HG Infra Engineering Ltd
BSE:541019

Watchlist Manager
HG Infra Engineering Ltd Logo
HG Infra Engineering Ltd
BSE:541019
Watchlist
Price: 1 276.15 INR -0.28% Market Closed
Market Cap: 83.2B INR
Have any thoughts about
HG Infra Engineering Ltd?
Write Note

Earnings Call Analysis

Q1-2024 Analysis
HG Infra Engineering Ltd

Company Maintains Revenue and Monsoon Impacts Progress

The company is steadfast in maintaining its revenue target of INR 5,500 to INR 5,600 crores for the year, despite an early monsoon impacting project progression. Nevertheless, a focus on achieving 22% to 25% progress leaves room for optimism. Updated guidance reflects a narrowing in order inflows to INR 7,000 crores to INR 8,000 crores, a reduction from previous estimates, due to the delaying of project awards. Margins are anticipated to stay stable, hovering around 15% plus. Looking ahead, the company is keyed towards significant revenue growth, aiming for a Compound Annual Growth Rate (CAGR) of 20% to 25% post the running year FY24.

Revenue and Profit Margin Stability

The company has set a revenue target of INR 5,500 crores to INR 5,600 crores for the current year. Despite early monsoon impacting some project progress, the company aims to improve and maintain a 22% to 25% year-on-year growth. Moreover, profit margins are expected to stay healthy at above 15% for this year.

Project Developments

The company reported solid progress on infrastructure projects. For instance, INR 500 crores of work on all Hybrid Annuity Model (HAM) projects was completed in the quarter, with Adani Ganga Expressway contributing INR 475 crores. Additionally, the financial closure documents for the Karnal Ring Road project are to be submitted soon, and the appointed date for project commencement is expected by mid-September. The financing for three projects is anticipated in the first quarter of the following fiscal year, possibly by October.

Future Bidding and Projects Pipeline

The company has set an aim for NHAI to award 4,000 kilometers of projects, from which it expects to secure at least INR 4,000 crores to INR 5,000 crores worth of projects. The bids for the Pune Ring Road project are already submitted, and awards for these projects are expected by October or November. With a diverse pipeline of projects in the railway sector across various regions like Maharashtra, Gujarat, and Uttar Pradesh, the company is actively bidding and plans to continue doing so for upcoming opportunities.

Revenue and Order Inflow Guidance

The company's target for the year is to add INR 7,000 crores to INR 8,000 crorrs in new orders. From this target, about INR 2,000 crores is expected to come from sectors other than highways, such as railways and metros.

Earnings Call Transcript

Earnings Call Transcript
2024-Q1

from 0
Operator

Ladies and gentlemen, good day, and welcome to H.G. Infra Engineering Q1 FY '24 Earnings Conference Call hosted by Go India Advisors. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Ms. Sana Kapoor from Go India Advisors. Thank you, and over to you, ma'am.

S
Sana Kapoor

Thank you, Seena. Good afternoon, everybody, and welcome to H.G. Infra Engineering Limited's earnings call to discuss the Q1 FY '24 results. We have on the call Mr. Harendra Singh, Chairman and Managing Director; and Mr. Rajeev Mishra, Chief Financial Officer. We must remind you that the discussion on today's call may include certain forward-looking statements and must be therefore viewed in conjunction with the risks that the company faces. May I now request Mr. Harendra Singh to take us through the company's business outlook and performance, subsequent to which we will open the floor for Q&A. Thank you, and over to you, sir.

