the project but not have the full 50%. So there is those mechanisms that work both ways in the agreement. And Bill, you want to answer the first?

W
William Lytle
Senior Vice President of Operations

Yes, sure. So you are correct, Monjas and Trinidad currently, their resources are lower grade. And I guess internally at this point, we see those as potential out near the end-of-life of mine is kind of upside to extend the life of mine, for sure, and that really wouldn't do a lot for your NPV. But what I was talking about when I was talking about drilling is we're talking within the Gramalote Ridge area just outside of the existing design pit and even outside of that in the measure indicated and inferred. We see some potential to increase the NPV and the IRR by bringing inferred ounces into the indicated, which, of course, then allows us to put them in the 43-101. And as far as the infrastructure, you're correct, that was the other issue.

Operator

Your final question comes from the line of [ Charles Rahl], shareholder.

U
Unknown Shareholder

Much of what I was going to ask about has to do with the problem with Mali, I guess. So that's been answered. The only thing I would ask you to do is I've been asking for a copy of your annual -- what do you call it, your annual information form. And the last thing I've got was shareholder relationships. If you could put something in the mail to me the week of April 6. I still haven't received it. So if you could just remind your shareholder people, I'm still waiting for the annual form.

C
Clive Thomas Johnson
President, CEO & Director

Okay. That's [ what we'll do ].

U
Unknown Shareholder

And I'm obviously following what's going on with Mali because so much of the company's interests are there. But again, without the annual information report, I'm kind of winging. I've got 40,000 shares, sure very small compared to the corporate people, but it's a small...

C
Clive Thomas Johnson
President, CEO & Director

No. No. That's important. We pride ourselves in our transparency and delivering on what we promised. So obviously, something slips through the cracks there. So it's very important, Charles. And you can send an e-mail if you'd like to imaclean@b2gold.com or to me, cjohnson@b2gold.com. And I will get on it and make sure that you get that not by snail mail but by a mechanism that gets it to you quickly. But thanks for being up and thanks for your support as a shareholder.

Operator

There are no further questions. I'd now turn it back over for closing comments.

C
Clive Thomas Johnson
President, CEO & Director

Well, I think we've turned a lot of ground here, and thank you for your time and your interest and some very good and interesting questions. We're really pleased with the quarter, obviously, and looking forward to another very good, productive year, profitable production and lots of exploration and development opportunities that we see. So thanks, everybody, for your time. And obviously, if you have follow-up questions, you can reach out to Ian MacLean to put you into the person you want to, or if you know the person you want to answer them, you can go directly. So thanks for your time, everybody, and stay safe. Thank you, operator.

Operator

That concludes today's conference call. You may now disconnect.