Sterling and Wilson Renewable Energy Ltd
NSE:SWSOLAR

Watchlist Manager
Sterling and Wilson Renewable Energy Ltd Logo
Sterling and Wilson Renewable Energy Ltd
NSE:SWSOLAR
Watchlist
Price: 479.95 INR 2.33% Market Closed
Market Cap: 112B INR
Have any thoughts about
Sterling and Wilson Renewable Energy Ltd?
Write Note

Earnings Call Transcript

Earnings Call Transcript
2022-Q1

from 0
Operator

Ladies and gentlemen, good day, and welcome to Sterling and Wilson Solar Limited Q1 FY '22 Earnings Conference Call. This conference call may contain forward-looking statements about the company, which are based on the beliefs, opinions and expectations of the company as on date of this call. These statements are not the guarantees of future performance and involve risks and uncertainties that are difficult to predict. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Vishal Jain, Head of Investor Relations from Sterling and Wilson Solar Limited. Thank you, and over to you, Mr. Jain.

V
Vishal Jain
Head of IR

Good morning, everyone. Welcome you all to Q1 FY '22 earnings call. Along with me, I have Mr. Amit Jain, Global CEO; Mr. Bahadur Dastoor, CFO; and Strategic Growth Advisors, our Investor Relation advisers. We will start the call with an update on the solar power industry and operational highlights for the quarter by Amit, followed by financial highlights by Bahadur, post which we will open the floor for Q&A. Thank you, and over to you, Amit.

A
Amit Jain
Global CEO

Thanks, Vishal, and warm welcome to all the participants on this call. I would like to give a quick update on solar power industry and status of our business operation. The global solar industry has been adversely affected in the last 9 months due to an unprecedented increase in price of modules, commodity prices and freight costs that have pushed the prices up for projects. In last 1 month or so, the module and commodity prices have been stable, though we continue to see an upswing in the freight prices. The freight charges have been on continuous uptrend fueled by various reasons, including a shortage of containers, the congestion at ports and closure of ports in different countries because of the COVID-related reasons. The increase in freight cost has severely impacted the transport cost of solar modules and other raw materials world over. The shipping rates have increased from 5 to 7x over the last 9 months, and this has -- there's been a significant cost input. Just to give an example how it has impacted. We were treating the -- before the last quarter of FY '21, the fleet growth from China to Chile around $2,000 for a 40-feet container, which has now increased to $13,500 in July, which is approximately 6 to 7x cost increase. Given the situation, many solar developers have delayed the finalization of orders. Consequently, the order finalization in the international markets for FY '22 has seen a lull till date and have been postponed to H2 FY '22. We expect around 80% of the orders for FY '22 to be finalized in H2 FY '22. Our pipeline continues to remain robust, and we expect about 15 gigawatt of orders as compared to 13 gigawatts once we finalize in FY '21 to be finalized this year. We expect to maintain strike rate of 14% to 15% for this year, in line with our past performance. Our unexecuted order book as on 14th August 2021 stands at INR 8,731 crores, which is executable over a period of next 12 to 15 months. This includes order amounting to INR 2,030 crores, which may now be unviable for developers considering increased module and commodity costs for which we are in discussion with our customers. On the growth market and opportunity over medium term, we continue to see a lot of traction in key markets, especially U.S., Australia and Europe. Currently, we have limited presence in the 2 markets, that's North America and Europe, and we will be targeting to increase our market share in these markets. As per IFS Markets, the overall market is expected to see a growth of 15% over the next 3 to 5 years. Our global presence provides us a lot of flexibility in selecting projects globally. Most of our clients are looking at significant capacity additions, and we continue to remain confident of the opportunities going ahead. Our O&M portfolio as at date is 8.7 gigawatts, and 40% of these are third-party EPC contracts. We expect O&M portfolio to grow by 40% within the year to 11.5 to 12 gigawatts by end of FY '22. We are focusing on increasing international O&M portfolio by pursuing projects where EPC has been done by third party. We expect O&M margins to remain robust at 35% during the year. With an aim to expand our renewable offering, we have decided to pursue EPC business for hybrid energy, power plant, battery energy storage and waste to energy, subject to shareholder approval. Hybrid energy market is expected to grow at 8% CAGR to USD 3.7 billion by 2025, whereas battery energy storage system and energy storage system is expected to grow 2x in next 4 years to $12 billion annually. Australia and U.S.A., where we have already have sizable presence, are the large market in battery energy storage systems, and we continue to see the trend of even the stand-alone at all the projects being coupled by both battery energy storage systems. Further, as battery prices are coming down, we are seeing a lot of traction for customers to combine solution in terms of solar plus that hybrid energy share to increase. We will be quickly -- be able to ramp up our battery storage business by adding a team of battery experts, whereas sales execution and design and engineering teams will be common for the businesses. We see a lot of opportunities to grow this business as most of the clients who are best are large IPP players with whom we have strong relationships. With ever-increasing generation of municipal waste globally and requirement of government to stop reduced landfills, the market for converting waste to energy continues to grow. Waste to energy market is expected to grow annually by USD 5.25 billion over the next 6 to 7 years with addition of 70 new plants annually. U.K. and Europe constitute more than 40% of the global market, which will be our key focus market in initial years. With carbon emission reduction becoming a global consensus, there are enormous opportunities in these earning field of hybrid energy power plants, energy storage solution and biomass Phase 2 energy. We can leverage our existing relationship with clients, further exploit our technical expertise and maximize the inherent benefits of our hub-and-spoke business model, thereby becoming a diversified global company into a rapidly growing ESG space. With this, I will ask Mr. Bahadur, our CFO, to take you through the consolidated financial highlights. Thank you very much.