H
Harendra Singh
executive

Yes. Thank you, Sana. Good afternoon, ladies and gentlemen, a very warm welcome to the Q1 FY '24 earnings conference call of H.G. Infra Engineering Limited. We are pleased to welcome you all here today to share the highlights of our quarterly performance, achievements and our vision for the future. I hope all of you have had the opportunity to review the investors presentation and the financial results which has been made available on the exchange. The entire country is drenched with a heavy rains and overall; it's much more than expected. Despite of all these abnormal prolonged, which has affected the sector overall, we have been able to meet our expected numbers, though it was slightly less than our expected target of this quarter. At the same time, we are working on the strategies, priorities to overcome these challenges. Performance, quality consciousness and safety measures remain our key element in our success story, which is deep rooted in all our activities. And the sector, we have firm believe that the government is expected to continue with its thrust on the infrastructure sector, a lion's share of which would be towards the road, highways and railway sector, considering the highest budget overlay in the sector and the new initiatives being taken to support the project completion on time.There has been new firms bidding in the first phase, but in the next quarter, it will propel and to cover the targeted numbers. Let me start the growth journey of this quarter and give you the glimpse of the operational highlights first. From quarter ended June 2023, our order book stands at INR 11,674 crores, which has established our presence across 11 states with the EPC segment comprising of 53% and HAM segment constitution the remaining 47%. There are the updates on the ongoing projects. Talking about the EPC projects, the Ganga Expressway project has achieved approximately 23.5% completion. The project is running well in the time as per the contract timeline. In Delhi [indiscernible] project, we have made significant progress of around 65.8% and which is expected to be completed by December '23.The Neelmangala-Tumkur project is progressing well and has reached an execution status of 10.6%. The progress of various HAM projects is also looking good and moving ahead as per the planned schedule. Below is an update on the same. Progress of total execution of Package 5 of Raipur-Visakhapatnam Orissa OD5 it stands at 43.6% completion. Package #6 of Raipur-Visakhapatnam Orissa project OD6 it is at 46.3%. Again, in AP1 of Raipur-Visakhapatnam corridor, it has reached completion of total of 46.7%.At Khammam-Devarapalle package Project 1, we have -- we have already achieved 16.3% completion. While in Package 2 of Khammam-Devarapalle, we have reached 24.4% completion. Rewari Bypass we have applied for PCOD as the project is nearing completion stage, and we are expected to receive it soon.As you know, we have established our footprint and our order book with diversification and successfully ventured into the railway and network sector, I would like to touch the progress of these projects pile. We have completed 13% of DMRC's metro project. Execution of this project is going well on track and will be completed as per the contract time line. At the last year Himachal Pradesh railway projects of RVNL, where we have recently received the appointed date is progressing well. At the Kanpur railway station project, the mobilization is going on a very fast track.Let me now share other significant updates. We have received COD of Maharashtra Package 1, 2 and 3 or more -- in this quarter, although we have received PCOD of these packages after 2020. Although our Kanpur station and small project of NTPC has been received on 5th June 2023 and 23 May 2023, respectively. Apart from this, we have also received a project date of RVNL rail projects on 24 May 2023.For our 3 new HAM projects, namely Karnal -- Varanasi Ranchi Kolkata Kolkata Expressway Package# 10 and 13 and Karnal projects. Financial modeling is expected to be completed through August 23, and the appointed date will be received in quarter 2 and quarter 3, respectively.In Karnal ring road, the land availability is around 86%. And at Jharkhand Package# 13 of Varanasi Kolkata Expressway, that is around 50%.Coming to the financial highlights of this quarter. At the standalone level in Q1 FY '24, the standalone revenue reached at INR 1,271.3 crores, indicating a notable 19.3% year-on-year growth from INR 1,065.7 crores recorded in Q1 FY '23. The standalone EBITDA of quarter 1 FY '24 was INR 204.8 crores, reflecting a year-on-year growth of 26%. The PAT and the PAT margin for Q1 FY '24 stood at 9.3% and INR 118.4 crores. That is compared to 9.2% and INR 97.6 crores last year. PAT grew by 21.3% in Q1 FY '24 on a year-on-year basis.Regarding the company's debt position on a standalone basis, the gross debt amounting to INR 665.2 crores, which includes the working capital debt of INR 178.6 crores. Term loan and current maturity, along with the trade remit totaling INR 389.6 crores and the NCD of INR 97 crores.Moving on to the consolidated numbers. During quarter 1 FY '24, the consolidated revenue surged to INR 1,351.2 crores, marking a 22.2% year-on-year growth compared to INR 1,105.9 crores recorded in Q1 FY '23. At the consolidated level, the EBITDA of Q1 FY '24 was INR 280.7 crores, displaying a robust year-on-year growth of 41.1%. The PAT margin for Q1 FY '24 consolidated stood at 11.1%, resulting in a PAT of INR 150.4 crores as compared to INR 109.4 crores in Q1 FY '23. The resurgence of significant growth of 37.4% in PAT on a year-on-year [technical difficulty] stood at a consolidated level, the gross debt amount is amounting to INR 2,131.2 crores. The total equity requirement for the 12 HAM projects is estimated to be INR 1,592.6 crores, and that is until FY '26. As of March '23, INR 758.7 crores has been already been invested and there is a projected investment of INR 407.4 crores in this financial year FY '24.Progress update on monetization of [indiscernible]. Last quarter, we have signed share purchase agreement of 4 HAM projects with highway infrastructure trust backed by [ KCR ] we are awaiting some procedural approvals to close the production. We have received lender's approval for 2 SPVs and approval of third SPV that is Gurgaon-Sohna in principal is expected by 10th of August. Other conditions that we met are either completed or in an advanced stage of compliance. The final approval from NHAI is expected by 31st of August 2023. Once receipt of NHAI's final approval, we will proceed for the completion of our mission, including the charter of shares and receipt of the consideration till 30th September 2023.For the fourth HAM project that is Rewari Bypass Package 4, approval process will be intermediate and the second tranche will be initiated in December '23 quarters that is post COD of Rewari Bypass. We are optimistic that we would be able to complete this transaction well within the time and we do not see any challenges in the current scenario.Before I end my speech, let me assure that we would be able to meet our expected numbers of growth with 2025 it was an upside in the revenue, and we would bring momentum in the order inflow with the new project in the tune of INR 7,000 to INR 8,000 crores this year. We are working mainly on the operational efficiency and executional capabilities to add every penny to our EBITDA and PAT margin.Digital transformation remains on our priority from automation in the plant and machinery, operations and other vehicles, which will add a lot of value in our financial indicators, with a seamless and transparent real time working environment. That is all from my side. We can now open the floor for the question and answers.

Operator

[Operator Instructions] We take the first question from the line of Mr. Shravan Shah from Dolat Capital.

