Operator

Hello, and welcome to the Subsea 7 4th quarter and full year 2019 results. [Operator Instructions] Just to remind you, this conference call is being recorded. Today, I'm pleased to present John Evans, CEO; Ricardo Rosa, CFO; and Katherine Tonks, Investor Relations Director. Please go ahead with your meeting.

K
Katherine Tonks
Head of Investor Relations

Thank you, and welcome, everybody. With me on the call today are John Evans, our Chief Executive Officer; and Richard Rosa, our Chief Financial Officer. The results press release is available to download on our website along with the presentation slides that we'll be referring to on today's call. Turning to Slide 2, may I remind you that this call includes forward-looking statements that reflect our currencies, and are subject to risks, uncertainties and assumptions. Similar wording can also be found in our press release. And now I'll turn it over to John.

J
John Evans
Chief Executive Officer

Thank you, Katherine. Good afternoon, everyone, and welcome to our 2019 Results Conference Call. I will cover highlights of our performance before handing over to Ricardo, who will cover our financial results in more detail. I'll conclude with an introduction to our 2 main strategic focus areas and the market outlook. At the end of the call, we'll take your questions. But first, I want to say a few words on the changes we've made this year to our leadership team. As you know, the retirement of Jean Cahuzac and CEO succession has been planned for some time. And as of January, I've taken over leadership of Subsea 7. We've also strengthened our executive management team, adding 3 new members. And I would like to take this opportunity to welcome Olivier Blaringhem, Phil Simons and Steph McNeill to the new positions. Olivier is heading up our SURF and Conventional business, with all the regions reporting to him. And Steph overseas our Renewables business unit. Phil is in charge of Projects and Operations, and is responsible for our operational, fleet, digital and IT functions that provide services to all business units. Together, they have nearly 90 years of experience in this industry, and I'm very pleased to welcome them to the executive management team. Our Subsea integration Alliance and Strategy activities continue to be overseen by Stuart Fitzgerald. Now turning to Slide 4. I'd like to talk to you about our highlights for the year. In 2019, we reported $3.7 billion of revenue, 10% lower than the previous year, mainly due to the lower contribution for Renewables and Heavy Lifting Business Unit after the completion of Beatrice as well as the timing of some awards in the SURF and Conventional business side. Fourth quarter revenue was $889 million with 85% generated from our SURF and Conventional business unit. Adjusted EBITDA for the full year was $631 million, with a margin of 17%, while margin in the fourth quarter was 19%. And this was driven by good operational performance as well as some commercial settlements on some projects. Total vessel utilization was 66% in the quarter, reflecting the impact of seasonality in the North Sea as well as a low level of activity in the Renewables segment. In 2019, we took the opportunity to adjust our balance sheet, and we returned $304 million in surplus cash to shareholders, whilst retaining a strong liquidity position of over $1 billion in cash and undrawn revolving credit facilities. While we are confident of the improving conditions in our markets, in a view of the current global economic uncertainty and market volatility, combined with the change in law impacting the continued validity of our advanced tax agreement with the Luxembourg authorities, which we are still evaluating, the Board of Directors does not recommend the payment of a special dividend to the shareholders at the AGM, on the 7th of April 2020. Rather, the Group will manage its returns to shareholders through the current USD 200 million share repurchase program. On Slide 5, our order backlog at the year-end was $5.2 billion, with new order intake of $3.9 million, meeting our expectation of a book-to-bill ratio of above 1x despite some big orders slipping into 2020. The solid inflow of orders, comprising of 18 announced new awards during the year, covered all business units and demonstrates our ability to deliver cost-effective solutions in a macro environment that remains challenging. We have $3.3 billion worth of work for execution in 2020. This represents 79% of consensus revenue for this year, a healthier level of visibility that is more or less the same as this time last year. Turning to Slide 6. We see some of our recent operational highlights. Our offshore execution remained strong in the quarter with an emphasis on safe and reliable execution worldwide. In the U.S. Gulf of Mexico, the Seven Borealis performed the first pipelay campaign on the Vito project. The Burullus 9B project completed its 2019 campaign with the Simar Esperança installing jumpers offshore Egypt and the engineering work for our 2020 campaign is well underway. The Zinia project has continued with engineering work for the 2020 offshore campaign and started fabrication phase in the Sonamet yard in Angola. The PRP6 project, offshore Brunei, has reached a significant milestone with the completion of topside work. And all flexible flow lines were installed by the Seven Eagle. Meanwhile, in the Middle East, we made good progress on the Berri-Zuluf project in Saudi Arabia. Lastly, fabrication of the Arran project, offshore U.K., progressed well in the quarter at our spoolbase in Scotland. In renewables, we continue to fabricate the array cable for the Yunlin project, which will be installed offshore Taiwan later this year. Life of Field continued to deliver good uptime on the long-term contracts, with BP in the U.K., Shell in the Gulf of Mexico and Equinor in Norway. In Brazil, our 4 PLSVs remain highly utilized in the quarter, with no significant downtime. Three of the vessels are on firm contracts through 2021 and 1 firm until 2022. Turning to Slide 7. In 2019, we added sustainability to our existing fine values and set up a new team to manage our ESG reporting. We're proud to be publishing our first Sustainability Report to coincide with the publication of our annual report. Inside the report, you will find details of our strategy, KPIs and targets. And I'd encourage everyone to read it when it's released in March. I will now hand over to Ricardo to present our financial results in more detail.