B
Bahadur Dastoor
Chief Financial Officer

Thank you, Amit, and good morning, friends. I will take you through the consolidated financials for the quarter ended June 30, 2021. Before we run through the financials, I would like to reiterate that being an EPC company, the revenue, order inflow and gross margins could be lumpy due to geographical mix and stage of execution of the project in any particular quarter. And hence, comparison on corresponding previous period will not be a true reflection, and performance for a quarter may not be representative of the full year. Before commenting on our financial performance, I would like to update you on the recent event of resignation of our statutory auditors. Pursuant to the COVID-19 situation and its impact on the operations of the company, there has been a sharp focus to reduce overheads across the organization. From time to time, we have been in discussion with B S R & Co. LLP, our statutory auditors, for a substantial reduction in audit fee. However, as we couldn't reach a common ground, B S R & Co. LLP resigned as our statutory auditor. We would like to thank B S R & Co. for all the cooperation they have extended to us during the various audits to date. On the recommendation of the Audit Committee, we have appointed M/s. Kalyaniwalla & Mistry LLP as the statutory auditors of the company to fill the casual vacancy caused by the aforesaid resignation from August 15, 2021, still the ensuing fourth AGM and to further appoint them for a period of 5 years, subject to approval of the shareholders of the company at the ensuing AGM. Revenue for Q1 FY '22 grew by 12% to INR 1,195 crores as project execution was impacted in Q1 last year due to COVID. Region-wise revenue breakup for EPC is as follows: Australia contributed about 64.3%; Americas contributed 25.3%; followed by India, which contributed 8.7%; and the balance contribution by MENA region and Africa. Our O&M revenue stood at INR 61 crores in Q1 FY '22 and constituted 5.1% of revenue in Q1 FY '22. O&M margins in Q1 FY '22 have been 35%. Due to the impact caused by the increase in module and commodity prices, adjusted gross margins in Q1 FY '22 continue to remain suppressed for ongoing projects and stood at 2.3%. The orders booked in the current year has come at our historic margins of 10% to 11%. Recurring overheads on absolute terms remained at the same level in the corresponding previous quarter despite the previous quarter having lower salary and travel costs due to COVID-19. Our recurring overheads as a percentage of revenue reduced from 7.5% in Q1 FY '21 to 6.9% in Q1 FY '22. EBITDA losses for Q1 FY '22 stood at INR 93 crores due to lower gross margins and accelerated mark-to-market on cancellation of forward cover contracts. Accelerated MTM represents loss of INR 49 crores on account of cancellation and rebooking of forward contracts on expiry related to ongoing projects, which resulted in accelerated accounting of losses, which has been explained in detail in Note 11 of the Q1 results. The same has been flushed out from effective portion of cash flow hedge of other comprehensive income, resulting in negligible impact on shareholder funds. Now coming to the balance sheet. I would again like to reiterate that as per the amended Articles of Association, the company cannot give loans to promoters or their affiliates post listing. The external term debt outstanding as on August 14, 2021 is INR 64 crores. Decrease in borrowings is on account of repayment of ICDs and cash flow from operations. Since listing, we have repaid a total of INR 2,447 crores through internal accruals and money received from group companies on collection of intercorporate deposits. The repayment schedule of term debt in Q2 FY '22 and Q3 FY '22 involves payment of INR 24 crores and INR 40 crores, respectively. We have a cash and cash equivalent of approximately INR 336 crores and a net worth of INR 651 crores as on June 30, 2021. As of June, we had a negative working capital of INR 571 crores as compared to negative working capital of INR 530 crores as at March 2021. Negative working capital is driven by a combination of higher collection, efficient management of working capital and advance from customers. There do exist, however, delay in payment to certain vendors. Of the receivables due for more than 1 year, which stood at INR 445 crores as on June 30, 2021, it comprised of related party receivables of INR 136 crores, which include receivable of INR 102 crores against which the company has received unconditional assurance of proceeds from sale of plants. We have been able to collect, settle old receivables of INR 18 crores during the year-to-date and are confident of recovering most of the balance overdues. The total intercorporate deposits repaid till date from 1st of April was INR 172 crores. As at 14th August 2021, ICD stood at INR 741 crores, including interest accrued. On the cash flow front, during the quarter, we had a negative operating cash flow from operations due to payment towards MTM losses on cancellation and rebooking of forward contracts, as explained above. Cash flow from investing activity was positive in Q1 FY '22 due to receipt against ICDs and interest thereon. Here, I would also like to add that in accordance with the Sterling and Wilson Solar Limited Employee Stock Option Plan, the Nomination and Remuneration Committee at its meeting held on August 14, 2021, has approved the grant of 13,01,213 out of a total of 16,03,600 employee stock options, which were approved by the shareholders, to eligible employees, exercisable into not more than 13,01,213 equity shares of a face value of INR 1 each fully paid at an exercise price of INR 238 per share. With this, we can now open the floor to questions and answers.