S
Shravan Shah
analyst

And congratulations to the team for the robust performance for this quarter. So the first question is just to reconfirm the guidance what we have spoken in the last con call. So on the top line front, we are maintaining the INR 5,500 crores, INR 5,600 crores revenue for this year. And in terms of the margin, 16% and order inflow, you mentioned INR 7,000 crores to INR 8,000 crores, but last time, it was INR 8,000 crores to INR 9,000 crores. And in our annual report we mentioned INR 8,000 crores to INR 9,000 crores. So can you just reconfirm the numbers?

R
Rajeev Mishra
executive

Of course, I think as we have already done around 20% this quarter on a year-on-year, we can see this because of the monsoon, early arrival because of this [indiscernible] and that has impacted some of the progress in the project. But definitely, we are all very much focused on that, that we will be touching upon the 22% to 25% progress. That is where we will be reaching up to [indiscernible]. And because the order guidance has been reduced by INR 1,000-odd crores because we have seen that there has been some delay in the awarding of the projects at HAM at few other clients. So that is how we are keeping that to INR 7000 crores to INR 8000 crores. Margins definitely will remain -- likely to be remain intact as we have seen into our numbers. So that seems to be the same range of 15% plus on this.

S
Shravan Shah
analyst

And in terms of the breakup of the revenue last time you said INR 2,000 crores revenue from Ganga Expressway, INR 1,800 crores from existing HAM [technical difficulty] from the new HAM. So if you can also help us with if anything in that number or if it is same, then it is fine.

H
Harendra Singh
executive

It is more or less same because in the quarter, we have done about INR 500 crores on all HAM projects that are majorly 4, 5 HAM projects. And in the project of Ganga Expressway, we have done this INR 475-odd crores coming from the project of Adani Ganga Expressway, other NHAI, EPC and DMRC put together. So we are very much clear on that, whether it's SPV and Ganga Expressway and the other NHAI EPC projects are the major contributors to this particular year revenue.

S
Shravan Shah
analyst

And now on flow front, broadly how much INR 5,000 crores would be from the HAM and in terms of the new other than the road sector, we were looking at close to INR 2,000-odd crores. So will it remain the same?

H
Harendra Singh
executive

Yes. So more or less same because the INR 1,000-odd crores, we have just taken it as a guidance for this year was keeping that at almost 4 months has passed. But then again, it remains the same.

S
Shravan Shah
analyst

And sir, just want to clarify in annual report, we have mentioned that we are looking at [technical difficulty] in 3 years. So just to clarify, so that 3 years starts from --

H
Harendra Singh
executive

Shravan, sorry, I couldn't understand your question. Please repeat it.

S
Shravan Shah
analyst

Just clarify in annual report, we have mentioned INR 10,000 crores revenue.

Operator

I'm sorry, sir, your voice is breaking. You are losing your audio n between?

S
Shravan Shah
analyst

I was saying in annual report, we have mentioned that we want to achieve a INR 10,000 crores revenue over the next 3 years. So I think it's -- these 3 years should start from end of the FY '25 onwards. Otherwise, if -- sorry, sir?

H
Harendra Singh
executive

So this year, it is '24 the running year. We are not considering this year, so it can be post '25, 3 years down the line.

S
Shravan Shah
analyst

Yes. Because otherwise, the CAGR is much higher versus normal what we are talking 20%, 25% revenue growth CAGR. So that's why I just wanted to reconfirm. Secondly, in terms of the appointed date, you said that both this Varanasi, will be getting appointed in October, December, Q3. And for Karnal Ring Road, it moved -- when we -- we are getting the IP appointed date.

H
Harendra Singh
executive

See, Karnal Ring Road, we already -- about to submit our financial closure documents. And by September mid, we will be getting the appointed date. Jharkhand Package 13 it would be a bit early in quarter 3 -- by quarter 3 end. And definitive followed by quarter the Jharkhand Package 10 quarter 4 in January to be precise.

S
Shravan Shah
analyst

For Kanpur Railway Station, it would be by this month, we will be getting the appointed date.

H
Harendra Singh
executive

In the quarter 2 only.

Operator

[Operator Instructions] We take the next question from the line of Mr. Parikshit Kandpal from HDFC Securities.

P
Parikshit Kandpal
analyst

Congratulations on a decent quarter. My question is on the monetization part. So when do you expect joint approvals to come in LTs and as far as approvals in [indiscernible]. And when do you expect the money to come?

H
Harendra Singh
executive

Parikshit your voice is so -- you are not so clear.

P
Parikshit Kandpal
analyst

What stage of approvals or are we for these assets, which have been monetized with KKR. So I think you said that by month end and approvals will come in. So when do you expect the money final inflow to come in?

H
Harendra Singh
executive

See the -- out of 3 projects, which we already have completed that COD wants. So 2 projects have already been sent to their finance department from the operational technical division. Just one project within this week is likely to be sent to them and financial -- finance department hardly take normally 7 to 10 days for issuance of the in-principle approval. So this is one stage 4 stage of NHAI. And post that, the entire formality of -- put together NOC from all the lenders and this again that will be sent to NHAI. So since the big delays rather 1 month delay because of some of the changes at NHAI. But then as we are hoping that not -- if not during the September quarter. But in quarter 1, we will -- say October, we would be getting the funds for these 3 projects.

P
Parikshit Kandpal
analyst

What I was asking when you said there has been quite some delay in NHAI giving approvals or NOC there has been big queue of approval to fill have been given, that is why I was asking this question. Are you able to...