R
Ricardo H. Rosa
Chief Financial Officer

Thank you, John, and good afternoon, everyone. Slide 8 shows the highlights from our income statement. Fourth quarter revenue was $889 million, taking the full year 2019 to $3.7 billion, down 13% and 10%, compared with the respective prior year periods. Full year activity in the Surf and Conventional and Life of Field business units was in line with 2018 but declined significantly in Renewables and Heavy Lifting. In 2019, we generated adjusted EBITDA of $631 million, down 6% year-on-year. But in the fourth quarter, adjusted EBITDA was $168 million, an increase of 3% from the fourth quarter last year. The percentage margin for adjusted EBITDA was 17% for the full year and 19% for the quarter, both benefiting from solid execution as well as certain commercial -- favorable commercial settlements, partly offset by greater seasonality, mainly affecting activity in the North Sea compared with the prior year. In the fourth quarter, we took $100 million goodwill impairment charge relating to the Renewables and Heavy Lifting business, driven by lower utilization of the Heavy Lifting vessels and a highly competitive wind turbine foundations market. We also recorded a $70 million asset impairment charge, mainly relating to 2 older vessels, previously active in Surf and Conventional that are candidates for disposal. Our net loss for the quarter was $129 million. Adjusting for the goodwill impairment charge, we incurred a net loss of $29 million in the quarter and generated net income of $18 million for the full year 2019. Adjusted diluted loss per share was $0.12 for the quarter, reducing the equivalent earnings per share to $0.05 for the full year. Slide 9 provides more detail behind the income statement. A few points are worth mentioning here. Administrative expenses improved by $6 million in the quarter and $18 million for the full year, compared to the prior year periods. This was mostly due to tight control of costs throughout the group, combined with our successful efforts in the year, to resize the organization of the Renewables and Heavy Lifting business. Depreciation and amortization increased by $14 million in the quarter and $54 million in the full year, mainly reflecting the implementation of IFRS 16 on leases in 2019, partly offset by lower charges in respective property, plant and equipment and intangibles. Other gains and losses reflected a $22 million adverse swing from 2018 to 2019, mainly related to foreign exchange movements. The $2 million tax credit in the fourth quarter and $30 million tax charge for the full year were not impacted by the goodwill and asset impairment charges, which had limited beneficial tax effect. Moving to Slide 10 to look at our performance in more detail, and starting with our performance in the fourth quarter. Our Surf and Conventional business unit generated 85% of the group's revenue in the quarter, with notable contributions from the Vito and Katmai projects in the U.S. Gulf of Mexico as well as good progress on the Berri-Zuluf project in Saudi Arabia and solid utilization from the PLSVs on long-term contracts. However, in absolute terms, revenues fell year-on-year, mainly due to the inclusion of work on the West Nile Delta project earlier in the year. Renewables and Heavy Lifting revenue at $59 million was $23 million lower in the fourth quarter compared to the prior year period following the completion of the Beatrice project in the first quarter of 2019, while revenue in Life of Field showed a marginal $3 million improvement. Surf and Conventional's net operating income of $33 million was impacted by vessel impairment charges and lower vessel utilization, mainly in the North Sea, but benefited from commercial settlements on certain completed contracts. Renewables and Heavy Lifting reported a $129 million net operating loss in the quarter or $29 million after excluding the goodwill impairment charge. The deterioration from the prior year period was due to lower vessel utilization and the competitive price environment. Life of Field incurred a net operating loss of $3 million, an improvement of $14 million on the prior year. For the full year, the group's net operating loss was $23 million, equating to net operating income of $77 million after excluding the goodwill impairment charge. In Slide 11, we've summarized our 2019 expenses, divided into 4 main categories. Last year, we highlighted the tight rein we had kept on costs as the offshore recovery got underway. And this cost discipline has been maintained. Vessel and other costs, which included impairment charges, are unchanged at approximately $0.5 billion. We ended the year with 35 vessels in our fleet, 2 more than 2018, with the acquisition of the diving vessel, Seven Pegasus, and the chartering of an additional Life of Field vessel. Our continuing strategy is to own the high end or specialist vessels so that we have full control of their availability for our projects, and supplement this with chartered vessels to provide additional capacity when needed. We continually look for ways to be more efficient with our fleet, saving costs as well as reducing greenhouse gas emissions. Seven Viking successfully completed its first full year of operations, since it was converted to hybrid power, with a reduction in CO2 emissions of 19%, in line with our expectations. Our personnel costs remained flat at approximately $1 billion in 2019, despite the integration of acquired businesses, reflecting our constant focus on optimizing resources. Direct project costs are a function of the volume, mix and phasing of our activities and the pricing environment for procurement. In 2019, we saw a $400 million increase in our procurement costs, driven by the mix and phasing of our portfolio of projects. In 2019, we saw no significant supply chain price inflation, but this risk will become more prominent as the industry-wide recovery in offshore Oil & Gas projects continues. Slide 12 shows our cash flow waterfall for 2019. Our 2019 operating cash generation was robust at $357 million and included an improvement in working capital of $23 million in the fourth quarter, driven by an improving receivables profile. Our investment in working capital, nevertheless, remains relatively high and is a target for improvement in 2020. We ended the year with $398 million in cash and cash equivalents and a net debt position of $181 million when IFRS 16 lease liabilities are included. The $367 million reduction in cash, compared to the prior year, reflected $26 million invested in acquisitions, $258 million of capital expenditure and $304 million in cash returned to shareholders. And turning to Slide 13. 2019 was a year of disciplined capital allocation. We continue to invest in the business, both organically with the ongoing construction of our new reel-lay vessel, Seven Vega, and through acquisition, extending our capabilities and early engagement and digitalization, with the addition of Xodus and 4Subsea. At the same time, we signaled our commitment to capital discipline with the return of excess cash to shareholders while maintaining an investment-grade profile. We have the mandate granted in July 2019 for a further $200 million in share repurchases and expect to utilize it with appropriate regard to our 3 priorities for capital allocation. Finally, turning to the outlook for 2020. Our guidance for revenue and adjusted EBITDA in 2020 is unchanged since the third quarter, with both expected to be higher in absolute terms, year-on-year. Our administrative expenses are expected to range between $260 million and $280 million, in line with last year, as we maintain cost discipline despite the increase in tendering activity. Our net finance cost is expected to be between $10 million and $15 million. Depreciation and amortization expense is expected to fall between $500 million and $520 million. Our effective tax rate is anticipated to range between 30% and 32%, reflecting the anticipated geographic mix of activity in the year. Capital expenditure is expected to be between $270 million and $290 million, marginally higher than the $250 million spent on assets and intangibles in 2019, but well below forecast depreciation for the year. This range includes approximately $70 million for the new rigid reel-lay vessel, which is under construction for delivery in 2020. I will now pass you back to John.