Operator

[Operator Instructions] The first question is from the line of Mr. [ Vivek Gupta ], an individual investor.

U
Unknown Attendee

Yes. Sir, being an individual investor, being invested in Sterling and Wilson on account of considering it as a global EPC player, but the numbers which are coming quarter-after-quarter is not giving me any confidence. And on top of it, I have been seeing that management is attributing these losses to COVID. But I have seen that there are companies which are performing, and we should not just attribute this to COVID. And on top of it, like post listing, we have been seeing that the diversion of funds was there, and we have been like committed for ICDs repayment. What is pushing management to settle these ICDs at the last leg of the committed date? Because investors are -- being an investor, I'm losing my confidence in Sterling and Wilson totally. How you are going to assure me that Sterling and Wilson is on the right path of development and how you can reassure that confidence?

B
Bahadur Dastoor
Chief Financial Officer

I will address your question. I believe there were 3 parts to it. The first part, which you said, is we should not attribute everything to COVID. Mr. [ Gupta ], COVID is a reality. It has been there from the last 18 months. We have faced the impact. We were one of the first companies to mention that COVID is going to impact us in March '20, and it did. COVID has impacted all organizations during this year, and there has been a substantial increase in module and commodity prices. This is also a reality. This is something that has affected the solar entities all across the world and Sterling and -- amongst other businesses, and Sterling and Wilson Solar has been no exception. So we have attributed where it needed to be attributed. Coming to the question of the ICD repayment. As we have mentioned, there has been a lot of ICD repayment in the previous financial year as well as almost INR 172 crores of ICD repayment from the start of this financial year. The figure is now down to INR 740 crores. In the last Board meeting, the promoters have given confidence to the Board of meeting their objectives of taking off all the ICDs by the appointed date of September 30, and we are hopeful and confident that they will do the same. That is all the information that I have, which is based on the confidence given by the promoters to the Board.

U
Unknown Attendee

So -- sir, so it means like we can be rest assured that these ICD payments won't be delayed further. Like I've seen that you have attributed some INR 850 crores or INR 805 crores of securities in case these ICDs -- as a part of this ICDs repayment. But the only thing is, like, see, these ICDs are big overhang on Sterling and Wilson. The IPO price which came was somewhere around INR 770, INR 790. And post listing, it has eroded shareholders' wealth to a great extent. And till date being the investor, I don't know about others, but I am not at all compatible in booking losses and on top of it being a part of SP -- the Sterling and Wilson shareholder. So at least it's a request -- sincere request from my side that management or promoters -- they should be transparent enough to meet this trust -- to regain the trust of investors. It would be good.

B
Bahadur Dastoor
Chief Financial Officer

Mr. [ Gupta ], thank you for your confidence. And as I said, the promoters have given this assurance to the Board, and that's what we are transparently projecting to you. I, once again, thank you for remaining invested, and thank you for the confidence.

Operator

[Operator Instructions] The next question is from the line of Ankit Gupta from Alchemy Capital.

A
Ankit Gupta

Sir, what's the status of our negotiation with our Chinese vendors regarding solar modules pricing? Like on the last call, we discussed something about it that we are negotiating with them. Are there any progress on that front? Yes.

A
Amit Jain
Global CEO

Yes. So as we discussed our last call that going forward, whatever new orders we are going to negotiate with our Chinese module suppliers, we are going to ask for higher amount of bank guarantees. So it is on the same line. So whatever new orders we are going to take, and if it is not passed through to the customers, in that case, we are going to seek higher amount of bank guarantees as compared to what we were taking earlier to safeguard against all the risks arising from the module uncertainty in the market.

A
Ankit Gupta

Okay. Okay. And sir, like are we seeing this solar module prices to again being revert in our view. What's causing -- because of the chip shortage or per plate, I think, it has increased to about $0.25 -- $25 per watt peak or levels. What do you think can be the peak?

A
Amit Jain
Global CEO

No. Actually, past 1 month or so, what we have been seeing that trend, that module prices are stabilizing. And whatever the market reports we are hearing that a lot of capacity addition is happening in China, both on -- for the module manufacturing as per the upstream raw materials of polysilicon and glass. So that is happening, and we continue -- we hope that it continues to be stable, but it's very difficult to give like how it is going to pan out in next coming quarters. But certainly, last 1 month or so, we have seen prices getting stabilized.

A
Ankit Gupta

Got it. Got it. And sir, you talked about out of INR 8,700 crores of order book, around INR 2,000 crores of order book might be unviable. What was that number? I missed that number.

A
Amit Jain
Global CEO

So that number is around INR 2,000 crores where we see that it may not be viable for developers, but we continue into the negotiations, which we expect. So that we say it may not be viable, but discussions are ongoing with the customers. And we will get more clarity on how it pans out in the next coming quarters.

A
Ankit Gupta

And sir, for the remaining INR 6,000-odd crores of order book, the gross margins could be negative or it would be like 2%, 3%? What can be an approximate number for the remaining order book?