H
Harendra Singh
executive

That was very much on the cards, but because of the recent changes at their -- from the task -- from the position changes, so that will delay, eventually it is not us but was never in the control. But things are moving well on track.

P
Parikshit Kandpal
analyst

Because I was asking this question was that earlier. I mean we have done with KKR in the past, they have faced similar issue and earlier got called off with one of your competitors. So is that in that now that whether the time lines and whether the purpose have become more streamlined in terms of NOCs and approvals coming in from NHAI?

H
Harendra Singh
executive

They are also -- they are putting their total effort on our -- for getting the -- start this on time.

P
Parikshit Kandpal
analyst

Sir, this is my second question is, on the pipeline. So you can help us understand the rest of the year. We need to understand that -- now even L&T was saying that the fourth quarter, will be mostly model code of conduct, and nothing has been happening in terms of awarding. From now on or August onwards you hardly have 4 months left. So how do you think that will end up this year, what is the bid pipeline from different again [indiscernible] again NHAI what is the bid pipeline, railways and also water. So what are we targeting for the rest of the full 5 months.

H
Harendra Singh
executive

Definitely we have 4 months [indiscernible] as we have guided, various times the 1,000-odd kilometer to be awarded this year. So -- but it's not so easy. So we are also keeping that -- our target, announced target that definitely, if they will be -- they are in a position to be able to award even 4,000-odd kilometer. Then we are keeping that at least some INR 4,000 crores to INR 5,000 crores of project coming from NHAI and balance from MSRDC and other sectors.

P
Parikshit Kandpal
analyst

Have you please bid for that Pune Ring Road and have you participated in that tender?

H
Harendra Singh
executive

Sorry.

P
Parikshit Kandpal
analyst

The Pune Ring Road tender have we participated in that tender?

H
Harendra Singh
executive

Yes, we have already applied for the RFQ. And very soon, I think they are going to declare the results of RFQ post where the price that has to be quoted or bided.

P
Parikshit Kandpal
analyst

And for October, November, I think it will be -- so when do you expect the awards to happen?

H
Harendra Singh
executive

Probably by October or say by November, definitely, they are looking to award these projects.

P
Parikshit Kandpal
analyst

And just the last question on the station redevelopment sir. I mean are we looking at that as an opportunity to bid, I mean, so in terms of railway CapEx, so I understand right now we are more on maybe metro will be tracking. So what are the capabilities there and whether in terms of value chain, how are we upgrading ourselves so that we can cover more broader spectrum of awarding from railways.

H
Harendra Singh
executive

Railway business is there, many projects which we have already recently bided. So there are of that nature only where the permanent crafting and team work so does work those kind of works are all included. So they are having a lot many projects in their pipeline, we have in Maharashtra, Gujarat, or the -- in UP also, we have seen those business. So for sure, I think the railway and opportunities are coming in a very significant way.

P
Parikshit Kandpal
analyst

Then the other would be largely related to tracking and also not and maybe metro...

H
Harendra Singh
executive

With the kind of a joint venture, not frequently required joint venture with MOU business, where the -- we are aligned with any of the associates for this track linking, permanent growth.

P
Parikshit Kandpal
analyst

Station redevelopment anything we can do there.

H
Harendra Singh
executive

It's already there. There are many projects in the pipeline.

P
Parikshit Kandpal
analyst

But are we participating in that? And that's the last question are we looking to participate in...

H
Harendra Singh
executive

Yes. We will keep continuing bidding in these kind of situation.

Operator

[Operator Instructions] We take the next question from the line of Mr. Chinmay Kabra from Emkay Global.

C
Chinmay Kabra
analyst

I just wanted to know one thing. In terms of Rewari Bypass, has there been any modification in the contract because there's a percentage of completion, it has changed from Q4 FY '23 to Q1 FY '24, what I see right now.

H
Harendra Singh
executive

What you are saying if 96% already has been completed.

C
Chinmay Kabra
analyst

Yes. So I mean, what I was -- I am able to understand was 94% is what was showing in Q4 FY '23. And I think if I'm not wrong in Q1 FY '24, it is showing 86.5%, sir, so just...

H
Harendra Singh
executive

Yes, there is some error. I think there is one more -- 2 more errors are there because of the -- I think they are getting it corrected because in 2 of the projects of this RV and the last 4 there is like Kanpur Railway Station the percentage that has been quoted, this is -- are wrongly -- now it is being corrected.

C
Chinmay Kabra
analyst

I mean -- so yes, so there's no change in the contract or anything like that, right?

H
Harendra Singh
executive

Yes, yes. Correct.

C
Chinmay Kabra
analyst

And other than this, sir, just wanted your perspective on -- again, I just wanted to reconfirm the guidance that the FY '24 revenue, which we have said INR 5,500 crores to INR 5,600 crores and the EBITDA margin of 16%. I just wanted to reconfirm the order inflow guidance which you have given, sir, if you could please state that again?

H
Harendra Singh
executive

Yes. So INR 7,000 crores to INR 8,000-odd crores we are targeting to add this year.

C
Chinmay Kabra
analyst

And of this, how much is -- are we expecting to be from the other projects in terms of railways and metros?

H
Harendra Singh
executive

We are looking at about INR 2,000-odd crores needs to be added from these other sectors rather than highways.