J
John Evans
Chief Executive Officer

Thank you, Ricardo. Turning to Slide 15. I'd like to talk to you about our 2 strategic focus areas: The Subsea Field of the Future and Energy transition. These focus areas will provide direction and clarity on the strategic, organizational and operational basis, that will guide us for the foreseeable future. And you'll see us discuss the company in the context of these themes regularly throughout the coming years. Many of the initiatives are already relatively mature within our organization. And the intention is to further develop them to enhance our capabilities and to position Subsea 7 to create differentiation and seize opportunities in our evolving energy sector. The Subsea Field of the Future is about systems, what we're offering to our clients, and delivery, how we're delivering those systems to our clients. And this is based on 4 pillars: early engagement, system innovation and enabling products, integration and digitalization.As you've heard us say before, early engagement has been a structural change to the subsea market and has gained significant momentum over the last 24 months. We've embraced this change, and are well-positioned through our field development group, the acquisition of Xodus and the launch and growth of the Subsea Integration Alliance.Innovation is key to the Subsea Field of the Future. We discussed some of our new technologies out of Stavanger Investor Day last year, and we will share other ways we are creating value for our clients in the coming quarters. The integration piece, you are very familiar with by now. We've embraced the integration of SPS and SURF Solutions with some notable successes recently. Our efforts with OneSubsea have firmly positioned us as a market-leading integrated supplier worldwide. Finally, our digitalization agenda covers both project execution as well as seeking future digital revenue streams as we have started with 4Subsea. On the right-hand side, we have the big topic that the whole hydrocarbon industry is grappling with, the energy transition. Our energy transition strategy covers investment in subsea technologies to support low carbon, gas and LNG developments and, of course, Renewables, where we target the offshore wind market. Turning to Slide 17. We're proud of the recent achievements of the Subsea Integration Alliance, our partnership with OneSubsea. Both partners have put a lot of time and effort into making this alliance a success, and this has been borne out by recent contract awards. In 2019, we won 56% of the market share that was bid competitively with notable awards on large projects in Australia, Senegal and most recently, in Brazil. The market remains competitive, but awards to date clearly demonstrate that we offer an attractive proposition to clients. Integrated Solutions create opportunities for differentiation and optimize solutions for our clients, particularly on greenfield projects. Slide 18 illustrates some of our larger awards and show our worldwide reach, from the Americas, to Africa and Asia Pacific. These projects also demonstrate our success in early engagement, which is particularly effective in an integrated context. Bacalhau is a recent FEED award that is expected to convert to full EPCI towards the end of this year. And Scarborough is the final part of our trio projects with Woodside, alongside Julimar and Sangomar, which should convert to EPCI this year. Now changing tack to the other focus area, energy transition, shown on Slide '20. The global demand for renewable energy continues to grow, supported by increasing pressure to limit greenhouse gas emissions. Our expertise in wind turbine foundations and in array cables as well as project management, procurement, engineering and installation have already helped to lower the cost of wind farm developments. We've installed more than 500 monopile foundations over 100 jacket foundations and more than 1,500 kilometers of intra array cables. Although we have a wide range of clients, our competitive advantage lies with 2 main groups: those with an international reach and those that adopt an EPCI contracting model. We can leverage our existing global organization to support clients and expanding their developments outside Northern Europe. And we're obviously ready to support our Oil & Gas clients with their energy transition journey as they invest more in Renewables. Finally, today, we turn to Slide 21 and present our outlook for future rewards. Tendering activities has increased over the last year, and we estimate we are working on Surf and Conventional bids worth around USD 11 billion, up from USD 9 billion this time last year. This increase comes despite continuous oil price volatility and demonstrates the industry's success in reducing the economic breakeven of projects. While contract pricing is only gradually improving, we do see vessel availability tightening for certain Surf projects in '22 and '23. Renewables remains a challenging market for now. But we are confident that the growth in demand will absorb the current oversupply on the supply side. And this will be a profitable growth market for Subsea 7. We see, on the horizon, a mix of stand-alone and Integrated Surf and Conventional work along with several renewables projects. We're expecting 2020 to be a solid year for order intake. On the slide, you can see some of the projects in our bidding pipeline. To summarize, we've positioned ourselves well to deliver value to all our stakeholders, as the offshore market continues to recover, and as the energy transition market grows. We're focused on continuing our strong track record of successful execution in 2020, delivering quality services to our clients and on capturing new profitable opportunities to grow our business over the coming years. With that, we'll wrap up our prepared commentary, and turn to Q&A.