A
Amit Jain
Global CEO

Yes. So I'll request Bahadur to give you guidance on that.

B
Bahadur Dastoor
Chief Financial Officer

So the gross margins, obviously, would be suppressed, and they would not be the historical gross margins that we have. But I would just like to add that the gross margins, which we have seen in this particular quarter, also bear the effect of projects, which were in the negative and for which all the losses were taken in March '21. So -- however, in the current quarter, you do have revenue and cost equal to revenue because all the losses have to be front-ended, and this has suppressed, in percentage terms, the margin. So if we were to remove out the impact of such zero-level -- zero-margin jobs, which are ongoing, margins actually would have been slightly higher than 5% in this quarter. Going forward, we do believe that the margins will be much higher than 5% by the end of the year.

A
Ankit Gupta

Okay. That's good to know. And last question from my end. Why the other expenses also continue to be higher? Is it because of the freight cost? What's the key item in this figure?

B
Bahadur Dastoor
Chief Financial Officer

So when you're looking at other expenses, it does not include freight costs because all costs, which are attributable to the project, go up before the gross margin. What you're seeing as overheads, which is about INR 80 crores, is comparable with the INR 80 crores last year where also the salary costs as well as traveling was much lower due to the higher impact of COVID. In spite of that, it has been maintained, though the management is looking at reducing cost overheads all across the board, and that is what we are working on to bring it down much lower than what it was in the previous year, the number being INR 324 crores in the previous year.

A
Ankit Gupta

Okay. So we are aspiring project numbers for the fiscal year, full FY '22?

B
Bahadur Dastoor
Chief Financial Officer

To come down much below that. That number which I gave you was FY '21. We are trying to bring it down as much as possible, which is why efforts are ongoing across the board.

A
Ankit Gupta

Okay. Okay. And sir, just what you talked about new businesses for energy storage and hybrid. Just on our capability front, how are we hiring our team for that? And how can cost be increasing for those kind of project level cost? So it will be front ended, I believe, right? If we have to build on any project, we must have some capability in our team. How are you doing that?

B
Bahadur Dastoor
Chief Financial Officer

So let me start off with this, and then Mr. Amit can add. The business pipeline that we are looking at for this kind of projects are between INR 800 million to about INR 1 billion. So at that point in time, you would require to build up your business development team, and there would be costs incurred for that. Now if there are -- if that is the kind of pipeline that we are looking at, we would be seeing some kind of overheads in the range of about INR 25 crores to INR 30 crores, which is normal to build up this size. That is, of course, assuming that there are no orders which come in. The group has evaluated its capabilities in doing this. There are certain prequalifications, which would require the involvement of partners, which will be taken up appropriately from time to time. If Amit has anything, which he would like to add, he may go ahead.

A
Amit Jain
Global CEO

And I would like to add that our geographical presence across the globe and existing teams and existing clients will help us in leveraging. And overhead, despite adding a new business, would be minimal and we'll be achieving a lot of synergies, which will give us a lot of cost advantages even in the new lines of businesses by keeping overheads low.

B
Bahadur Dastoor
Chief Financial Officer

And just one more point that I would like to add is that this line of business has long-term orders. So it is not like solar orders, which get executed between 12 to 15 months. These take anywhere between 24 to 36 months. So we will also be having not only order book visibility, long-term order book feasibility, also revenue visibility.

Operator

Next question is from the line of Mr. Kunal Koladiya from ANOVA CAPITAL.

K
Kunal Koladiya

Yes. Sir, I have 2 questions, if I may. Sir, first one is like given the commodity impact, would you consider bidding for EPC contracts, excluding the module procurement for shorter-duration contracts as well?

A
Amit Jain
Global CEO

Yes. So that's what we are considering. That we are -- like in our existing 2 big markets, U.S. and India, already we are bidding for projects without modules. And even in the geographies we are bidding with modules, we are now adopting a strategy of passing the risk on to the customers. So that is very much on board. So we are considering both the options. We're bidding without modules and where we are bidding with modules, passing on the cost risk to the customers.

B
Bahadur Dastoor
Chief Financial Officer

It is also important to further add that unlike in India, where, ex modules, your price of BOS is much lower, it's almost 2, 2.5x that in the international market. So it is not that if we were to bid ex modules or modules as a complete pass-through, there would be a very heavy shrinkage in revenue because the 2 BOS markets are not comparable, the India and the international.

K
Kunal Koladiya

Okay. Okay. That's helpful, sir. And secondly, sir, what is our current status of project execution or, you may say, operating efficiency in Australia in the light of COVID-19 lockdowns?

A
Amit Jain
Global CEO

So in Australia, so far, COVID-19 lockdowns have not impacted our project execution because the lockdown in the cities and project site continue to operate the same manner. However, there have been some delays on account of delay in module supplies. But the project's execution remains unimpacted on account of COVID.

Operator

[Operator Instructions] The next question is from the line of Mr. V.P. Rajesh from Banyan Capital.

V
V.P. Rajesh
Managing Partner & Portfolio Manager

My first question is just trying to understand this price impact that we got hit by. So -- and I apologize in advance if some of these questions are repetitive. But just trying to understand how much did you book in the last year, the losses on the current order book. And in the current order book, what percentage is still going to be impacted by these price escalations?