C
Chinmay Kabra
analyst

But I mean, since we are being conservative and we are thinking -- I mean we are just assuming that NHAI might just do 6,000 kilometers to 4,000 kilometers. Are we still confident in order to achieve these order inflow targets that we have set?

H
Harendra Singh
executive

Yes, of course, I think there's not a big challenge this -- that we also have seen in the last 2 years, what we have planned and roughly, roughly, we will be able to achieve that on the God is always there, so we would be able to add this number.

Operator

We take the next question from the line of Ms. Ankita Shah from Elara Capital.

A
Ankita Shah
analyst

Sir, I wanted to understand about the working capital I think on account of working capital requirement has increased. So is this on account certain projects or reason for the increase in working capital requirement?

H
Harendra Singh
executive

This year before the working capital base or net working capital requirements?

A
Ankita Shah
analyst

Requirement. If I look at the debt breakup the requirement on the working capital has gone up?

H
Harendra Singh
executive

That time I was clear about it. So the working capital with say utilization has gone high at this absolute, as we are talking of 30th of June, but it then between -- it is now coming back to the same range of INR 500 crores. This is because of the reason, specific reason that the payments which we are likely to get from SPVs and say even Adani and one more NHAI client. So it got remade for a few days, just 2, 3 days. So that's why it's very -- for just a week or 10 days time it shoots up to that level. But otherwise it would be in the same range only.

A
Ankita Shah
analyst

And sir, second question is on the Bhanupalli-Bilaspur. Was it the margins that you can cause it -- and how are the payments?

H
Harendra Singh
executive

The payments definitely as RVNL as a public sector undertaking this payments are likely to be on -- very much on track only. There's no issue as much as far as RVNL metro or railway projects are concerned. But definitely, the margins which we have put -- we have kept in sight estimate at about, say, 14%. So that would -- that are likely to be there.

Operator

The next question is from the line of Mr. Jiten Rushi from Axis Capital.

J
Jiten Rushi
analyst

Sir, first of all, can you give us the breakup of equity required in next 3 years? As you said that in FY '24 the requirement is almost INR 407.4 crores what would be for FY '25 and '26.

H
Harendra Singh
executive

The equity total requirement, which is around INR 1,592 crores, INR 758.7 crores already invested till June '23. So that the current year requirement would be in the range of INR 407-odd crores once we would be getting the solid data around the project and the balance requirement for all 5 running projects. So that is one and FY '25 it is estimated about INR 268 crores and FY '26, it is INR 158 crores.

J
Jiten Rushi
analyst

You said that the land available for the Karnal project is 86%, while for the Varanasi Ranchi project for both the project is we have got 50%, right?

H
Harendra Singh
executive

No, that is turning a bit ahead because they are -- they have the forest area -- there the majority part is forest. So in project term it is a bit low.

J
Jiten Rushi
analyst

So you said 50% for Package 13 and not for Package 10, right?

H
Harendra Singh
executive

Yes. Yes. Yes.

J
Jiten Rushi
analyst

So how much Package 10 will be less than 50%. And sir, on the current outstanding bid pipeline. So can you highlight -- throw some light on the current outstanding bid pipeline? And when are these standards going to open and which sector, if you can break up?

H
Harendra Singh
executive

Of course, I think as we have just discussed about MSRDC has got above INR 45,000-odd crores, where we would be looking at about say where we are qualified for INR 30,000-odd crores -- this is one I think strong one. And for sure, active projects that are on the portal, where the bid pipeline are showing about INR 45,000 crores. And the sooner I think more of the projects which are at the GPR or the approval is yet awaited from their, say, respective competent authority, they would be there. So these are the 2 major ones. And then apart from NHAI and these projects, there are lot many projects which we have seen in the railways, which we are continuously bidding in metro even we are looking for it.

J
Jiten Rushi
analyst

Sir, my question was any outstanding bid right now, which you have participated and you're awaiting the total...

H
Harendra Singh
executive

INR 5,600 crores.

J
Jiten Rushi
analyst

That should be in road?

H
Harendra Singh
executive

Road is about INR 3,500 crores and the rest is in railways.

J
Jiten Rushi
analyst

So this should open by end of this month?

H
Harendra Singh
executive

Probably by this month August end.

J
Jiten Rushi
analyst

And sir, can you just throw some light on the revenue breakup. So as you said that there was a miss in revenue as against your internal target for the Q1 because of the monsoons. But you are very optimistic that we should be able to achieve the full year event target of INR 5,500 crores to INR 5,600 crores. So what kind of revenue contribution we are expecting from the Adani project like you had guided for around INR 2,000 crores at the start of the year and probably from the HAM projects.

H
Harendra Singh
executive

We already believed during the annual con call, that around INR 2,000 crores would be coming from this project of Adani, roughly INR 2,010 crores and balance majorly Raipur, Visakhapatnam projects and projects put together, that will be about INR 1,800-odd crores coming from those projects. So this is our other EPC of UER, NHAI and Tumkur and then that should put together would be the total.

J
Jiten Rushi
analyst

My last question would be a bookkeeping question. If you can give me the mobilization outstanding mobilization advances, retention money and bill revenue that created in the inventory possible.

H
Harendra Singh
executive

Yes, sure. You can see the Bhubaneswar one is about INR 285 crores.