Operator

[Operator Instructions] The first question we received from Frederik Lunde from Carnegie.

C
Chr. Frederik H. Lunde

How do you see margin progression through 2020? And also activity, if you please? Should we expect the normal seasonality or will activity be more smoothen out through the quarters this year?

J
John Evans
Chief Executive Officer

Thank you, Frederik. I think in terms of margin progression, as we said, we are seeing a gradual recovery and a slow improvement in our pricing. We do see 2020 has been a reasonably positive year in terms of order intake with some very large projects that we are already the preferred bidder on moving from FEED to final investment decision. So we do see -- expect to see some progression on margins throughout the year. In terms of activity, we still see some seasonality. We saw it already in quarter 4 with quite a quiet renewable sector activity and the North Sea was quite quiet for us as well. So I'd expect to see reasonably strong performance in Q2 and Q3 with probably some subdued activity going into quarter 4.

C
Chr. Frederik H. Lunde

That's great. And if I could say so, flavor on your CapEx ambitions going forward. Obviously, a more uncertain medium-term Oil & Gas, while Renewables is a bit challenging near term, but same potential long-term growth. So in that context, do you expect it to continue harvesting on your existing assets for the foreseeable future? Or do you see any sort of medium-term plans for -- or requirements for newer vessels or technology that would change your sort of $200 million CapEx number?

J
John Evans
Chief Executive Officer

I'll give a general overview to that question, and then Ricardo can give a bit of detail on the CapEx figure we've put in the presentation here. I think for us, at the moment, Frederik, we're pretty comfortable with the fleet that we got. Our fleet covers our near-term needs in terms of what we're looking for. We are also focusing in on continuing our technology development activity, which will allow us to position ourselves where we want to be for the Field of the Future. I think for us, as well, there may be some niche acquisitions in the engineering front as well as we did last year, where certain types of capability we will acquire. We purchased a very small engineering environmental company, based in both in Perth in Australia last year called Greenlight Environmental that provides us with a competency and a skill that we did not have in the group previously. But generally, there will be no major fleet acquisitions in our plan for this year. But I'll let Ricardo talk about how the CapEx works for this year.

R
Ricardo H. Rosa
Chief Financial Officer

Thanks, John. I think John has summed up very well. I mean I think we are in a phase now when -- after a very intense capital expenditure program in the previous period of '14 to '17, we are now more in a harvesting road -- mode and we are rebalancing our capital expenditures toward technology. And I think, as a result, you will see growth perhaps in intangibles as opposed to physical assets. Having said that, we are very conscious of the need for capital discipline, given the uncertain environment that we are working in at the moment with the growth of focus on energy transition. And it's important that we remain mindful of the need to achieve an improved return on investment. So I think overall, I mean, we will not exclude the possibility of acquiring new assets, such as vessels. But we will look at them very, very carefully and be very sparing in our expenditures. Our focus will remain on, I think, innovation and technology as differentiators.

C
Chr. Frederik H. Lunde

That's great. And on that note, just on your buyback program or a mandate? Is there any sort of trigger point for utilizing that? Or is that just not nice to have for you for now?

J
John Evans
Chief Executive Officer

I think, Frederik, I think you know our position well on that. We have a good track record of returning cash to shareholders, particularly through previous share repurchase programs. And we only suspended cash returns in total in 2015 and '16 in the depth of the downturn affecting our sector. We will continue to make our decisions regarding share buybacks and other forms of cash return by reference to the 3 priorities that we've been consistently setting out: reinvesting in the business, investment-grade profile and returning surplus cash to shareholders and we want to do that in an efficient manner.

Operator

The next question received is from Mick Pickup from Barclays.

M
Michael Brennan Pickup
MD & Senior European Oilfield Services Analyst

A question, if I may, on the integrated model for the Subsea fields. Obviously, 57% of greenfield awards went that way last year. If I look at your bidding pipeline, it seems to be much higher than that going forward. So can you just talk about adoption where we are? And how far you think it's going to go?

J
John Evans
Chief Executive Officer

It's an area that we've been very pleased in the last year with our performance, and we feel very comfortable in terms of where we're at in the market. The adoptions we showed in our slides, we see the first big integrated project with Bacalhau coming in there with Equinor in Brazil. They're also using that model at the moment. We're currently bidding Vadinar in Canada, also for Equinor on an integrated basis. We're seeing a lot of the very large projects at the moment, either have that as a base case or have it as an option in it. So I think we've got through that phase of understanding the merits, as clients have looked at it a couple of years ago as to whether there was traction in it. So for us, it's mainstream. As I mentioned at the very introduction here, Stuart Fitzgerald is integral in the leadership of the Subsea integration line, so a [ ex-core ] member of Subsea 7 is fully embedded in that organization along with a similar senior member of OneSubsea, and we have a lot of good traction there. So a lot of good visibility and a lot of good traction there at the moment. What's been very key for us is winning the big greenfield projects. We see that as the path to the future is getting ourselves incumbent on the very large greenfields. And as we showed in the diagram there, Mad Dog 2, Scarborough, Bacalhau, all these key projects that will be very large developments in the future. We believe the [ SA ] have got themselves well positioned. So that's our focus area.

M
Michael Brennan Pickup
MD & Senior European Oilfield Services Analyst

And when you look at your market share on those big greenfields, 50% is obviously a very high number. What is it you're offering? Is that just we've got a small subset at the moment?