B
Bahadur Dastoor
Chief Financial Officer

I'll start off on that. As you would have seen in our investor presentation for March '21, the one-offs, which had an impact on that quarter, were about INR 374 crores. This included the cost of contractor going bankrupt due to COVID. This is also the cost escalation due to elongation of time due to such contractor having gone bankrupt. It included the module, freight and commodity price increases, and it also included certain provisions for liquidated damages, which the management prudently felt should be made on account of extension of time due to COVID. So the impact that was there was about INR 370-odd crores. Now in the current quarter, we have taken the margins, which were there for March '21, and continued that further. There have been no further losses on those projects, except in case of one where a particular module supplier had asked for an increase in price, and that was, to a significant extent, also agreed to be compensated to us by the customer. That has been mentioned in our investor presentation for this quarter where we have put it as price variations. So other than that, there has been no other major impact in this current quarter. Whatever had to be taken was taken in the last quarter. Margins do continue to remain suppressed because the impact of that will continue over the execution and life cycle of the project.

V
V.P. Rajesh
Managing Partner & Portfolio Manager

Right. So out of that INR 370 crore figure last quarter, how much was due to nonrecurring things, like bankruptcy, et cetera? If you remove all that pertaining to price escalation, freight cost and module prices, what was that portion of INR 370 crores?

B
Bahadur Dastoor
Chief Financial Officer

So I will just respond to that in a minute. The total amount of...

V
V.P. Rajesh
Managing Partner & Portfolio Manager

No problem.

B
Bahadur Dastoor
Chief Financial Officer

Just a minute. That amount was about INR 102 crores for -- approximately, as I remember. It was INR 102 crores for the subcontractor going bankrupt; roughly about INR 80 crores, INR 85 crores on modules and freight and about INR 100 crores, if I remember correctly, on other extension of time due to COVID-19.

V
V.P. Rajesh
Managing Partner & Portfolio Manager

Okay. So the price impact was [Technical Difficulty]

B
Bahadur Dastoor
Chief Financial Officer

I'm sorry. Your voice broke.

V
V.P. Rajesh
Managing Partner & Portfolio Manager

Sorry. The impact of the price escalations and freight was around INR 80 crores, INR 85 crores, that was basically, correct, from out of that INR 370 crores?

B
Bahadur Dastoor
Chief Financial Officer

We extend it pertain to the last quarter. You have to understand that as the project progresses -- so unless there is a loss, only that loss would be booked front-ended. But if there is anything which the project remains positive, that suppressed profit would continue over the life cycle of the project.

V
V.P. Rajesh
Managing Partner & Portfolio Manager

Understood. Understood. Okay. So now coming to this year, out of this book of INR 6,000 crores, which you think is viable, how much is the price hit you are taking because of which our margins are going to be suppressed?

B
Bahadur Dastoor
Chief Financial Officer

The price hit that had to be taken has already been taken. The margins that are there in the particular quarter, in this one, we have said that it is also impacted by no margin coming where the loss has been booked in the previous year. As I mentioned, if that was to be eliminated, the margins would be in the region of 5%. Orders that we have booked in the current quarter have come at our historical margins. So we believe that we should have a much more than 5% margin at the end of the year. We will be in a position to give a correct margin guidance by the time we come to the next quarter call.

V
V.P. Rajesh
Managing Partner & Portfolio Manager

Okay. And just last one question on this topic. So how should I think about it that out of this INR 6,000 crores that you have, order book, what percentage is where you are not able to pass through these price escalations, and therefore, that will be on a lower-margin trajectory? I understand that because it is not negative, you can't book the losses upfront, but we know that over the next few quarters you're not going -- your margins are going to be subdued. So I'm just trying to get a sense what percentage of the book is in that particular bucket.

B
Bahadur Dastoor
Chief Financial Officer

About 40% to 45%.

V
V.P. Rajesh
Managing Partner & Portfolio Manager

Okay. Understood. On the new business initiatives that you have talked about in the presentation, are you also thinking about getting into data centers?

B
Bahadur Dastoor
Chief Financial Officer

Your voice is not clear. You will have to repeat your question.

V
V.P. Rajesh
Managing Partner & Portfolio Manager

I'm sorry. Sorry about that. My question is in the new business initiatives that you have talked about in the presentation, are you also planning to get into the data centers as well? Or what's the thinking on that side?

B
Bahadur Dastoor
Chief Financial Officer

No. We will not be getting into data centers.

Operator

The next question is from the line of Subhadip Mitra from JM Financial Service.

S
Subhadip Mitra
Power Analyst of Institutional Equities Research

Yes. Just wanted to get a sense of how do you see the Indian solar market evolving because we've seen a lot of entrants and a lot of existing utilities who are coming up with big plans. And how do you see the EPC market here evolving in India? I'm sorry if you've already answered this question. I joined the call a little late.

A
Amit Jain
Global CEO

No. No. So thanks for the question. So we see, as you yourself has said, that there is a lot of plans and a lot of announcements are happening. So we continue to see the robust uptrend in the solar market, both domestic and international. So in India, this year itself, we see a bid pipeline of more than 6 gigawatts, which is coming in. And internationally, we expect a bid pipeline of more than 15 gigawatts to get -- to be finalized this year. So for the EPC industry, the prospects remain strong, and the market will continue to grow at the rate of approximately -- at the rate of 15% per annum for next 3 to 4 years.