J
Jiten Rushi
analyst

INR 285 crores.

H
Harendra Singh
executive

Is reduced by INR 70-odd crores from the last quarter. And the debtors have gone out as early as explained that we have received a significant amount in first week of July only. So that is around, say, INR 750 crores plus INR 225 crores as retention and deposits. So put together INR 978 crores.

J
Jiten Rushi
analyst

So you said INR 750 crores attaching, how much the INR 228 crores?

H
Harendra Singh
executive

INR 750 crores and INR 228 crores correct.

J
Jiten Rushi
analyst

INR 220 crores. And what will be the inventory and unbilled revenue?

H
Harendra Singh
executive

Maybe it's around INR 256 crores.

J
Jiten Rushi
analyst

And unbilled?

H
Harendra Singh
executive

Unbilled. Almost INR 500 crores --something. As it was last year, last quarter...

J
Jiten Rushi
analyst

CapEx guidance, if you can throw some light on the...

Operator

[Operator Instructions] We take the next question from the line of Mr. Aman Soni from Prudent Equity.

A
Aman Soni
analyst

So sir, my first question would be on the asset monetization. So in the previous con call, you mentioned that there will be a reduction in debt at about INR 350 crores. So do you have any different amount by in the next 1 to 2 quarters, how much reduction in debt are you planning?

H
Harendra Singh
executive

I think what we have discussed last time that there would be a likely reduction in the debt because every quarter there is an outflow of about INR 55 crores to INR 56 crores. The entity due payment and term loan payment is there. So it is likely that INR 200-odd crores would be reduced by this year-end and then likely there should be INR 70-odd crores would be added because of the new CapEx during the year. So put together, we would be in the range of INR 425 crores at the year-end.

J
Jiten Rushi
analyst

So this will be a reduction of INR 400 crores to INR 450 crores.

H
Harendra Singh
executive

INR 425 crores, INR 450 crores. That range would be there for the year-end. So we see anything from the monetization.

J
Jiten Rushi
analyst

This is excluding the monetization?

H
Harendra Singh
executive

That we have not considered.

J
Jiten Rushi
analyst

But even if we, let's say, consider that obviously deal concludes then also there will be a certain portion of and then that will go off. So what will be the consolidated number?

H
Harendra Singh
executive

Sorry, I couldn't get your question.

J
Jiten Rushi
analyst

So you mentioned that this reduction of INR 400 crores of debt will be excluding the asset monetization, right?

H
Harendra Singh
executive

Correct.

J
Jiten Rushi
analyst

So if we consider the debt reduction from the asset monetization side after that what will the reduction in debt?

H
Harendra Singh
executive

We have not factored here as of now.

J
Jiten Rushi
analyst

So my next question will be on the Varanasi Ranchi project. So there are certain news reports like going on regarding certain issues with the land procurement. So is there work commencing this project? And can we expect certain kind of revenue in the upcoming quarters from this? Or is there any kind of difficulties?

H
Harendra Singh
executive

Which project you are talking about?

J
Jiten Rushi
analyst

Varanasi.

H
Harendra Singh
executive

Varanasi Kolkata is already on fast track. The land possession is, which I am talking of about 50% is the last question. Varanasi with the 2, 3 months or 4, 5 months, the land of Package #13 would be first handed over and then before that 10.

J
Jiten Rushi
analyst

So from the second quarter, a certain amount of revenue could come in from this project?

H
Harendra Singh
executive

The third quarter or 4 quarters, some portion of the revenue is likely to come from this projects. We are expecting quarters 3 and 4 the revenue will be coming from this Karnal Munak Road.

Operator

[Operator Instructions] The next question from the line of Mr. Sarvesh Gupta from Maximal Capital.

S
Sarvesh Gupta
analyst

Sir, on this order inflow guidance of INR 7,000 crores to INR 8,000 crores. Now I think till now, we haven't received much this financial year and then Q4 is also most likely going to be a washout. So you're saying around INR 5,500 crores is the outstanding bid, which is expected to open this month, assuming that we win maybe INR 1,000 crores, INR 2,000 crores from here, what is the remaining sort of a pipeline that is there for you to win further bids in the coming 5 months?

H
Harendra Singh
executive

So this pipeline as per NHAI and MSRDC and other railway or metro projects, it's already there, this is almost a good number. It's almost INR 1,00,000 crores, INR 50,000-odd crores is there. Out of that we are targeting to bid around INR 90,000-odd crores. So there, we are looking into the bid strike ratio, if the historical path we have seen that we will be able to make out at least, say, 7% to 8% at the bid strike issued then we would be able to hit that number.

S
Sarvesh Gupta
analyst

And this is -- these are the bids which are expected to be done by end of this calendar year, itself?

H
Harendra Singh
executive

Yes, of course, by the year-end, we are expecting the quarter 2, 3 and 4 out of these 8 months, we are expecting to add this.

S
Sarvesh Gupta
analyst

And sir, on the Ganga Expressway, any further updates in terms of your payments in the project sort of a thing? Is everything on track? Or are there any...

H
Harendra Singh
executive

Since you have seen that we have already exhibited INR 475-odd crores during the quarter, which is a runrate, our runrate is about INR 160 crores, INR 170-odd crores a year on a formal basis. So this is alone, we are getting the payments well on time. So just over 45 days macro timeline of the payment.