J
John Evans
Chief Executive Officer

Well, I think the feedback I've had from senior members of the oil companies, they've been very pleased with the way the Subsea Integration Alliance put different ideas on the table, looked at different ways to lay out their fields, being quite innovative with different ideas, worked in a very collaborative manner as well as then an exceptionally strong execution machine that both OneSubsea and Subsea 7 have in the market. And lastly but not least, is always a sound commercial model. So I think we've been able to demonstrate to our clients that, that investment that we've made in 400-odd people now working with us in the early engagement side of our business between Xodus on one side in the Field Development group inside Subsea 7 has really been able to put some good ideas on the table. And I think that's been a key part of our success to date.

Operator

The next question received is from James Evans from Exane BNP Paribas.

J
James Matthew Evans
Analyst of Oil and Gas

First, I wanted to ask about Renewables. What do you need to see to get back to breakeven profits in there? Is it simply absorption and awards? Or do you actually need to see some of these EPCI contracts come through as well, given where pricing is? And I guess, just relating to this, I don't know if you can share this, Ricardo, what is the carrying value of your Renewables business now post the write-downs? And then secondly, one for John really, around consolidation, obviously, we've had some reports towards the back end of last year. We've got others in financial distress. You're obviously reluctant to take additional vessels onto the balance sheet, certainly at the wrong price. So I just kind of wondered if you have any comments on how the organization sees the merits and likelihood of consolidation in the industry this year.

J
John Evans
Chief Executive Officer

I guess with the Renewables, the message we tried to give for the last 2 to 3 quarters is that there's a current oversupply of contractors and assets piling into that market at the moment. And actually, for me, it's actually about risk is the key thing. We are, I guess, quite highly attuned to managing risk because our business is arbitraging risk for our clients in our industry. And therefore, then it's about 2 things need to come into play. The supply and demand needs to get a balanced position, which -- and the opportunities out there should allow that to take place. The second one then is finding the right risk balance. At the moment, we're seeing a number of contractors prepared to take some risk positions that we're not prepared to take. But we are seeing, though, the coming together of certain key clients and certain international expansion of key clients who want to take solid and reputable contractors with them. So we're working, for example, with Ørsted. We'll be working within the U.S. this year on their key demonstrated project in the U.S. We're also working with them on their Hornsea Project. RWE Renewables, which will become the second largest is the owner of Innogy, and we're currently working with them on Triton Knoll, and we're bidding some future work with them at the moment. So for us, it's around getting the right profile, and also then some of the key projects that we have and all this should come into play this year, James. I'll let Ricardo talk about the carry value and then I'll take the consolidation question.

R
Ricardo H. Rosa
Chief Financial Officer

James, I have to disappoint you on that point, but I don't have the figure to hand. In any event, I don't believe we'd disclose it. However, we will be publishing very soon our annual report, which gives a pretty detailed note regarding our 10 cash-generating units and the allocation of goodwill between them. So I hope that you'll bear with me, and perhaps we can have a discussion once the report has been issued.

J
John Evans
Chief Executive Officer

And on consolidation, I guess, in terms of vessels, I think your question sort of indicated there were a lot of vessels and assets around. I think I'll come back to my response earlier. I think we are reasonably comfortable with our fleet at the moment. We have the right fleet, we have the right asset base. We were quite ruthless in terms of sizing and structuring that, and we continue to focus on trying to get the right fleet for our business. In terms of Renewables, we know which sectors we want to be in, which is the foundations in the inter array cables. So again, at the moment, we don't see anything in particular that would move us to do something in terms of consolidation because there is some asset availability. For ourselves, you've seen our pattern in the past. We have consolidated business such as EMS. We consolidated business such as Xodus when they become available. The focus areas that I'm interested in at the moment is what does that Field of the Future in subsea look like, and we need engineering capability, early engagement capability there. And what exactly that energy transition position looks like. We have a strong foundation already in renewables and where that will take us to in the next few years. We're very open minded, and we'll look at opportunities that will come that way.

Operator

And the next question is from Amy Wong from UBS.

A
Amy Wong

A couple of questions from me, please. The first one is, in your prepared remarks, you called out that to watch out for some inflation in the supply chain. So I was hoping you could help us understand the magnitude of the inflation you're talking about, be a bit more specific of maybe segments that you're seeing inflation creeping in? And thirdly, are you able to pass on some of these inflation into your bids that you are currently tendering on? That's my first question.

J
John Evans
Chief Executive Officer

I think what we're seeing at the moment is certain segments, there are certain sub-suppliers in those segments where a number of these projects, particularly the big greenfield ones come together at the same time, there's a risk here of capacity constraints. So at the moment, we are certainly making sure that we have a very transparent mechanism as we go from FEED into FID with our clients, where if there's any inflationary elements in there. For example, things like stainless steel tubes for umbilicals, it's actually not any of the key umbilical suppliers that provide you the tubes there are -- there's a supply chain underneath that, which we're seeing some tension in at the moment. Pricing of steel and stainless steel products, in particular, the go in line pipe, again, we do quite a bit of work to make sure that we're quite transparent with our clients. So we have a mechanism that allows them to understand the changes that are going on there, both up and down, by the way, to allow that to take place. So it's not a general concern across the board. It's certain specific elements, and we believe it's always best that we highlight those in our discussions with our clients because some of these FEED elements from the selection on Bacalhau, which is at the start of this year to the FID and Bacalhau will probably be at the end of this year. We need to have mechanisms that allow those elements to go through. We also flagged to our clients, certain materials or preorders for materials that we may need to do to keep their schedules on track. And again, we work constructively with our clients on that.