S
Subhadip Mitra
Power Analyst of Institutional Equities Research

Understood. So within this, let's say, bid pipeline of 6 gigawatt in India, would there be any target market share that you're looking to get? Or let's say over the period of the next maybe 3 to 5 years, what is your target market share, say, within India and international? If you could just throw some light on that.

A
Amit Jain
Global CEO

Yes. So see, our target hit rate usually has been 14%, 15% of the targeted pipeline. So we expect in India this year to be going somewhere around 1.5 to 2 gigawatts. And depends upon the project closure which are going to happen in coming years, so we'll continue to maintain our market leadership position.

B
Bahadur Dastoor
Chief Financial Officer

Also, if you see, we have -- if you see our investor presentation, we have won about 623 megawatts already in India in the -- from April onwards.

S
Subhadip Mitra
Power Analyst of Institutional Equities Research

Understood. And I mean how are these projects typically? Are these also tend to be fixed-price contracts or they tend to be more of variable cost where you can pass on the module risk to the final customer?

A
Amit Jain
Global CEO

No, no, no. As far the Indian market is concerned, it is -- the module risk is on developers. So we are bidding in Indian markets without any module risk.

S
Subhadip Mitra
Power Analyst of Institutional Equities Research

Understood. And in terms of the international market, the 15-gigawatt market size that you talked about, there, again, you would be targeting about 14%, 15% market share?

A
Amit Jain
Global CEO

Yes. That's correct. So our historical strike rate has been 14% to 15%, and we'll maintain that as well in international markets. But that can vary across geographies, but consolidated hit rate would be 14% to 15%.

S
Subhadip Mitra
Power Analyst of Institutional Equities Research

Understood. So would the international contracts then be more of these fixed-price contracts?

A
Amit Jain
Global CEO

No. As we elaborated on our earlier question that U.S. is a market where we -- without modules and in all other markets where we did EPC with modules, we'll pass on the price risk on to our customers.

Operator

The next question is from the line of [ Priyanka Singh from Atidhan Securities ].

U
Unknown Analyst

I have a couple of questions. First of all, what is the global market size of the new business verticals that we are targeting? And what would be the industry margin profile over here?

A
Amit Jain
Global CEO

Yes. So we expect the hybrid energy market to be close to $3.5 billion to $4 billion by 2025 and the energy storage systems to grow to next 3 to 4 years up to $12 billion. So that's a significant market size. And more of the clients in this market is our existing clients. And as and when we come to waste to energy market, that is going to be in excess of $5 billion market in next few years. So there, we see the market is pretty big, and we expect to maintain our historical strike range, which we have for our existing business. So that's what we expect to maintain. And margin profile of the industry is 10% to 15%, where the markets are currently, and we'll be also maintaining margins in that particular bandwidth.

U
Unknown Analyst

Okay. And what kind of synergy benefits we are -- we expect to get from these new verticals?

A
Amit Jain
Global CEO

So there will be significant synergies because we are in the same line of business. As far as hybrid and energy storage is concerned, the client profiles are same -- clients are same and geographies are same. And majority of the business is expected to come from Australia, Europe and U.S.A., where we have significant presence now. So we'll be -- there will be -- just we'll be adding going forward as for the hybrid and battery storage systems only the project execution team, so -- and we'll be taking the advantage of our existing BD engineering project execution teams in those geographies. So synergies are going to be significant in these markets. As far as these 2 energies is concerned, we'll be -- as we look forward to more order bookings, so we'll be significantly building teams there. And we expect like the order book from these 2 new verticals going forward in the range of 5 -- in excess of $500 million to $1 billion range in the coming years, and there will be proportional INR 25 crores to INR 30 crores of overheads on this account in coming years from new verticals.

Operator

[Operator Instructions] The next question is from the line of [ Amit Shah from Ace ] Securities.

U
Unknown Analyst

Sir, I have one question. Sir, can you indicate the expected margins for FY '22 and '23 based on the current commodity prices and freight cost? Do we foresee any further provisions due to current prices?

B
Bahadur Dastoor
Chief Financial Officer

As we had mentioned, the current year's margins, why we will give a better range when we come to the second quarter call, right. We are at about 5% and are expected to grow over this year. As far as FY '23 is concerned, that will also be something we will try and put out as the year goes by. The new orders, though, as we have mentioned, comes at our historical margins of between 10% to 15%.

U
Unknown Analyst

Okay. Sir, do we see any further provisions?

B
Bahadur Dastoor
Chief Financial Officer

At this stage, we do not see any further provisions that are required.

Operator

The next question is from the line of Faisal Hawa from H.G. Hawa and Company.

F
Faisal Hawa

Sir, to me, this looks like a business which has a very good tailwind because of continuously the world shifting to solar power. But somehow I feel that our place in it as an EPC player has, first of all, very low margins. And those low margins probably make us deal with not the very top end of suppliers of solar panels, et cetera. And that is why we -- when we deal with the more fragile suppliers, they are not able to fulfill their commitments or they go bankrupt because -- and you may not have done this. So we are actually [Technical Difficulty] a small disaster to another and the promoter also having his own problems. I mean this is looking like one storm is over and another comes in after 6 months. So can you just comment on because this is looking more structural rather than any kind of management problem.