S
Sarvesh Gupta
analyst

Are the new gross lot that we had added, which was quite significant in terms of the construction equipment -- so is that helping us to sort of improve our margins because of lowering our dependence on outside vendors in terms of your EBITDA margin because now some of the operational costs would have been converted to CapEx related costs.

H
Harendra Singh
executive

Yes, to some extent, it is helping, but not to the larger extent. But definitely, these are all the internal strategical backward integration and forward integration, which we have done some operational efficiency improvement through technology. So this is all helping us.

S
Sarvesh Gupta
analyst

But we are able to do a decent utilization on these equipment?

H
Harendra Singh
executive

Yes, definitely. These are all put to use, and we are getting the most benefit. Most of the benefits are coming for that angle only.

Operator

[Operator Instructions] We take the next question from the line of [ Ms. Akshita Dev from Vivo Commercial ].

U
Unknown Analyst

Just want to know the margin guidance that was given was around 15%. And the company has been able to do roughly 19% to 20% EBITDA in the last few quarters. Is there a [technical difficulty].

H
Harendra Singh
executive

I couldn't understand your question. What you're saying is...

U
Unknown Analyst

The margin guidance that you are taking for the upcoming year. The top line, INR 5,500 crores, INR 6,000 crores top line expectations [indiscernible] with a margin.

H
Harendra Singh
executive

Again, I'm sorry.

Operator

[Operator Instructions]

U
Unknown Analyst

So the top line expectation for this year is roughly INR 5,500 crores to INR 6,000 crores, right, with 16% EBITDA margin guidance?

H
Harendra Singh
executive

It's roughly INR 5,550 crores should be very specific.

U
Unknown Analyst

Right. And with the 16% margin guidance.

H
Harendra Singh
executive

Correct.

U
Unknown Analyst

So is there a reason that we're expecting a dip in margin because you've been able to do roughly 20% consistently for the last few years.

H
Harendra Singh
executive

So I think it doesn't matter, margin with respect to the top line. So all the deployment of the resources, the efficiency, operational efficiency design. So put together or everything matters, hardly depends upon the top line, INR 5,000 crores or INR 6,000 crores or INR 7,000 crores. We are keeping our eye focused that we should be aiming at the whole project where the margins are included and as well as the decent growth in the top line can be maintained as a part of our sustainability.

U
Unknown Analyst

So do you expect the current margins that you received in this quarter as they were sustainable for the rest of the year, going forward?

H
Harendra Singh
executive

Yes, of course.

Operator

[Operator Instructions] We take the next question from the line of [ Mr. Ashish from JM Financial ].

U
Unknown Analyst

Just one question. Has there been any change in scope or increase in scope in any of the HAM or the EPC role projects that you are executing?

H
Harendra Singh
executive

Yes, definitely, there has been some changes in INR 200 crores of variation orders has been issued in 2, 3 projects.

U
Unknown Analyst

Would it be possible to just break down this INR 200 crores into the individual projects, even approximate number should be, okay.

H
Harendra Singh
executive

Readily, I'm not having this breakup of INR 200 crores all the NHAI SPV projects, which is like that.

Operator

The next question is from the line of Mr. Uttam Kumar Srimal from Axis Securities Limited.

U
Uttam Srimal
analyst

And congratulation on a good set of numbers. Sir, what is our CapEx guidance for FY '24 and '25.

H
Harendra Singh
executive

'24, '25.

U
Uttam Srimal
analyst

Yes. CapEx guidance for FY '24.

H
Harendra Singh
executive

Yes, we are expecting about, say, 20% year-on-year. So roughly, it would be about INR 5,500 crores that one.

U
Uttam Srimal
analyst

No, sir, This is CapEx guidance, I am asking.

H
Harendra Singh
executive

CapEx, roughly, it would be in the range of INR 100-odd crores.

U
Uttam Srimal
analyst

For FY '24 and '25, both or the same number will do.

H
Harendra Singh
executive

Yes. Sorry?

U
Uttam Srimal
analyst

For FY '25 also only INR 100 crores or more than that?

H
Harendra Singh
executive

No, it would be like this or same.

Operator

We take the next question from the line of Mr. Shravan Shah from Dolat Capital.

S
Shravan Shah
analyst

What is the trade payable as on June?

H
Harendra Singh
executive

Trade payable is roughly around INR 680 crores.

S
Shravan Shah
analyst

And you mentioned, sir, retention money is INR 228 crores. So in March, it was INR 111 crores. So any specific reason...

H
Harendra Singh
executive

This Adani projects do have the retention money recovery, which is, say, a significant high number is there. So -- but then again, we would be able to get this back through a replacement through bank guarantee.

S
Shravan Shah
analyst

So this INR 400 crores plus execution what we have done. So there is INR 110 crores, INR 120-odd crores kind of a retention money. Is it my understanding, right?

H
Harendra Singh
executive

The retention and finance deposit, there are 2 kind of deposits. So earlier in last year March number, you would -- it was roughly around INR 170-odd crores, INR 178 crores rather. And now it has gone high INR 50-odd crores, which is within this quarter only.

S
Shravan Shah
analyst

And you mentioned because of 2, 3 days, this working capital has increased. So the debt number, which is INR 665-odd crores as on June. So now this should have come back to a INR 450-odd crores.