A
Amy Wong

All right. Okay. So it sounds like you are working with clients to be able to pass that through, right. Okay. I guess my second question is unrelated, but just -- it relates to your number -- thanks for giving a tenders number, about $11 billion. Now given you guys have always said, it's very difficult. It's not very transparent to the market like split the volume of that work. So perhaps the way to ask the question is, if we were to think about that $11 billion and compare that to, say, 4, 5 years ago, what's the volume comparison to like, whether you want to quote that in like the days of pipe-laying work that you need to do? Or the amount of equipment that you need to -- just help us understand the kind of the change in dynamics between the bid volume and the bid dollar value?

J
John Evans
Chief Executive Officer

Well, I think it's quite an interesting question, and it's not a straightforward one to give you an answer on, I guess. The bid volume is what we think we will have ahead of us in terms of workload ahead of us. I think the key message here is, if we compare to where we were 5 years ago, we were up at 44 vessels. We sent a lot of vessels back to charterers that we owned. We scrapped quite a bit of tonnage. So really, for us, it's around focusing for work to bring into our key enabling assets, the big steel rigid pipe layers and such like to make sure then that those are fully utilized or as well utilized as we can to then allow us to work from there. So I can't easily give you a read across from one number to the other because it isn't that easy to go from where we were 5 years ago to where we are now. But the aim is to see, as I mentioned in the prepared remarks, we can see that in '22 and '23, there is a reasonable volume of workload for the large rigid pipe layers which, again, at the moment, for all those projects fitted into place would mean that we would need to manage the schedules of those assets quite tightly for those periods.

R
Ricardo H. Rosa
Chief Financial Officer

If I could just add to what John has said, Amy, I think you got to bear in mind, too, that the market of today is very different to what it was, say, 5 years ago in terms of the resources that are applied, the ways of working, the cost structures, the fact that we are much more involved in the early engineering phase of the project. So I think you're going to be trying to compare apples with pears, to be frank. But I think it's important to look at the cycle and the progression of the current cycle rather than look back to history.

Operator

And the next question received is from Haakon Amundsen from ABG.

H
Haakon Amundsen
Lead Analyst

Yes, just wanted to follow-up on the margin question as we go into 2020. I mean your EBITDA and revenue guidance is quite clear. I just wanted to understand, should we expect your 2020 EBITDA margin to be flat or up compared to '19, as I think, the '19 margins ended up a little bit higher than some of us expected?

J
John Evans
Chief Executive Officer

I think we've given our guidance to try to help you work your way through this. For us, it's about -- our revenue was up, our absolute EBITDA is up. Margin, we will see as the year progresses. It depends on how some of these very large projects kick in or don't kick in during the year. Once those large projects come in, as you know, we have a period where we don't recognize profit at the start of big projects. We also have a large period of work associated with procurement. So for us, I think our guidance is clear and we'll stay as we are on that.

H
Haakon Amundsen
Lead Analyst

All right. And then just for Ricardo. Maybe, if -- could you give some color on the initiatives on the working capital and the potential scope for improving that position? Is it possible to give any indication of what we should expect for the year?

R
Ricardo H. Rosa
Chief Financial Officer

I'm not going to start giving you precise figures, but I can talk to you about the drivers and what we're focused on. I think as far as '19 is concerned, we'd mentioned that we had some challenges with regard to the investment in working capital that we had in the Middle East. It was relatively high. I'm pleased to say that things have improved quite significantly in the course of the year there. And we're in much better shape as we enter 2020. However, we do still have some challenges in 1 or 2 other regions of the world. And we are expecting to resolve them in the course of 2020. So our expectation is that we will improve our working capital position. I think as well that we are discussing working capital in our negotiations and discussions with clients at the tender stage. And we're highlighting to them the importance from our perspective of a neutral to positive cash flow throughout the life of a particular project. And I think we're beginning to see some initial positive reaction from their side. So we hope that this will translate into improvement on that front.

Operator

And the next question is from David Farrell from Crédit Suisse.

D
David Richard Edward Farrell
Research Analyst

One question for me, just going back to the Renewables business. Could you help us understand, as that industry kind of shift into deeper water, we move towards kind of heavier turbines. Does that mean we're going to see more jackets rather than monopoles? And if that's the case, does that play into the assets that you have in terms of executing projects?

J
John Evans
Chief Executive Officer

Yes, it's very interesting to see at the moment that the industry historically has either used jackets or monopiles. And there's been a lot of good engineering work done on effectively maximizing monopiles. We're putting in monopoles just under 2,000 [ tons ], which are huge at the moment. So I think the engineering and the technology that's been developed in the industry is reaching the point where monopiles reach their sort of natural limit, which then means you then head towards jackets. And then beyond jackets, then you go into a floating environment. So again, we're seeing a number of clients who use jackets and some clients use monopiles. So if you look at the U.K., which is probably the largest market for that, it's a mixture of both. Some clients go for jackets at around 65 meters of water. Some other clients enter around 50 meters of water, will try to keep pushing very, very large monopiles in there. So yes, larger jackets helped towards the size of the asset base that we've got. But also some of these monopiles are getting to the point where they're getting towards the limit of what our assets and other people's assets can do as well. So 2 of the things are moving in parallel, I think.

D
David Richard Edward Farrell
Research Analyst

Okay. And then just a follow-up. You've been a preferred bidder on the HKZ renewable project for some time now. Have you got any update as to when that might move ahead? I think one of the other contractors on it has been a bit more positive in terms of moving that project into their order book?

J
John Evans
Chief Executive Officer

Yes. HKZ was a project which comes in 4 phases. If you might recall, we won the first 2 phases. And then our client, Vattenfall, then bid for the opportunity to have the concessions for Phase 3 and Phase 4. They were successful on that. So at the moment, we're in the process of just tidying up our agreements with them. And we expect, hopefully, in the next quarter that we could announce finally what that looks like. But the conversations are ongoing with them. So it was -- it's around putting together all 4 phases of that into a contractual structure.