B
Bahadur Dastoor
Chief Financial Officer

So Faisal, 2 points. First of all, we take solar panels only from the Tier 1 solar manufacturers. We do not work with Tier 2 and below solar manufacturers at all. So the ones who have reneged are not the small and the fragile. They are the ones who have the largest capacities in the market. And these -- out of that, a couple of them are the ones who have reneged on their contract. It is an industry-wide issue. It is not something which is related to Sterling and Wilson Solar alone. Secondly, as far as the customers and developers are concerned, we also deal only with the top-tier customers and developers, and therefore, it is not a question of our margins getting affected because we deal with fragile vendors and customers.

Operator

The next question is from the line of Dixit Doshi from Whitestone Financial Advisors.

D
Dixit Doshi

My first question is related to this current order book. You mentioned that out of which around INR 2,000 crore order book is currently not viable. So by when do you see that the negotiation of higher prices will be over, and we can start executing that order as well?

A
Amit Jain
Global CEO

So we are in discussion with our customers. And I hope by the time we get on the next earning call, we would have concluded and get some sense of direction where we are with respect to those particular orders. So discussions are on, and we'll get to know in the next few weeks where we are with respect to those orders.

D
Dixit Doshi

Okay. Secondly, the remaining order book of INR 6,000 crore approx, that entire will be executed this year?

A
Amit Jain
Global CEO

Yes. Most of it will execute it this year. As we have said, we will be finishing the entire order book in the next 12 to 15 months, but majority of it will be executed this year.

B
Bahadur Dastoor
Chief Financial Officer

To that, of course, you would add orders that you have booked in the current year or book and bill as we call it. So a part of that would also get executed in the current year, which would add to the revenue.

D
Dixit Doshi

Okay. And last question, you -- can you give a guidance of what kind of order inflow you expect for this year? You mentioned that we expect a strong inflow in H2. So in terms of amount, if you can give a broad range because you did mention in terms of how much gigawatt, but sometimes it varies a lot because in India the per gigawatt -- per megawatt order book is much different than per megawatt in Australia.

A
Amit Jain
Global CEO

Yes. So as we said that the bid pipeline, which we see and which we're likely to see will get concluded, is in excess of 15 gigawatts, and we'll maintain our strike range of 14% to 15%. So -- and they're going to be lumped. So at this point of time, it is difficult to give geography-wise breakup because this pipeline is spread across geographies and what should be the conversion rate across various geographies. So that -- we'll be able to give you more color to your answer the next 1 quarter where we are with respect to that, but we'll maintain our historic hit rate of 14% to 15% on a pipeline of more than 15 gigawatt across the globe.

D
Dixit Doshi

So broadly -- just broadly, I don't hold you, but broadly INR 6,000 crores to INR 8,000 crores of order is a fair range?

B
Bahadur Dastoor
Chief Financial Officer

Let us not put a number. It can, of course, be calculated because like you yourself said, it's different across different geographies. But yes, but it would be -- we are expecting it to be larger than last year and corresponding order book.

Operator

The next question is from the of Shantanu Mantri from MKVentures.

S
Shantanu Mantri

Sir, I just wanted to get this correct. These new lines of business that we are talking about where we have our existing clients already there, one is this hybrid energy, and the other is waste to energy. So can you throw some more light that what exactly would we be doing? And I also heard you saying that our order book of what we are trying to get is somewhere around $500 million to $1 billion orders. Is that right?

A
Amit Jain
Global CEO

So first of all, we'll be setting up as far as the hybrid and battery energy storage systems are concerned. So we are looking at stand-alone projects in these markets and the projects which are coupled with our existing solar portfolio. So where we'll be providing these services where our clients are coming up with both solar and storage solution or they want some other additional power-generation sources -- renewable power-generation sources, coupled with solar. So that we'll be providing to our existing clients, and we'll see a lot of these kind of projects coming up in our -- with our existing clients in existing geographies. As far as with the order pipeline, which we are talking about, that will be building up gradually in years to come. So that is the revenue forecast which we have and which we'll be finalizing after getting our shareholders' approval, and that will be in years to come. So we'll build up gradually what would be the revenue and order book in next 2 to 3 years from the new business segments.

S
Shantanu Mantri

All right. All right. And sir, say, let's just skip FY '22 for now with all that has happened, and major part of our order book will be facing this suppressed margins. But if I am to go ahead and, say, FY '23, '24, what should we take for the -- on the solar EPC part? What normalized EBITDA margins can we consider? Or will there be a new normal here? I just wanted to get your sense there.

B
Bahadur Dastoor
Chief Financial Officer

No. No. We do not believe the present is the new normal. We believe that FY '23 onwards, we should be back to our historical margins of between 10% to 11%. Now when I say historical margins, I'm talking about the gross margin. Of course, as the revenue size increases and overheads are in control, we will have operating leverage because the overheads would come down percentage points below what it is right now, thereby giving us an increase in the EBITDA. So we are looking at 10% to 11% and, if everything falls into place, overheads of between 3%, 3.5%. That's our target.