H
Harendra Singh
executive

Is again coming back to normal. It's roughly about INR 450 crores, INR 460 crores. And by the year-end, we would be having that say, guidance number is INR 425 crores to INR 450 crores not more than that.

S
Shravan Shah
analyst

Sorry, sir, I didn't get. Can you -- if you can repeat the same thing.

H
Harendra Singh
executive

So in the -- starting of June, it was being utilized on the higher number. But ultimately it is now coming back to the normal, and it is in the range of about INR 425 crores, INR 470 crores. That is there.

S
Shravan Shah
analyst

Sir, again, on coming back to one on the bid pipeline grow is bid for INR 90,000-odd crores kind of a project. But any specific, if you can -- if you want to highlight in next 2, 3 months? Is there any sign that this much we want to? Because I'm just trying to understand that post the code of conduct, is there a possibility in terms of awarding goals are -- slows down?

H
Harendra Singh
executive

So till February '24, I don't see there's a big challenge, but they are also having the big clarity. So by the time the model code of conduct is to be introduced or implemented so that all orders, they are having ample number of bid pipeline readily and with a few changes in the -- at the NHAI level, you can all understand, but those could not happen that is the reason. But we are quite hopeful and that will be done.

S
Shravan Shah
analyst

And sir, any idea in terms of Bharatmala Phase II where it is when it's likely to be...

H
Harendra Singh
executive

There is no update as of now, very recently, there is no update.

Operator

[Operator Instructions] We'll take the next question from the line of Ash Shah from Elara Capital.

A
Ash Shah
analyst

First question would be how much amount have we invested in these 4 SPV that we are planning to sell and how much are we going to receive in FY '24 in total?

H
Harendra Singh
executive

This is also the INR 343 crores as invested into these SPV and post monetization, it is INR 551 crores.

A
Ash Shah
analyst

But that will also include -- that is on the EV part, but how much would be the equity value in the INR 531 crores?

H
Harendra Singh
executive

There's altogether equity only.

A
Ash Shah
analyst

There is altogether equity.

H
Harendra Singh
executive

Centralized value is roughly around INR 1,300 crores.

A
Ash Shah
analyst

Second question would be, so in our annual report also, we have guided for 20% to 25% from the non-road sector. So do you see any margin contraction in the next 2 to 3 years as we see our non-road order book increase?

H
Harendra Singh
executive

We are very selective in taking on the call as far as bidding the projects part -- apart from the highway. So we are keeping that intake. So we would not be doing very desperately -- that is why we are keeping 24% for 3 years road map that we're gradually venturing taking the projects apart from the highway. So I don't see much of a challenge maintaining the same margins.

A
Ash Shah
analyst

Also last question would be, can you give the breakup of revenue for this quarter, like price variation and operate O&M revenue.

H
Harendra Singh
executive

Price escalation is INR 71 crores -- if you can see the numbers differently SPV, they have contributed INR 500 crores, running 2 projects, INR 494 crores. NHAI all put together at roughly around INR 225 crores. And rest of our BMRC and...

Operator

We take the next follow-up question from the line of Jiten Rushi from Axis Capital.

J
Jiten Rushi
analyst

My question is more on the competitive engine that you said you see most of these payers are unable to win projects in Q1. So what kind of competition intensity can build up in the next 3 to 6 months? And how are we placed -- do we -- if at all, we are not able to get any projects in next 2 to 3 months, do you see any kind of a desperation from our side where we try to grab inflows at a lower margin, something -- can you throw some light on that?

H
Harendra Singh
executive

No, I don't see much of a challenge. Definitely, there are many other competitor contractor. They are full of their appetite the projects -- they're having a good number of projects. So we normally have seen the correction in last few months, we have seen that a lot -- a number of bidders as they were as high as 15, 20 or even in EPC 35,40. EPC definitely there is not much how much of an improvement is there and not visible even. But in -- hope we have seen that 7, 8 bidders are there ideally. So we believe that is all competitive intensity, which was at a very high cost cutting aggression was high, but then it's not ruled out. We expect that -- without compromising and without looking into that margin shrinkage, we would be able to add this number of projects of -- just about INR 5,000-odd crores we have.

J
Jiten Rushi
analyst

So maybe for the EPC, we still see 35, 40 at hand at this time we will do it. Right?

H
Harendra Singh
executive

Yes.

J
Jiten Rushi
analyst

Sir, on the road inflow, which you are targeting on INR 4,000 crores to INR 5,000 crores, this should be mostly HAM or we will get the mix of EPC also? What is your thought on it?

H
Harendra Singh
executive

[indiscernible] is INR 4,000-odd crores you are looking from the HAM projects in -- that range from EPC, balance we are looking at from the...

Operator

Ladies and gentlemen, that was the last question for the day. I would now like to hand the conference over to the management for closing comments.

H
Harendra Singh
executive

Yes. Thank you, everyone, for bringing their expertise and experience around the table. We appreciate everyone joining us today on the call. I hope that we have addressed your all questions. If you are any other further inquiries, please do not hesitate to reach out to our IR advisors, Go India Advisors. Thank you for the participation. Thank you.

Operator

Thank you, sir. On behalf of Go India Advisors, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.