Operator

And the next question is from Lillian Starke from Morgan Stanley.

L
Lillian Starke
Research Associate

I just had 2 questions. The first one is, when you talk about vessels tightening in 2022, 2023. Could you provide a bit more detail on whether that's across 12 vessels in your fleet? Or whether you're seeing specific tightness in certain types of vessels, just given the mix of projects? And then the second question I had was just on when you look at the margin on an integrated contract, is there a significant difference to the ones that you're obtaining on a stand-alone basis and [ serves ]?

J
John Evans
Chief Executive Officer

Taking the first, I guess, on what we discussed on '22 and '23, which I think answered the previous question on the -- it's to do with rigid steel pipeline vessels that we're seeing quite a bit of bidding activity and a number of projects that are all looking at around the same time that '22 to '23 period. That's the area at the moment that we're seeing a high level of interest. That hasn't turned into contracts for the industry as yet, but the market is bidding that as part of our $11 billion pipeline that we discussed. I think in terms of margins, I don't intend to go into a margin discussion because each project is bid on a case-by-case basis. It depends on where we are, it depends on where our partner, OneSubsea is in terms of position in that country position in that field and such like. So it varies. I think it's a fair answer to say there where we see some advantages on some of the large compression and pumping projects as we announced just in the run-up to Christmas. We did the St. Malo project there for Chevron. It was announced before Christmas, which is a pumping project with a Framo technology from OneSubsea. So it varies. We have different strengths and different weaknesses on different projects.

Operator

And the next question we received is from Michael Alsford from Citi.

M
Michael J Alsford
Director

I've just got a couple left. Firstly, just on the Middle East. I was just wondering if you could talk more specifically about the competitive landscape there, what you're seeing in terms of pricing and I guess, the outlook from an awards perspective. And then secondly, on Brazil, you have the PLSVs that are obviously due for renewal. I just wondered if you can give any clarity on sort of the timing of the renewal process, when we should expect that. And maybe an outlook on what you see as sort of the demand outlook for PLSVs into 2021, 2022?

J
John Evans
Chief Executive Officer

I guess the main message on the Middle East, there still remains a reasonably consistent demand of bidding under the LTA agreement. As you know, we bid in consortium with Larsen & Toubro there. They do all our fabrication for the side of the project, and we do all the installation and engineering of the pipelines and the umbilicals and such like. We are continuing to bid under the LTA framework. The size of the project varies in size and scale. I mentioned in my prepared remarks, we're working at Berri-Zuluf at the moment. We also have Marjan 2 underway at the moment inside our portfolio. So there's a reasonable group of projects coming. The main one that the industry is interested in Zuluf field. There is a further redevelopment of Zuluf coming out, which will be done similarly to the Marjan field. So last year was all about Marjan. This year, it's all about Zuluf coming up. So we'd expect some bidding activity in that later this year. Moving to the PLSVS, I think we gave an update on the PLSVS, the last quarter. The messaging we're getting from Petrobras is that we expect with the next bidding round for PLSVs to be in the second half of this year. And at that stage, it will become clear what their needs are and where that takes us to. So no fundamental change there. And our PLSVS, as I mentioned in my prepared remarks, are doing a lot of pipe-lay at the moment for them as a number of the big FPSOs are right there in Brazil. So there's no change from what we mentioned in Q3.

M
Michael J Alsford
Director

And one more, if I might. Just I was wondering, you touched on, I think, earlier around floating wind. And I just wondered if you could talk a little bit about what you see there in terms of get your capabilities and whether there's anything on the horizon that might work? Or is it still very much early days in terms of conceptual design and studies?

J
John Evans
Chief Executive Officer

I think it's fair to say there are many, many different concepts and many different designs in the market, which is always a good sign that you've got a lot of technology and a lot of ideas. We own a small minority share in a small floating wind company from -- based in France, which has a floating technology capability in its portfolio. So for us, it's more about effectively a technology watch and watching how that develops. As you know, we also picked up the Tampen work with Equinor. So we're doing all the inter array cables for the Tampen field activity, which is a floater. We also did the cables for the initial Equinor floater, the Hywind project of Scotland. So again, I think it's a smallish market at the moment, but it's a market that we're keeping our eye on. Inevitably, it will move into floating in terms of the depth of the water in due course. But at the moment, the very, very large majority of our work in the high 90% is all fixed wind at the moment.

Operator

And the next one is from James Thompson from JPMorgan.

J
James Thompson
Analyst

Just a couple for me, please. Firstly, what is the right sort of win rate, John, for Subsea 7 that you think? Obviously, 2019 from a greenfield perspective, was very good. I mean is that a level where you sort of think maybe a bit too aggressive on pricing or sort of 50% win rate that you're pretty comfortable for when you look at your projects outlook?

J
John Evans
Chief Executive Officer

James, I think we always answer the same question. We always expect to get our share of the market. There's 2 sides on integrated projects, incumbency and non-incumbency. When you are doing a step out, a small step out in the field, if that field does not have OneSubsea trees on that, it's very difficult for us to offer our client a competitive advantage because mainly the control system and everything there is designed around an existing tree manufacturer. So for ourselves, it's also -- so it's around where we position ourselves. So for us, we've talked there about 56%. Just remember, that's only the greenfield projects. It's really around the fact as a mixture of greenfield and brownfield in that space. I guess the other one then just depends on vessel availability where we're at and where our assets are based at the time. But we've always been reasonably clear. We expect our fair share of the market, and I'm not too concerned at the moment that we won't get our fair share of the market.