S
Shantanu Mantri

Sure. Sure. Understood. And sir, one last question, if I may. So for these new lines of hybrid and waste to energy, so what I heard was like around INR 25 crores to INR 30 crores would be spent like on -- as overhead, right? Other than that, any capital expenditure we would have to incur?

B
Bahadur Dastoor
Chief Financial Officer

First of all, this INR 25 crores, INR 30 crores is not going to be a day 1 expenditure. It will be a gradual buildup, seeing as how orders are there, new markets, business development team, engineering team, et cetera. As Mr. Amit mentioned, there is a significant amount of synergy. What we have given you is what we believe would be an estimate in case no orders come in. Also, what Mr. Amit mentioned was this is something which will be built up because these are long gestation projects unlike solar. As we mentioned, this can take between 24 to 30 months. It will give us an order view, a long-term order view as well as a long-term revenue view, which, right now, has been missing insofar as the stand-alone solar EPC business is concerned.

Operator

The next question is from the line of [ Danesh Mistry from Investor First Advisors ].

U
Unknown Analyst

I had a couple of questions. The first one is on the receivables piece. So whilst you've touched upon the IL&FS receivable, if you could give us some sense on the time period for recovery of the receivables of INR 102 crores from the related party as well as some status update on Argentina. That was question number one. Then I'll just have 1, 2 more.

B
Bahadur Dastoor
Chief Financial Officer

That's fine. Yes. As we have mentioned in our investor presentation that the matter as far as Argentina is concerned, it is under arbitration. This is something that will happen in the U.S. In the U.S., generally, arbitration takes about a year, and we are hopeful of getting a response by that time. There have been claims and counterclaims by both parties. We believe our claims are extremely strong, and we have a legal opinion to substantiate that. So matter will be resolved in that period of time. As far as the related party receivables from against the sale of plant is concerned, we believe that the plant is just in the final stages of commissioning. We believe that we should be able to have this somewhere towards the end of this year. And this is our estimate at the moment, yes.

U
Unknown Analyst

Got it. Got it. And this is sale of plant of the related party, you said, right?

B
Bahadur Dastoor
Chief Financial Officer

Yes. Yes. The plant that we are making, so...

U
Unknown Analyst

Understood. Understood. So essentially, hopefully, by March '22 is when we'll get recovery of this INR 102 crores?

B
Bahadur Dastoor
Chief Financial Officer

That's right.

U
Unknown Analyst

Fair enough. And you -- in your commentary as well as in your presentation, you've touched upon the negative working capital, which is excellent. But you did touch upon some delay in payment to vendors. So was this on a contractual basis? Or was this for any other reason?

B
Bahadur Dastoor
Chief Financial Officer

So it was a mix of contractual as well as cash flow issues. Right now, the overdue vendors would be in the region of about INR 200 crores to INR 250 crores. The -- even after that, you would see that the working capital would still continue to be negative.

U
Unknown Analyst

Yes. Got it. Got it. But we've paid off these overdue vendors now or do we continue with the cycle?

B
Bahadur Dastoor
Chief Financial Officer

We paid off about INR 50 crores of those vendors in the previous months, and we are looking at liquidating them as soon as possible.

U
Unknown Analyst

Interesting. Interesting. And one more question was on our term loans. So we brought it down very strongly, and we have about INR 64 crores. You mentioned, INR 24 crores in Q2 and INR 40 crores in Q3. Do we plan to refinance these or just pay them off and be 0 term loans?

B
Bahadur Dastoor
Chief Financial Officer

So it depends on a combination of how soon the promoter inflow is coming, last date of which is September 30 or whether we have operational cash flows to take care of it. In the absence of which, of course, there could be ways and means to do a bridge refinance till such time as this is completely closed.

U
Unknown Analyst

Understood, Bahadur. And sorry, one last question from my end, and then I'll just get off. In the solar module piece, you mentioned that this has resulted in an overall increase in estimated cost of projects by $21 million. So is that the margin hit that we expect to flow through by the end of this year, this $21 million?

B
Bahadur Dastoor
Chief Financial Officer

A part of it -- a major part of it has already been taken in the previous year, and the balance is what has suppressed the margin over the existing contracts. Of course, as we said, we have received a substantial amount of variation also from the customer to compensate us for this.

U
Unknown Analyst

Got it. Got it. So broadly, can we say about 2/3 was booked last year and 1/3 is left?

B
Bahadur Dastoor
Chief Financial Officer

No. Not really. It would be closer to half and half.

Operator

Ladies and gentlemen, that would be the last question for today. I will now hand the conference over to Mr. Amit Jain for closing comments.

A
Amit Jain
Global CEO

Yes. We would like to again thank everyone for joining this call and for your continued support all this while. We hope we have been able to address all your queries. For any further information, kindly get in touch with Mr. Vishal Jain or Strategic Growth Advisors, our Investor Relation advisers. And thank you once again. Have a great day. Bye.

Operator

Thank you very much. On behalf of Sterling and Wilson Solar Limited, that concludes this conference. Thank you for joining us. You may now disconnect your lines. Thank you.

A
Amit Jain
Global CEO

Thank you.