J
James Thompson
Analyst

Okay. That's pretty clear. I mean I guess we've talked about a few of the geographies. It was nice to see Sangomar come to FID at the start of this year. It was good for West Africa, which has been pretty quiet otherwise. Could you maybe just give us an update about West Africa in general? And whether you see any signs of progress in some of these projects that have been on the cards for some time?

J
John Evans
Chief Executive Officer

Yes, I think West Africa has some level of traction, which is good. And I think the main message about West Africa, it's not just a 2-country story anymore. Historically, that's been a Nigeria and Angola discussion. We're working in Sangomar, we're currently supporting Aker Energy on their Pecan opportunity in Ghana. And again, there may be an opportunity there that, that turns into an FID later this year. We're currently bidding PAJ, which is the BP opportunity in Angola. And as you know, we are working on Rovuma and a bid there for Rovuma and some of the early work there on Rovuma in consortium with Saipem in Mozambique. So we're seeing a good spread of activity compared to where we've been, and we continue to bid some of the larger deepwater projects such as Bonga. Where we have seen a bit of slowdown, which I think was mentioned in Ricardo's messages was that the conventional work in Nigeria, where we did get some work last year has slowed down a bit at this as we see for 2020. So -- but we are seeing some movement. And as you said there, I think the key on all these, James, is actually getting to final FID on each of these projects, each one is a story unto themselves. Each one is a -- not just a question of reserves and economics of the field, but also the politics of each country that we're working in. But we're comfortable there. And as we speak at the moment, the Borealis is working for Tullow in Jubilee in Ghana. So again, we have assets working in Africa as we speak.

Operator

And the next question is from Vlad Sergievskii from Bank of America.

V
Vladimir Maximovich Sergievskii
Research Analyst

Quick ones, actually. First, you mentioned in your prepared remarks that there are certain changes to the tax law in Luxembourg, I think. And you are already evaluating potential impacts. Would you be able to give us a bit more color on what this change is related to? And what the area of outcomes could be from this? And another quick one to follow-up on would be on your operating lease repayment expectations for 2020. I mean you disclose that you repaid about, I think, $105 million of operating leases in 2019. And I'm just wondering if it's a good proxy for 2020 as well?

J
John Evans
Chief Executive Officer

Thank you, Vlad. I'll ask Ricardo to answer both of those.

R
Ricardo H. Rosa
Chief Financial Officer

I think in terms of more color regarding the question of tax law changes in Luxembourg, I think what we can say is that in December '19, Luxembourg issued Budget Law 2020, which invalidated all advanced tax agreements signed before 2015. Our particular agreement had given us clarity regarding the applicability of withholding tax on distributions. And we are in the process of evaluating the implications of the new law to the specific circumstances of the group. Our view is that at the moment that we are confident that we will find a position that is defendable and that works for our shareholders, but all of this requires additional analysis. With regard to your second question on operating leases for 2020, you're right. And you picked up from our cash flow, our cash waterfall that we paid about $105 million in 2019. I think directionally, that is a reasonable place marker to use going forward. As you probably realized, I mean, most of our leases are related either to vessels. And those are set out -- the chartered vessels are set out in our fleet summary and to certain properties around the world. So it's currently relatively stable figures.

Operator

And the last question received is from Mark Wilson from Jefferies.

M
Mark Wilson
Oil and Gas Equity Analyst

It's actually related to Vlad's last question regarding Luxembourg tax. Ricardo, the last few years, it seems like cash tax has been slightly higher than the tax through the P&L. Would you expect that to be a way to look at tax for 2020 and beyond versus the effective tax rate? That's my first question. And the second one is to John. It may have been said, apologies if it has, but that 2019 greenfield market share, could you just tell us how many projects in total that is? And it sounds like you would expect more than that to come in 2020 overall to the market if things go as planned?

R
Ricardo H. Rosa
Chief Financial Officer

Okay, Mark, I'll take the question on tax, and then hand over to John. The -- just to be absolutely clear, I mean, there is no -- within the tax figure, there's no withholding tax relating to any distributions that we've done in the past from Luxembourg. We've always distributed without any withholding tax. The -- as far as the tax -- the cash taxes are concerned, I think what you have to bear in mind is that the tax that we -- the cash tax of the current year relates to the liability of the previous year in a number of jurisdictions. So to the extent that there has been, if you like, a decline in profitability in certain jurisdictions, you'll end up with a tax charge that is lower than what we paid in the previous year. And I think that's the way to look at it. On a steady-state basis assuming no shift in a major shift in the geographies of our activities, you should not expect to see a very significant differential between the tax charge and the cash taxes.

J
John Evans
Chief Executive Officer

And just taking your other point, I don't have the figures to hand, but I think the key message here is the greenfield ones are the brand-new fields where there's no incumbency effectively. So if you just take the list of all the awards on an integrated basis in the industry, we took 56% of the greenfield ones. So effectively, ones where we're not bolting on a step-out to an existing infrastructure there. And the main reason we're interested in greenfields is 2 elements. Greenfields are generally very large developments for ourselves. You can see on the graph that we've got 2 projects there, Carcará and Sangomar. They're over $ 0.75 billion each of work for us. So there's a lot of infrastructure to put in initially with a large number of [ trees ]. And secondly, that creates the incumbency position for the future, which, again, we're interested in as a company. So unfortunately, I don't have a figure to hand, but that's how we can do the numbers. And with that, I'd like to thank everybody for your time today. We look forward to catching up with you when we give you the update on Q1. Thanks a lot.